26 crushed stone and 30 more items

Virginia Awarded

Contract number
A501_0001317430-V4
Awardee
Rockydale Mundy Quarries
Contracting organization
Virginia Department of Transportation
Cumulative value
$25,917

About this award

Rockydale Mundy Quarries was awarded a contract by the Virginia Department of Transportation on August 20, 2026, with a cumulative value of $25,917.27. The contract encompasses the delivery of various aggregate and stone materials to David Ernest Diaz. Materials include multiple classifications of crushed stone, riprap, select materials, and sand products, all measured and billed in short tons. Specific line items with recorded quantities and unit pricing include #21A stone (29 short tons at $9.80 per ton), #26 crushed stone (1,925 short tons at $9.65 per ton), select material type 1 CBR 30 (523 short tons at $9.65 per ton), riprap class I (45 short tons at $18.25 per ton), riprap class II (35 short tons at $19.80 per ton), riprap class A1 (18 short tons at $16.00 per ton), and select material type III RDC (23 short tons at $7.35 per ton).

The contract includes additional line items for stone dust, screening, modified stone, surge stone-rockfill, and gabion materials, though quantities and unit pricing were not specified for these items. All materials are designated for delivery to the same recipient, indicating consolidation of aggregate sourcing for Virginia Department of Transportation projects. The contract represents a materials supply arrangement typical of transportation infrastructure maintenance and construction support, with pricing structures reflecting standard aggregate commodity rates.

Line items

Item Total
1 stone —
2 stone —
3 stone —
5 stone —
8P grade b stone —
8 stone —
9 stone —
10 stone —
10 stone dust/screenings —
21A stone… 29 Short Ton × $9.80 $284.20
21B stone… —
24 crushed stone —
25 crushed stone —
26 crushed stone 1,925 Short Ton × $9.65 $18,576.25
56 stone —
26 modified stone —
Select material type 1 - CBR 30 523 Short Ton × $9.65 $5,046.95
57 stone —
68 stone —
78 stone —
357 stone… —
RIP RAP class i 45 Short Ton × $18.25 $821.25
RIP RAP class II 35 Short Ton × $19.80 $693.00
RIP RAP class III —
Select material OGB —
RIP RAP class A1 18 Short Ton × $16.00 $288.00
Surge stone - rockfill —
Gabion —
Select material type III - RDC 23 Short Ton × $7.35 $169.05
Grade a sand —
Grade b sand —
Show all 31

Award details come from logi.cgieva.com. Updated .

Quick answers

Who was awarded contract A501_0001317430-V4?

Contract A501_0001317430-V4 was awarded to Rockydale Mundy Quarries by Virginia Department of Transportation on August 20, 2026.

How much is contract A501_0001317430-V4 worth?

Its cumulative value is $25,917.

Is contract A501_0001317430-V4 an order under another contract?

Yes. It was placed under contract 0000000000000000000053469 LINE.

On GovTribe

See this award's full record

  • Every line item and file
  • The contract it was ordered under and its other orders
  • Similar state and local awards and opportunities
  • Ask GovTribe AI about this award