OCO funding - the object of this project is to construct infrastructure electrical distribution and telecommunications in support of the fort hood hospital replacement. Work includes electrical…

Ended Awarded Last action

Contract number
0002
Awardee
Awarding agency
Obligated
$10,156,116

Award facts

Contract value 100% obligated
$10,156,115.80 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Funding agency
Federal Acquisition Service General Services Administration
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 8 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Fort Hood, TX 76544, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change Order 11 · MOD to pay bonding company instead of prime contractor - project for FT hood hospital infrastructure. Telecommunication duct banks - hospital $0
Change Order 11 · OCO funding - MOD to change payments to go to bonding company instead of prime contractor - project for FT hood hospital infrastructure. $0
Change Order 10 $0
Change Order 10 · Arra arra::yes::arra project number::74650::RPH arra reporting modification no longer required under far 52.204-11 OCO funding $0
Change Order 9 · Correcting contractors duns number. Telecommunication duct banks - hospital $0
Change Order 9 · Corrcting duns number. OCO funding $0
Change Order 8 · Infrastructure MC012 - redundant telecommunication duct bank MC013 - repair work at substation MC014 - road deletion and design change credit $0
Change Order 8 · TAS: :97 0501:: yes:: arra recovery project#::74650::RP#project title: 74650 hospital replacement (phase 1 and 2), infrastructure at fort hood, TX… $142,685
Change Order 7 · Infrastructure MC011 reroute utilities $0
Change Order 7 · TAS: :97 0501:: yes:: arra recovery project#::74650::RP#project title: 74650 hospital replacement (phase 1 and 2) electrical distributution &… $33,111
Change Order 6 · Elec. Dist & telecommunication MC010 weather time extension july 11-DEC 11 $0
Change Order 6 · TAS: :97 0501:: yes:: arra recovery project#::74650::RP#project title: 74650 hospital replacement (infrastructure) at fort hood, TX MC010 weather time extension… $0
Change Order 5 · Arra elec. Dist & telecommunation MC006 overhead distribution $0
Change Order 5 · Arra:: yes:: arra recovery project#::74650::RP#project title: 74650 hospital replacement (infrastructure) at fort hood, TX MC006 overhead distribution $272,570
Supplemental Agreement for work within scope 4 $0
Supplemental Agreement for work within scope 4 $6,867
Change Order 1A · TAS: :97 0501:: yes:: arra recovery project#::74650::RP#project title: 74650 hospital replacement (infrastructure) at fort hood, TX weather time extention… $0
Change Order 1A · Arra elec. Dist & telecommunication $0
Change Order 3 $19,904
Change Order 3 · Arra::yes::arra recovery project#::74650::RP# project title 74650 hospital replacement (infrastructure) at fort hood, texas the government elected to… $0
Change Order 2 · Arra::yes::arra recoveryproject#::74650::RP# project title: 74650, fort hood hospital replacement this modification is to change ssho level 6 to level 3 ssho,… -$17,722
Change Order 2 · This modification is to change ssho level 6 to level 3 ssho, delete the government field office, and increase copper pair count by 75, from 25 pair to 100… $0
Funding Only Action 1 · Telecommunication duct banks - hospital -$3,394,545
Funding Only Action 1 · Arra::yes::arra recoveryproject#::74650::RP# project title: 74650, fort hood hospital replacement this project is for all labor, equipment, and materials to… $3,394,545
Modification $3,394,545
Original award Recoveryproject#::74650::RP# the object of this project is to construct infrastructure electrical distribution and telecommunications in support of the fort… $6,304,155
Show all 26

About this award

This federal contract award, valued at $10,156,115.80, was issued by the Federal Acquisition Service (FAS), a civilian agency, to RMA Land Construction, Inc., a minority-owned small disadvantaged business. The contract is a delivery order under a larger vehicle and involves the construction of electrical distribution and telecommunications infrastructure to support the Fort Hood Hospital Replacement project. The work includes electrical substation expansion, feeders, telephone switching station, and telecommunications ductbanks. This contract has a total small business set-aside designation.

Description

OCO funding - the object of this project is to construct infrastructure electrical distribution and telecommunications in support of the fort hood hospital replacement. Work includes electrical substation expansion, feeders, telephone switching station, telecommunications ductbanks.

Quick answers

Who was awarded contract 0002?

0002 was awarded to RMA Land Construction, Inc. by ENDIST Fort Worth (US Army Corps of Engineers) on June 14, 2010.

How much is contract 0002 worth?

The government has obligated $10,156,116 on 0002.

Which agency awarded contract 0002?

ENDIST Fort Worth (US Army Corps of Engineers) awarded 0002, with funding from Federal Acquisition Service (General Services Administration).

Is contract 0002 an order under another contract?

Yes. 0002 is a delivery order under W9126G09D0100, an indefinite delivery contract.

Was contract 0002 competed?

The extent of competition for 0002 was full and open competition after exclusion of sources. The government received 8 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award