West branch grand calumet river reaches 6 and 7 remedial action

Ended Awarded Last action

Contract number
0001
Awardee
Awarding agency
Obligated
$3,042,662

Award facts

Opportunity
Contract value 18% obligated
$16,600,000.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
562910 Remediation Services
Set-aside
No set-aside
Competition
Full and Open Competition · 6 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Hammond, IN 46320, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action P00024 $0
Definitize Change Order 23 · West branch grand calumet river reaches 6 and 7 remedial action finalizing settlement proposal. $717,437
Change Order 22 $17,437
Supplemental Agreement for work within scope 21 · West branch grand calumet river reaches 6 and 7 remedial action design changes for RIP RAP at finger and railroad culvert $0
Supplemental Agreement for work within scope 20 $750,000
Change Order 19 · West branch grand calumet river reaches 6 and 7 remedial action UCO eliminating removal of access road material $0
Supplemental Agreement for work within scope 18 · West branch grand calumet river reaches 6 and 7 remedial action supplemental agreement $393,825
Supplemental Agreement for work within scope 17 · West branch grand calumet river reaches 6 and 7 remedial action reductive change order $0
Supplemental Agreement for work within scope 16 · West branch grand calumet river reaches 6 and 7 remedial action differing condition $8,000
Change Order 15 $25,000
Change Order 14 · West branch grand calumet river reaches 6 and 7 remedial action change order $32,000
Other Administrative Action 13 · West branch grand calumet river reaches 6 and 7 remedial action administrative action $0
Funding Only Action 12 · West branch grand calumet river reaches 6 and 7 remedial action quantity overruns $8,463
Other Administrative Action 11 · West branch grand calumet river reaches 6 and 7 remedial action add ALT. COR $0
Change Order 10 $82,000
Change Order 9 $25,000
Change Order 8 · West branch grand calumet river reaches 6 and 7 remedial action change order $38,500
Change Order 7 $180,000
Other Administrative Action 6 $0
Change Order 5 · West branch grand calumet river reaches 6 and 7 remedial action mutual agreement $225,000
Change Order 4 $450,000
Change Order 3 · West branch grand calumet river reaches 6 and 7 remedial action change order $90,000
Other Administrative Action 2 $0
Other Administrative Action 1 $0
Original award $0
Show all 25

About this award

This is a firm fixed-price delivery order awarded by the U.S. Environmental Protection Agency (EPA) Region 5 to a joint venture of Ryba Marine Construction Co. and Terra Contracting Services, LLC. The $16,600,000.00 contract is for remedial action work on Reaches 6 and 7 of the West Branch Grand Calumet River as part of the EPA's Great Lakes National Program Office Construction Services II major program. The contract does not have a set-aside designation and is scheduled for completion by October 12, 2016.

Quick answers

Who was awarded contract 0001?

0001 was awarded to Ryba Marine Construction Co / Terra Contracting Services, Llc, A Joint Venture by EPA Region 5 (Regional Offices) on May 27, 2015.

How much is contract 0001 worth?

The government has obligated $3,042,662 on 0001. Its current value, with exercised options, is $16,600,000.

Is contract 0001 an order under another contract?

Yes. 0001 is a delivery order under EPR51502, an indefinite delivery contract.

Was contract 0001 competed?

The extent of competition for 0001 was full and open competition. The government received 6 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award