Pursuant to dfars clause 252.216-7006, ordering, and the terms and conditions of contract W15P7T-14-d-C006, task order KZ03 is hereby issued on a cost plus fixed fee basis in the amount of $2,392,236.…
Funding Only Action
46 · The purpose of this modification is to deleted slin 0011AB.
-$564
Funding Only Action
45 · The purpose of this modification is to deobligate somards funds from slin 0011AA in the amount of ($564.04) and transition funds to an alternative financial…
$0
Funding Only Action
44 · The purpose of this modification (44) is to DE-obligate funding in the total amount of ($10,000) from slin 0013AB.
-$10,000
Funding Only Action
43 · The purpose of modification is to deobligate funds in the amount of ($8,000) from slin 0014AA.
-$8,000
Supplemental Agreement for work within scope
42 · The purpose of this modification (42) to task order KZ03, is to extend slins 0020AA, 0020AB, 0020AC, and 0021AA period of performance (POP) from 30 SEP 2022…
$0
Supplemental Agreement for work within scope
41 · The purpose for modification (41) is to extend the period of performance (POP) for slin 0018AA by one (1) additional month, and to provide funding in the amount…
$690,617
Supplemental Agreement for work within scope
40 · The purpose of this modification (40), to task order KZ03 is to extend the period of performance (POP) of slin 0018AA by one (1) month at no additional cost…
$0
Funding Only Action
39 · The purpose of this modification 39, is to DE-obligate funding from slin 0007AC in the amount of ($2,929.22).
-$2,929
Supplemental Agreement for work within scope
38 · The purpose of this modification is to extend KZ03 task order clin 18AA to 12/31/21 to account for expenditure and processing of expense reports.
$0
Supplemental Agreement for work within scope
37 · The purpose of this modification (37) to task order KZ03, is to extend the below slins on period of performance (POP) at no additional cost to the government.…
$0
Supplemental Agreement for work within scope
36 · The purpose of this modification (36) is to provide funding in the amount of $743,902.00 for the electronic warfare planning and management tool.
$743,902
Funding Only Action
35 · The purpose of this modification is to deobligate $105,000 from this contract.
-$105,000
Funding Only Action
34 · The purpose of this modification (34) is to deobligate $36,000 from this contract. Please see section b and g for further information on this deobligation.
-$36,000
Change Order
33 · The purpose of modification (33) on W15P7T-14-d-C006 KZ03 is to increase the contract ceiling and provide funding for the cema ONS training support effort.
$1,574,188
Supplemental Agreement for work within scope
32 · This modification was done to extend the period of performance on slin 0014AB.
$0
Change Order
31 · This modification was done to incorporate the "U.S.-ROK status of forces agreement" (sofa) into task order KZ03
$0
Change Order
30 · The purpose of this modification is to fully definitize the NTE change order created with modification 29.
$1,041,431
Funding Only Action
29 · The purpose of this modification (29) is to provide incremental funding in the amount of $1,033,683.62 to rapidly design, develop, integrate and test an initial…
$1,033,684
Supplemental Agreement for work within scope
28 · The purpose of this modification is to increase the ceiling of the subject task order by $598,926.00 in order to fund usareur ONS training. As well as update…
$598,926
Supplemental Agreement for work within scope
27 · The purpose of this modification (27) is to provide funding in the amount of $2,148,197.00 for the electronic warfare planning and management tool, cema ONS…
$2,148,197
Supplemental Agreement for work within scope
26 · The purpose of this modification (26), is to extend task order KZ03 period of performance for clin 0009 from 30 september 2019 to 31 march 2020 at no additional…
$0
Supplemental Agreement for work within scope
25 · Pursuant to far 43.103(a)(3), "types of modifications," the purpose of this modification (25), is to extend task order KZ03 period of performance for slin…
$0
Other Administrative Action
24 · The purpose of this modification (24), is to extend task order KZ03 period of performance for slins 0009AA, 0009AB, 0010AA, and 0010AB from 31 july 2019 to 30…
$0
Supplemental Agreement for work within scope
23 · The purpose of this modification (23), on W15P7T-14-d-C006 KZ03 is to fully fund the raven claw touch points effort.
$2,484,003
Supplemental Agreement for work within scope
22 · The purpose of this modification (22) is to provide funding in the amount of $689,798.00 for the electronic warfare planning and management tool, appew phase 2B…
$689,798
Change Order
21 · The purpose of this modification (21) is to provide funding in the amount of $300,345.00 for the electronic warfare planning and management tool joint…
$300,345
Supplemental Agreement for work within scope
20 · The purpose of modification (20) on W15P7T-14-d-C006 KZ03 is to definitize ewpmt cyber electromagnetic activities (cema) operational needs statement (ONS)…
$1,396,679
Other Administrative Action
19 · The purpose of this modification (19) is to correct modification (18) section a narrative.
$0
Change Order
18 · The purpose of this modification (18) is to provide incremental funding in the amount of $1,433,764.75 to rapidly design, develop, integrate and test an initial…
$1,433,765
Change Order
17 · In accordance with far 52.243-2 changes-cost reimbursement, the purpose of modification (17) on W15P7T-14-d-C006 KZ03 is to definitize ewpmts raven feather /…
$98,177
Funding Only Action
16 · Pursuant to far 52.232-22 "limitation of funds", the purpose of this modification (16) is to provide incremental funding to rapidly design, develop, integrate…
$207,712
Supplemental Agreement for work within scope
15 · The purpose of this modification (15) is to provide incremental funding in the amount of $529,730.00 for the continued development of the raven claw phase II…
$529,730
Funding Only Action
14 · In accordance with far 52.243-2 changes-cost reimbursement, the purpose of modification (14) on W15P7T-14-d-C006 KZ03 is to increase the contract ceiling and…
$248,794
Funding Only Action
13 · The purpose of this modification (13) is to fully fund the raven claw phase II effort in the amount of $36,327.55.
$36,328
Funding Only Action
12 · The purpose of this modification (12) is to provide incremental funding to rapidly design, develop, integrate and test an initial capability for the raven…
$650,972
Funding Only Action
11 · Pursuant to far 52.232-22 "limitation of funds", the purpose of this modification (11) is to provide incremental funding to rapidly design, develop, integrate…
$1,996,661
Funding Only Action
10 · The purpose of this modification (10) is to provide incremental funding to rapidly design, develop, integrate and test an initial capability for the raven…
$399,098
Change Order
9 · The purpose of modification (09) on W15P7T-14-d-C006 KZ03 is to definitize ewpmts raven claw HTML5 software conversion effort
$0
Definitize Change Order
8 · The purpose of modification (08) on W15P7T-14-d-C006 KZ03 is to definitize ewpmt raven claw phase II effort.
$0
Change Order
7 · Pursuant to far 43.103(a)(3), "types of modifications," the purpose of this modification (07), is to extend task order KZ03 period of performance for raven…
$0
Funding Only Action
6
$2,600,000
Funding Only Action
5
$1,600,000
Funding Only Action
4 · Pursuant to far 52.232-22 "limitation of funds", the purpose of this modification (04) is to provide incremental funding to rapidly design, develop, integrate…
$1,537,000
Change Order
3 · Pursuant to the changes clause of basic contract number W15P7T-14-d-C006 (subsection i-85, far 52.243-2 "cost - reimbursement - alternate i"), the purpose of…
$792,190
Funding Only Action
2 · The purpose of this modification (02) is to provide additional funding in the amount of $128,876 to repair software defects.
$128,876
Other Administrative Action
1 · The purpose of this modification is to correct the erroneously chosen contract type. Contract type should be cpff
$0
Original award
$2,392,236
Show all 47
About this award
Written by GovTribe AI
·
This is a cost-plus-fixed-fee task order under contract W15P7T-14-D-C006, issued by the PEO Intelligence Electronic Warfare & Sensors (PEO IEW&S) to prime contractor Raytheon Company for "Interim Contractor Support (ICS)" work valued at $2,392,236. The overall contract has a ceiling value of $27,190,815.74 and does not have a socioeconomic set-aside designation.
Raytheon, a major defense contractor, is performing this work at its facility in Fort Wayne, Indiana. The task order includes engineering services provided by two subcontractors: AEA Consulting, Inc., a service-disabled veteran-owned small business, and Perceptronics Solutions, Inc., a small business focused on communications systems research and development. This contract supports the PEO IEW&S' strategic communications, electronic warfare, and missile defense priorities.
Description
As the agency reported it.
Pursuant to dfars clause 252.216-7006, ordering, and the terms and conditions of contract W15P7T-14-d-C006, task order KZ03 is hereby issued on a cost plus fixed fee basis in the amount of $2,392,236. All work shall be in accordance with the attached performance work statement entitled, "interim contractor support (ICS)" dated 8 february 2017, located in section j, attachment 0001.
Quick answers
Who was awarded contract KZ03?
KZ03 was awarded to Raytheon Company by ACC Aberdeen Proving Ground (Army Contracting Command) on February 28, 2017.
How much is contract KZ03 worth?
The government has obligated $27,190,816 on KZ03.
Which agency awarded contract KZ03?
ACC Aberdeen Proving Ground (Army Contracting Command) awarded KZ03, with funding from PEO Intelligence Electronic Warfare & Sensors (Acquisition Support Center).
Is contract KZ03 an order under another contract?
Yes. KZ03 is a delivery order under W15P7T14DC006, an indefinite delivery contract.
Was contract KZ03 competed?
The extent of competition for KZ03 was full and open competition.