Facility modification of mbta garage located at 11 channel street for occupancy by ICE and DEA.

Ended Awarded Last action

Contract number
47PB0017F0031
Awardee
Awarding agency
Obligated
$1,025,100

Award facts

Contract value 100% obligated
$1,025,100.34 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition after exclusion of sources · 3 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Boston, MA 02110, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PS0009 · This MOD is for an equitable adjustment for differing site conditions of the existing concrete floor at the channel street barnes garage in boston, MA. $6,365
Supplemental Agreement for work within scope PS0008 · Modification for scoping of drain to determine suitability for connection to oil/water separator. $1,473
Funding Only Action PS0007 · Modification to adjust contract value by taking credits for ordered work that was not required and not performed. -$54,184
Supplemental Agreement for work within scope PS0006 · Supplemental agreement to replace faulty gate valve for domestic hot water supply. $3,567
Supplemental Agreement for work within scope PS0005 · Change order to install ductwork security measures and high security lockset at the direction of the customer. $8,780
Definitize Change Order PS0004 · Modification to definitize change order PC02 for removal of subsurface obstructions encountered during trenching operations. This represents full settlement… $2,946
Supplemental Agreement for work within scope PS0003 · Supplemental agreement for work within scope to add man bars to ductwork to enhance security. $4,311
Change Order PC0002 · Change order to allow contractor to remove obstacles discovered i the course of trenching for drain. Definitization schedule in MOD. $11,157
Change Order PC0001 · Modification to provide demolition and removal of a wall that was discovered to be unsafe and beyond repair. As a result there was a net credit to the contract. -$4,802
Original award $1,045,488

About this award

The General Services Administration (GSA) Public Buildings Service Region 1 awarded a $1,025,100.34 firm fixed price delivery order to Maron Construction Co., Inc., a self-certified small disadvantaged business, for the facility modification of an MBTA garage located at 11 Channel Street in Boston, MA. This work was to prepare the space for occupancy by the Immigration and Customs Enforcement (ICE) and the Drug Enforcement Administration (DEA). The contract had a completion date of June 29, 2018 and did not utilize a set-aside. Maron Construction Co., Inc. provides construction services to federal agencies and has held multiple award contracts and indefinite delivery/indefinite quantity contracts with the Department of the Air Force and GSA for facility maintenance, repair, and modernization projects.

Quick answers

Who was awarded contract 47PB0017F0031?

47PB0017F0031 was awarded to Maron Construction Co., Inc. by Region 1 (Public Buildings Service) on September 29, 2017.

How much is contract 47PB0017F0031 worth?

The government has obligated $1,025,100 on 47PB0017F0031.

Is contract 47PB0017F0031 an order under another contract?

Yes. 47PB0017F0031 is a delivery order under GS01P13BZD0014, an indefinite delivery contract.

Was contract 47PB0017F0031 competed?

The extent of competition for 47PB0017F0031 was full and open competition after exclusion of sources. The government received 3 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award