PS04 MODIFICATION: THIS MODIFICATION IS ISSUED TO ADD ADDITIONAL FUNDS OF $8,123.75 TO PROVIDE FUNDING TO SAW CUT, DEMO AND REMOVE EXISTING CONCRETE SIDEWALK, RE-GRADE THE COMPACT EXISTING BASE MATERIAL AND FORM NEW CONCRETE AND POUR 4" CONCRETE TO BE FLUSH WITH CITY SIDEWALK. THE CONTRACT DELIVERY DATE IS ALSO EXTENDED FROM 9/31/2012 TO 10/31/2012 TO ALLOW FOR SUFFICIENT TIME TO COMPLETE THE PROJECT. BOTH PARTIES AGREE TO AN INCREASE IN PRICE TOTALING $8,123.75 AND A TIME EXTENSION TO 10/31/2012. IN CONSIDERATION OF THIS MODIFICATION AGREED TO HEREIN AS COMPLETE EQUITABLE ADJUSTMENT, REVA MURPHY ASSOCIATES, INC OF LIVERMORE, CA HEREBY RELEASES THE GOVERNMENT FROM ANY AND ALL LIABILITY UNDER THIS CONTRACT FOR FURTHER EQUITABLE ADJUSTMENTS ATTRIBUTABLE TO SUCH FACTS FOR CIRCUMSTANCES GIVING RISE TO THIS SUPPLEMENTAL AGREEMENT. Supplemental Agreement for work within scope $8.1k 8/24/12 PA03 THIS MODIFICATION IS ISSUED TO CHANGE THE FUNCTION CODES UNDER THE 2 ACCOUNTING STRINGS. Other Administrative Action $0 8/3/12 PA02 MODIFICATION: THIS MODIFICATION IS ISSUED TO ADJUST THE FUNDS TO BE USED FROM BA54 FUNDS AND BA61. $31,929.73 ORIGINALLY AWARDED IN CONTRACT IS USED WITH BA54 FUNDS AND MODIFICATION OF RAMP COST OF $7,978.30 IS TO BE EXPENSED WITH BA61 FUNDS. Other Administrative Action $0 8/1/12 PS01 MODIFICATION: THIS MODIFICATION IS ISSUED TO ADD ADDITIONAL FUNDS OF $7,978.30 TO PROVIDE FUNDING FOR ADDITIONAL ADA RAMP ON NW LOCATION AT NARA. THE CONTRACTOR WILL SAW CUT, DEMO AND REMOVE EXISTING CONCRETE, FORM NEW ADA RAMP, INSTALL REBAR AND POUR CONCRETE ADA RAMP, INCLUDING TRUNCATED DOMES, PLUG PAVE ASPHALT ALONG NEW CONCRETE RAMP, AND PAINT ALL NEW PAVEMENT MARKINGS AS SHOWN ON PLANS. BOTH PARTIES AGREE TO AN INCREASE IN PRICE TOTALING $7,978.30. IN CONSIDERATION OF THIS MODIFICATION AGREED TO HEREIN AS COMPLETE EQUITABLE ADJUSTMENT, REVA MURPHY ASSOCIATES, INC OF LIVERMORE, CA HEREBY RELEASES THE GOVERNMENT FROM ANY AND ALL LIABILITY UNDER THIS CONTRACT FOR FURTHER EQUITABLE ADJUSTMENTS ATTRIBUTABLE TO SUCH FACTS FOR CIRCUMSTANCES GIVING RISE TO THIS SUPPLEMENTAL AGREEMENT. Supplemental Agreement for work within scope $8.0k 8/1/12 Not listed CONTRACTOR WILL PROVIDE ALL LABOR, MATERIALS, EQUIPMENT AND SUPERVISION FOR THE NARA SIDEWALK IMPROVEMENT PROJECT WHICH WILL RECONFIGURE THE SIDEWALKS WITHIN THE TWO NARA PARKING LOTS ON THE SOUTH SIDE OF COMMODORE DRIVE THAT LEAD TO THE ENTRANCE OF NARA. THIS PROJECT IS TO BE PERFORMED IN CONJUNCTION WITH THE CITY OF SAN BRUNO'S COMMODORE DRIVE PEDESTRIAN ACCESS PROJECT WHICH WILL INSTALL SIDEWALK ALONG THE ENTIRE LENGTH OF NARA PROPERTY ON THE NORTH SIDE OF COMMODORE DRIVE. SEE ATTACHED SOW. Not listed $31.9k 5/22/12