Delivery Order AG82X9C090258-AG82X9D110026

Award Date 4/26/11
Potential Completion Date 10/30/12
Potential Value $142K
Awardee
Edaw, Inc.
Ultimate Awardee
Not listed
Federal Contract Vehicle
Set-Aside Type
No Set-Aside Used
Extent Competed
Full and Open Competition
Major Defense Program
Not listed
Pricing Type
Firm Fixed Price
Place of Performance
Fort Collins, CO, USA
Solicitation Procedures
Multiple Award, Fair Opportunity
Number Of Offers Received
1
Legislative Mandate
Not listed
National Interest Action
Not listed
Research Type
Not listed
Primary Consortia Member
Not listed
Similar Awards
The Department of Transportation Federal Highway Administration awarded a $5.7 million firm fixed price contract to Bruch And Bruch Construction Inc. to construct Segment B of the Spruce Railroad Trail in Olympic National Park, Washington. The 1.8-mile trail segment involves clearing, excavation, aggregate base, shotcrete, drainage, fencing, signs, and construction of a prefabricated steel bridge. Major subcontractors include Snell Crane Service, Inc. for crane services, Lakeside Industries Inc....
The U.S. Department of Agriculture Forest Service Rocky Mountain Region awarded a $81,789.61 firm fixed-price delivery order to Epic Construction & Environmental Inc. to construct a Rampart Reservoir fee booth pad and turnabout in Elbert, Colorado. The work must be completed by December 31, 2020. No set-aside provisions were applied to this award to build facilities supporting the Forest Service's land management activities at Rampart Reservoir. Epic Construction will serve as the prime...
Creative Trail Designs, LLC was awarded a two-year, one hundred thirteen thousand five hundred twenty dollar firm fixed price contract by the Department of the Interior Bureau of Land Management Oregon-Washington to provide off-highway vehicle (OHV) trail maintenance services. Per the solicitation, the contractor will deliver OHV trail maintenance at specified locations in the northwest Oregon district, adhering to the statement of work and provisions outlined. The contract has a set aside for...
The Department of the Army Corps of Engineers Engineering District Omaha awarded a $14.6 million firm fixed price contract to Tribal One Construction LLC dba T1 Construction to replace the ALPHA RAMP pavement at Colorado Springs, Colorado. The contract was awarded under Solicitation ATV/UTV Noxious Weed Spraying MATOC which requested licensed commercial application of weed and vegetation spray via all-terrain or utility terrain vehicles for control of noxious weeds on USACE managed lands in...
The Department of Transportation's Federal Highway Administration awarded a $5,639,235.72 definitive, firm-fixed-price contract to Hartland-Reliant JV LLC, a Service-Disabled Veteran-Owned Small Business, for the construction of approximately 3.3 miles of a new multi-use trail on Fremont Pass in Frisco, Colorado. The project includes asphalt concrete pavement, timber boardwalk, and a prefabricated steel pedestrian bridge. This contract was competitively awarded under a Service-Disabled...
This federal contract, awarded by the Department of Transportation Federal Highway Administration, was for the OR DOT 26(2) Mirror Lake Trailhead Relocation project in Government Camp, Oregon. The $5,693,368.32 firm fixed price contract was set aside for HUBZone firms and was awarded to Stormwater Plans LLC, a certified HUBZone and Alaskan Native Corporation-owned company. Key subcontractors included Guinett Masonry, Inc. (women-owned small business) for masonry work, Coral Construction...
This is a firm fixed-price delivery order awarded by the U.S. Department of Agriculture (USDA) Forest Service, Region 2 - Rocky Mountain Region, to Chaparral Construction L.L.C., a certified HUBZone small business located in Colorado. The contract, valued at $189,666.86, is for road work on the Pikes Peak, South Park, South Platte, and San Carlos Districts. The work includes chaparral to #02OY 02 road work, likely involving vegetation management, excavation, and infrastructure maintenance...
This is a $21,285,631.58 definitive, firm-fixed-price contract awarded by the Federal Highway Administration (FHWA), a civilian agency, to Crestline Construction Company, L.L.C. for the OR DOT CRGNSA 100(4) Historic Columbia River Highway State Trail, Mitchell Point Crossing project. The work involves tunneling, grading, paving, signing, striping, landscaping, structures, and rockfall protection along a 1.45-mile section of trail 3 miles west of Hood River, Oregon. The contract has a tentative...
The United States Department of Agriculture Forest Service Rocky Mountain Region awarded a $321,000 delivery order contract to Epic Construction & Environmental Inc. for Bil CMJR Ppk Rampart Range Reconstruction under the PSICC Roads IDIQ. The firm fixed price order has a period of performance from September 30, 2022 through June 12, 2023 for priority fire shed funding to support roads infrastructure and development work at an unspecified location in Pueblo, Colorado. No subcontractors...
<p>This is a federal contract award from the U.S. Operations Center Southwest, a civilian agency, to V Mountain Construction, Inc., a small disadvantaged business. The contract is for asphalt paving work on the RIM VISTA TRAIL mobility and disability accessibility project, with a total ceiling value of $133,398.83. The contract was awarded on March 15, 2010 as a Firm Fixed Price Delivery Order, with a final completion date of September 27, 2010. The award is set aside for small businesses.</p>
  • AG82X9C090258
    Indefinite Delivery Contract
  • AG82X9C090258-AG82X9D110026
    Delivery Order

OHV RAMPART TRAIL CONSTRUCTION