Selective Spot Spraying Weed and Vegetation per acre and 23 more items
Virginia Awarded
- Contract number
- A501_0001319056-V6
- Awardee
- AMC Specialty Inc
- Contracting organization
- Virginia Department of Transportation
- Cumulative value
- $1,343,211
About this award
AMC Specialty Inc. was awarded a contract by the Virginia Department of Transportation with an award date of September 29, 2026. The cumulative contract value totals $1,343,211.11. The contract is identified as VA|0000000000000000000050485 LINE|A501_0001319056-V6. Specific information regarding the period of performance, annual value, and places of performance is not available in the materials provided.
The materials supplied do not contain sufficient detail to identify the specific products and/or services being delivered under this contract award. To obtain comprehensive information regarding contract scope, deliverables, performance locations, and performance period, additional contract documentation should be consulted.
Line items
| Item | Total |
|---|---|
| Selective Spot Spraying Weed and Vegetation per acre | $31,187.00 |
| Guardrail Spraying - 2 Lane Primary - VEGETATION MANAGEMENT GUARDRAIL, 2LN PRIMARY, INCL LABOR, CHEM. EQUIP, INCIDENTALS | $170,950.50 |
| Brush Spraying- 4 Lane Primary per acre | $86,663.20 |
| Brush Spraying -2 lane primary per acre | $345,198.00 |
| Brush Spraying Secondary routes per acre | $83,917.08 |
| Broadleaf Spraying- 4 Lane Primary per acre | $25,906.50 |
| Broadleaf Spraying- 2 Lane Primary per acre | $175,286.85 |
| Facility Lot Spraying per acre | $29,977.00 |
| SWM Facility Spraying per acre | $38,084.40 |
| Selective Grass Spraying - 4 Lane Primary per acre | $33,607.00 |
| Selective Grass Spraying- 2 lane primary per acre | $40,344.75 |
| 2 Member Basal Crew per each | $3,960.25 |
| Turf Grass Regulator Spraying-4 Lane Primary per acre | $6,710.50 |
| Edging or Joint Spraying per shoulder mile | $44,883.00 |
| Turf Grass Regulator Spraying -2 Lane Primary per acre | $8,223.00 |
| Turf Grass Regulator & Broadleaf Spraying - 4 lane primary per acre | $10,670.75 |
| Turf Grass Regulator & Broadleaf Spraying - 2 lane primary per acre | $8,828.00 |
| Guardrail Spraying - 4 Lane Primary per shoulder mile | $147,003.03 |
| TMA Truck W/Arrow Board,2 Ton w/ Flashing Amber Arrow B or C per hour | $1,705.10 |
| Truck Mounted Arrow Board Type B or C per hour | $1,089.10 |
| Trailer Mounted Arrow Board Type B or C per hour | $836.00 |
| Truck, 4-WD, 3/4 Ton Full size per hour | $1,375.10 |
| Pre-Emergent per Acre | $3,795.00 |
| Pre-Emergent per SMI | $43,010.00 |
Show all 24
Award details come from logi.cgieva.com. Updated .
Quick answers
Who was awarded contract A501_0001319056-V6?
Contract A501_0001319056-V6 was awarded to AMC Specialty Inc by Virginia Department of Transportation on September 29, 2026.
How much is contract A501_0001319056-V6 worth?
Its cumulative value is $1,343,211.
Is contract A501_0001319056-V6 an order under another contract?
Yes. It was placed under contract 0000000000000000000050485 LINE.
On GovTribe
See this award's full record
- Every line item and file
- The contract it was ordered under and its other orders
- Similar state and local awards and opportunities
- Ask GovTribe AI about this award