The Purchase Order replaces EP2980103 and carries forward remaining encumbered balances for Line 8… and 4 more items
State & local contract award Virginia Awarded
- Contract number
- PO04358893-V3
- Awardee
- Cannon Design
- Contracting organization
- Old Dominion University
- Cumulative value
- $507,059
About this award
Cannon Design has been awarded a contract by Old Dominion University in Virginia for professional architectural and engineering (A/E) design and construction administration services related to the University's New Health Sciences Building. The contract, designated PO04358893-V3, was awarded on July 27, 2026, with a cumulative value of $507,059.43. Services are being delivered to Willie Spencer at Old Dominion University (757-683-4814) in accordance with the CO-3 Contract and Memorandum of Understanding dated February 8, 2019.
The contract encompasses the original scope of professional A/E design and construction administration services, including remaining encumbered balances from the superseded purchase order EP2980103. Additionally, the contract incorporates three change orders executed subsequent to the original agreement. Change Order #7 (executed April 26, 2023) covers additional design services for utility updates on Monarch Way to facilitate permit approval from the City of Norfolk. Change Order #8 (executed June 17, 2025) addresses costs associated with Leadership in Energy and Environmental Design (LEED) building certification and building plaque. Change Order #9 (executed June 17, 2025) provides for extended construction administration services. The cumulative contract value of $507,059.43 reflects all original services and change order additions.
Line items
| Item | Total |
|---|---|
| The Purchase Order replaces EP2980103 and carries forward remaining encumbered balances for Line 8 for Professional A/E Design and Construction Administration Services for the University's New Health Sciences Building. All Services and Associated Costs shall be Provided in Accordance with the… | $56,670.00 |
| The Purchase Order replaces EP2980103 and carries forward remaining encumbered balances for Line 12 for Professional A/E Design and Construction Administration Services for the University's New Health Sciences Building. All Services and Associated Costs shall be Provided in Accordance with the… | $163,793.00 |
| CHANGE ORDER #8 - This Changer Order #8 Reflects Additional Costs to Cover LEED Building Certification and Building Plaque. All Services and Associated Costs shall be Provided in Accordance with the Attached CO-11ae Change Order Form Executed June 17, 2025. | $37,621.00 |
| CHANGE ORDER #9 - This Changer Order #9 Reflects Additional Costs to Cover Extended Construction Administration Services All Services and Associated Costs shall be Provided in Accordance with the Attached CO-11ae Change Order Form Executed June 17, 2025. | $198,834.00 |
| CHANGE ORDER #7 - This Changer Order #7 Reflects Additional Design Services Requested by the City of Norfolk to Update the Utilities on Monarch Way in Order to Issue Approved Permit for the New Health Sciences Building. All Services and Associated Costs shall be Provided in Accordance with the… | $50,140.00 |
Award details come from logi.cgieva.com. Updated .
Quick answers
Who was awarded contract PO04358893-V3?
Contract PO04358893-V3 was awarded to Cannon Design by Old Dominion University in Virginia on July 27, 2026.
How much is contract PO04358893-V3 worth?
Its cumulative value is $507,059.
On GovTribe
See this award's full record
- Every line item and file
- The contract it was ordered under and its other orders
- Similar state and local awards and opportunities
- Ask GovTribe AI about this award