Recovery - FFS project # R1GF construct fish passages and screens at malheur national wildlife refuge.

Ended Awarded Last action

Contract number
INF10PD80057
Awardee
Awarding agency
Obligated
$2,551,066

Award facts

Contract value 100% obligated
$2,551,065.54 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 5 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Princeton, NJ 08544, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change Order 10 · Malheur fish pass/scrn constructn $23,000
Change PIID 9A $0
Change Order 9 · Modify screen panels for the construction of the fish panels and screens at malheur NWR $12,505
Change Order 7 · Recovery - FFS project #R1GF deobligate non-arra funds due to descope and add arra funds for concrete overage for the construction of the fish passages and… $25,969
Change Order 6 · Recovery FFS project #R1GF no cost modification to extend delivery date through 05/06/11 for the malheur fish passages and screens due to weather delays. $0
Change Order 5 · Recovery - FFS project # R1GF funds for additional sheet pile excavation for the fish passages and screens project at malheur NWR $89,053
Change Order 4 · Recovery - FFS project # R1GF perform sheet pile excavation for the construction of fish passages and screens at malheur NWR - this is non-arra money $131,456
Funding Only Action 3 · Recovery - FFS project # R1GF change in fund cite for $37,081 in arra monies to non-arra monies for the construction of fish passages and screens at malheur NWR $0
Change Order 2 · Recovery - FFS project # R1GF provide fabricated baffles for grain camp for the construction of fish passages and screens at malheur NWR $62,192
Change Order 1 · Recovery - FFS project # R1GF fabricate and deliver materials for the fish passages and screens at malheur NWR $149,395
Original award $2,057,496
Show all 11

About this award

This is a federal contract award to Northcon Inc., a Native American-owned small business based in Hayden, Idaho, for the construction of fish passages and screens at the Malheur National Wildlife Refuge. The contract, with a ceiling value of $2,551,065.54, was awarded on December 24, 2009 by the U.S. Fish and Wildlife Service, a civilian agency within the Department of the Interior. The contract is a Firm Fixed Price Delivery Order with an ultimate completion date of December 31, 2012. The contract does not have a set-aside designation. Northcon Inc. is a highly capable federal contractor, holding several large Indefinite Delivery/Indefinite Quantity (IDIQ) contracts across various government agencies, including the General Services Administration, Air Force, and Navy. This specific contract is likely part of the Fish and Wildlife Service's efforts to improve fish habitat and passage at National Wildlife Refuges.

Quick answers

Who was awarded contract INF10PD80057?

INF10PD80057 was awarded to Northcon Inc. by DOI Fish and Wildlife Service Region 1 (Fish and Wildlife Service) on December 24, 2009.

How much is contract INF10PD80057 worth?

The government has obligated $2,551,066 on INF10PD80057.

Is contract INF10PD80057 an order under another contract?

Yes. INF10PD80057 is a delivery order under INF08PC60069, an indefinite delivery contract.

Was contract INF10PD80057 competed?

The extent of competition for INF10PD80057 was full and open competition. The government received 5 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award