Purchase Order 140P8525P0005

Award Date 4/15/25
Potential Completion Date 8/8/25
Potential Value $215K
Federal Agency
Pacific West Region
Ultimate Awardee
Not listed
Federal Contract Vehicle
Set-Aside Type
No Set-Aside Used
Extent Competed
Competed under SAP
Major Defense Program
Not listed
Pricing Type
Firm Fixed Price
Place of Performance
Yosemite National Park, California, USA
Solicitation Procedures
Simplified Acquisition
Number Of Offers Received
3
Legislative Mandate
Service Contract Act
National Interest Action
Not listed
Research Type
Not listed
Primary Consortia Member
Not listed
Similar Awards
<p>The U.S. National Park Service, Pacific West Region, awarded a $123,012 firm fixed price purchase order to Clearstream Environmental Inc., a for-profit S corporation, for the repair of the secondary clarifier at the wastewater treatment plant in Yosemite National Park. The contract has an ultimate completion date of January 3, 2025. This contract does not have a set-aside designation and was awarded on June 17, 2024.</p>
The National Park Service (NPS) awarded a $217,243,435.00 firm-fixed-price definitive contract to Kiewit Infrastructure West Co. for the rehabilitation of the El Portal Wastewater Treatment Facility (WWTF) and Administrative Camp in Yosemite National Park, California. The project, which has a performance period of 1,460 calendar days and a completion date of June 15, 2029, involves fully replacing the 45-year-old, undersized WWTF that serves Yosemite Valley, El Portal, and adjacent...
The U.S. National Park Service, Pacific West Region, awarded a firm-fixed-price purchase order contract worth $85,973.00 to Gold Electric Inc. for the El Portal Lift Station Upgrade project in Yosemite National Park, Mariposa County, California. The contract has an ultimate completion date of February 15, 2023. The contract was awarded on August 9, 2022 and was not set aside for any small business program. The original federal contract opportunity was a small business set-aside solicitation...
This is a firm fixed-price definitive contract awarded by the Department of the Interior's National Park Service Pacific West Region to Sierra Communications &amp; Construction Inc. for $203,974.00 to replace the centrifuge controls at the Yosemite - El Portal Wastewater Treatment Plant in Mariposa County, California. The contract has a completion date of May 31, 2024. Sierra Communications &amp; Construction Inc. is an 8(a) program participant, HUBZone certified firm, and minority-owned small...
This is a firm-fixed price commercial items contract awarded by the National Park Service, Pacific West Region to Coast Sanitary, Inc., a small business subchapter S corporation, for vault toilet and septic tank pumping services at Yosemite National Park. The contract has a ceiling value of $170,850.00 and an ultimate completion date of October 19, 2024. The services will be performed at the El Portal, CA location over a 16-week period from July 1 to October 19, 2024. This contract was awarded...
The National Park Service awarded a $218,114 delivery order contract to Jacobs Government Services Company for supplemental wastewater treatment plant services at Tuolumne Meadows in Yosemite National Park. The prime contractor will provide unspecified additional support to the existing wastewater treatment plant in Tuolumne Meadows under a firm fixed price arrangement running from May through December 2022. Shannon &amp; Wilson, Inc. was selected as a subcontractor to offer other scientific and...
This is a firm fixed-price delivery order contract awarded by the National Park Service (NPS) to Jacobs Government Services Company, a professional services firm specializing in architectural, engineering, construction, and program management services for federal agencies. The contract is for the rehabilitation of the El Portel Wastewater Treatment Facility in Yosemite National Park, California, with a total ceiling value of $2,826,077.77 and a completion date of July 31, 2025. The contract...
This contract, awarded by the National Park Service to Ama Diversified Construction Group, a Small Business Administration certified 8(a) and minority-owned small business contractor, is for the replacement of the failing sewage disposal leachfields at the Wawona Campground in Yosemite National Park, California. The $7,339,977.63 firm-fixed-price contract involves the installation of new sewer gravity lines, force mains, a sewer pump station, water main, and related electrical and...
This is a firm-fixed-price definitive contract awarded by the Pacific West Region of the U.S. Department of the Interior to TSI Engineering, Inc., an SBA-certified 8(a) and HUBZone small business. The $358,144 contract is for improvements to the existing El Portal Wastewater Treatment Plant Headworks in El Portal, California. The work includes removal of the existing manual bar rack and replacement with an automatic self-cleaning mechanical bar rack, a washer/compactor unit, a screenings...
This is a firm fixed-price purchase order contract awarded by the National Park Service, Pacific West Region, to Synagro Technologies Inc. (doing business as RPM Marketing) for $182,609.99 to provide sludge removal and disposal services for the Yosemite National Park in El Portal, California. The contract has a base period of one year and four one-year option periods, with a total potential completion date of March 31, 2027. The contract was set aside for small businesses. The original...

This federal contract award was issued by the National Park Service, Pacific West Region, to Clearstream Environmental Inc. for the replacement of the secondary clarifier framework at the El Portal Wastewater Treatment Plant in Yosemite National Park, California. The contract is a firm-fixed-price purchase order with a ceiling value of $215,000.00 and a completion date of August 8, 2025. The work involves the removal of existing equipment, preparation and recoating of the concrete tank surface, and installation of new framework components including a cage and RAS box constructed of mild steel. This contract was awarded under a sources sought announcement, with no set-aside designation. The project aims to ensure the secondary clarifier remains fully functional and compliant with existing wastewater treatment permits.

Generated 4/21/25, 3:42 AM