MATOC -- construction in support of joint base lewis-mcchord (JBLM) and its sub-installations (yakima training center, yakima, WA; fort worden cemetery, port townsend, WA) and other customers…

Ended Indefinite Delivery Contract Awarded Last action

Contract number
W912DW14D1003
Awardee
Awarding agency
Task orders
20 $40,016,189 obligated

Award facts

Combined order value
  • $40,016,189 Current, with exercised options
  • $42,162,929 Potential, with all options
Last date to order 100% complete
IDV ceiling 40% used
$100,000,000.00
Award type
Multiple award
Who can order
Only the awarding agency
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 27 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Legislative mandates

Award details come from SAM.gov/FPDS.

Description

MATOC -- construction in support of joint base lewis-mcchord (JBLM) and its sub-installations (yakima training center, yakima, WA; fort worden cemetery, port townsend, WA) and other customers supported by the seattle district, corps of engineers, to include renovations, repairs, upgrades, or alterations to building or plant structural systems, mechanical systems, HVAC systems, fire suppression systems, fire alarm systems, electrical systems, communication line systems, renovations, repairs, upgrades, or alterations to infrastructure projects, such as roadways, airfields, underground utilities, overhead utilities, electrical distribution systems, minor "new" construction, to include pre-engineered structures or minor building expansions.

Task orders

Task order Ordering agency Obligated Awarded
RPR parking lot at waller hall W912DW18F2006 ENDIST Seattle (USACE) $4,670,172
Sustained airborne training facility W912DW17F2090 ENDIST Seattle (USACE) $644,463
Repair work items, building J00691 W912DW17F2068 ENDIST Seattle (USACE) $3,042,415
Youth center repair work ('k') W912DW17F2022 ENDIST Seattle (USACE) $4,376,574
Repair AC waterlines west of gaaf, JBLM, WA 0017 ENDIST Seattle (USACE) $2,078,241
RPR 12",16",18" C905 water lines 0016 ENDIST Seattle (USACE) $2,672,507
Repair failed stormwater systems mcchord 0014 ENDIST Seattle (USACE) $739,768
Repair fire suppression bldg 301, 304,&343 JBLM, WA. 0015 ENDIST Seattle (USACE) $2,730,868
Repair AC water main from main gate to madigan gate, JBLM. 0010 ENDIST Seattle (USACE) $3,718,059
Repair lincoln well 31 0009 ENDIST Seattle (USACE) $913,927
Repair failed sewer systems, mcchord 0012 ENDIST Seattle (USACE) $241,890
Repair exterior of building J00100 at mcchord field 0011 ENDIST Seattle (USACE) $1,643,780
Clean and regrout brick walls various bldgs 0008 ENDIST Seattle (USACE) $1,124,408
Repair sheridan fitness center, bldg 3759, JBLM WA 0007 ENDIST Seattle (USACE) $1,827,144
RPR 36" drainage line 0006 ENDIST Seattle (USACE) $1,242,857
Retrofitting of non-compliant wet wells 0005 ENDIST Seattle (USACE) $519,903
The purpose of this task order is to replace the HVAC systems for building 707. 0004 ENDIST Seattle (USACE) $956,706
Task order for replace fire suppression and fire alarm systems in bldg J01422, JBLM 0003 ENDIST Seattle (USACE) $3,830,293
Construct well #28 0002 ENDIST Seattle (USACE) $1,320,155
Task order award for project entitled, "replace HVAC building 2400, phase II, JBLM, WA 0001 ENDIST Seattle (USACE) $1,722,060
Show all 20

Transactions

Action Obligated Date
Exercise an Option P00007 · Exercise option period four $0
Change Order P00006 · Revision of far clauses 52.225-9, 52.225-11, and 52.225-11 ALT 1. $0
Exercise an Option P00005 · The purpose of this modification is to exercise option period three of the contract. $0
Other Administrative Action P00004 · Corrections to davis bacon wage rates $0
Exercise an Option P00003 · Exercise of option period two $0
Exercise an Option P00002 · $100M MATOC exercise option one-general construction at JBLM and sub-installations. $0
Other Administrative Action P00001 · $100M MATOC - base period - minimum guarantee DE-obligation $0
Original award $0

Quick answers

Who was awarded contract W912DW14D1003?

W912DW14D1003 was awarded to Pease Construction, Inc. by ENDIST Seattle (US Army Corps of Engineers) on April 25, 2014.

How much is contract W912DW14D1003 worth?

Orders under W912DW14D1003 have obligated $40,016,189. Their combined potential value, with all options, is $42,162,929. W912DW14D1003's own ceiling is $100,000,000.

How many orders have been placed under contract W912DW14D1003?

20 orders have been placed under W912DW14D1003, the latest on November 16, 2017.

Who can order from contract W912DW14D1003?

W912DW14D1003 is a multiple award indefinite delivery contract. Only the awarding agency can place orders on it.

Was contract W912DW14D1003 competed?

The extent of competition for W912DW14D1003 was full and open competition after exclusion of sources. The government received 27 offers. It was set aside: Total Small Business.

On GovTribe

See this IDV's full record

  • Every order and transaction
  • The awardee's other awards and teaming partners
  • Similar IDVs and recompete opportunities
  • Ask GovTribe AI about this IDV