Recovery - pine creek work center water system improvements. This project involves plumbing and valves to convert two water tanks for independent operation, installation of a pressure transducer…
Ended Indefinite Delivery Contract Awarded Last action
- Contract number
- AG0489C100328
- Awardee
-
P C R Inc. UEI MQ83JARVEUY1
- Awarding agency
-
Operations Center Northwest
Economic Recovery Operations, Department of Agriculture
- Task orders
- 0
Award facts
- Opportunity
-
- AG0489S100443 Solicitation number
- Pine Creek Water System Upgrade Award Notice · Posted Apr 7, 2010
- Last date to order 100% complete
- IDV ceiling
- $254,921.92
- Award type
- Single award
- Who can order
- Only the awarding agency
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- PSC
- Y119 Construct/Other Admin & Svcs Bldgs
- Set-aside
- Total Small Business
- Competition
- Full and Open Competition after exclusion of sources · 2 offers Negotiated Proposal / Quote
- Pricing
- Firm Fixed Price
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
Award details come from SAM.gov/FPDS.
About this IDV
This indefinite delivery contract (IDC) was awarded by the U.S. Forest Service, a civilian federal agency, to the small business P C R Inc. for water system improvements at the Pine Creek Work Center. The $254,921.92 contract involves plumbing and valve work to convert two water tanks for independent operation, installation of a pressure transducer well pump control system and remote water tank level monitor, reconstruction of an existing well house including increasing the well casing height and routing the well discharge, and miscellaneous distribution system work. This contract was funded through the American Recovery and Reinvestment Act (ARRA) and has a period of performance ending on September 26, 2011. The work is to be performed at the Pine Creek Work Center location.
Description
Recovery - pine creek work center water system improvements. This project involves plumbing and valves to convert two water tanks for independent operation, installation of a pressure transducer well pump control system, a remote monitor for water tank level, reconstruction work at a well house and miscellaneous work on the distribution system. The reconstruction work at the existing well house includes increasing well casing height, routing well discharge out the top of the well instead of a pitless adapter, new above grade plumbing and valves, a concrete floor slab, electrical and new well pump controls.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Supplemental Agreement for work within scope | $2,000 | |
| Supplemental Agreement for work within scope | $1,244 | |
| Supplemental Agreement for work within scope | $0 | |
| Change Order | $1,503 | |
| Change Order | $9,425 | |
| Change Order | -$3,100 | |
| Original award | $243,850 |
Quick answers
Who was awarded contract AG0489C100328?
AG0489C100328 was awarded to P C R Inc. by Operations Center Northwest (Economic Recovery Operations) on June 14, 2010.
How much is contract AG0489C100328 worth?
AG0489C100328's own ceiling is $254,922.
Who can order from contract AG0489C100328?
AG0489C100328 is a single award indefinite delivery contract. Only the awarding agency can place orders on it.
Was contract AG0489C100328 competed?
The extent of competition for AG0489C100328 was full and open competition after exclusion of sources. The government received 2 offers. It was set aside: Total Small Business.