Highway 18 kermit RI/FS the work plan dated september 21, 2018 as submitted by the contractor representing a total task order work plan amount of 1,464,021.00 is being partially approved for…

Ended Awarded Last action

Contract number
68HE0618F0317
Awardee
Awarding agency
Obligated
$836,870

Award facts

Contract value 100% obligated
$836,869.99 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
562910 Remediation Services
Set-aside
No set-aside
Competition
Full and Open Competition after exclusion of sources Architect-Engineer FAR 6.102
Pricing
Time and Materials
Place of performance
Lewisville, TX 75067, USA

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Funding Only Action P00008 · Highway 18 kermit RI/FS this modification is to DE-obligate funding in the amount of $.01. -$0
Other Administrative Action P00007 · Highway 18 kermit RI/FS this modification is to approve work plan revision 01 based on the attached statement of work dated june 23, 2020. $0
Other Administrative Action P00006 · Highway 18 kermit RI/FS this modification is to request a work plan revision based on the attached statement of work dated june 23, 2020. $0
Funding Only Action P00005 $103,000
Funding Only Action P00004 · Highway 18 kermit RI/FS increase funding and expenditure limits and increase the partially approved work plan budget by $30,000 from $703,870 to $733,870 and… $30,000
Other Administrative Action P00003 · Highway 18 kermit RI/FS field change form no. 01 dated 28 march 2019 shall be incorporated under EPA approved work plan and cost estimate, dated 21 september… $0
Other Administrative Action P00002 · Highway 18 kermit RI/FS this no cost modification of the highway 18 kermit texas task order is hereby issued to change the period of performance from april 1,… $0
Funding Only Action P00001 · Highway 18 kermit RI/FS this modification increases funding, increases the partially approved work plan budget and increases expenditure limits by $… $603,870
Original award $100,000

About this award

This federal contract award was issued by the Environmental Protection Agency (EPA) Region 6 to EA Engineering, Science, and Technology, Inc., PBC (EA Engineering), a for-profit employee-owned public benefit corporation that provides environmental services. The contract is for a Remedial Investigation/Feasibility Study (RI/FS) for HIGHWAY 18 KERMIT, with a partially approved task order value of $100,000.00 and a period of performance from April 1, 2019 to November 21, 2020. The contract does not have a set-aside designation, and the potential value of the overall contract is $836,869.99. EA Engineering has extensive experience providing environmental services, including remedial investigations, feasibility studies, remediation, and long-term stewardship, to federal agencies such as the EPA, Department of Defense, and Army Corps of Engineers through prime and subcontract awards.

Description

Highway 18 kermit RI/FS the work plan dated september 21, 2018 as submitted by the contractor representing a total task order work plan amount of 1,464,021.00 is being partially approved for 100,000.00, and a period of performance of 1 april 2019

Quick answers

Who was awarded contract 68HE0618F0317?

68HE0618F0317 was awarded to EA Engineering, Science, And Technology, Inc., PBC by EPA Region 6 (Regional Offices) on September 26, 2018.

How much is contract 68HE0618F0317 worth?

The government has obligated $836,870 on 68HE0618F0317.

Is contract 68HE0618F0317 an order under another contract?

Yes. 68HE0618F0317 is a delivery order under EPW06004, an indefinite delivery contract.

Was contract 68HE0618F0317 competed?

The extent of competition for 68HE0618F0317 was full and open competition after exclusion of sources.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award