- This $1,763,223.25 firm fixed price contract was awarded by the Federal Highway Administration (FHWA), a civilian agency, to Bruch & Bruch Construction, Inc., a small business based in Port Angeles, Washington. The contract is for the "WA NPS OLYM 2015(4), SPRUCE RAILROAD TRAIL SEGMENT C" project, which involves construction services for the National Park Service in Olympic National Park. The contract has no set-aside designation. Bruch & Bruch Construction is the prime...
- This is a definitive contract awarded by the Department of Transportation Federal Highway Administration to Bruch And Bruch Construction Inc., a small business, to perform the "WA NPS OLYM 2016(1), SPRUCE RAILROAD TRAIL SEGMENT A" project. The $1,128,082.34 firm fixed price contract was awarded on September 26, 2017, with a completion date of December 7, 2018. The work involves road construction and maintenance activities such as grading, paving, drainage, erosion control, and...
- The Department of Transportation Federal Highway Administration awarded a $1,565,740.52 definite contract to Bruch And Bruch Construction Inc. to repair slumps along approximately 11 miles of roads within Olympic National Park in Washington state. The work involves clearing, excavation, installing erosion controls, aggregate base, asphalt paving, drainage features, signage and pavement markings to restore structural integrity and drivability along affected segments of Hurricane Ridge Road and...
- This is a $684,430.77 firm fixed-price contract awarded by the Federal Highway Administration, a civilian agency, to 2 Grade, LLC, a small business based in Port Angeles, Washington. The contract is for the "WA NPS OLYM 2013(1), SPRUCE RAILROAD TRAIL" project, which involves construction, demolition, and infrastructure services for the National Park Service's Olympic National Park. The contract is a total small business set-aside and has a period of performance through November 4,...
- This $245,000.00 firm fixed price purchase order was awarded by the Department of Transportation Federal Highway Administration to Bruch And Bruch Construction Inc., a small business construction firm, for the WA JEFF 91420(3) project to perform upper Hoh clearing work on the Spruce Trail in Port Angeles, Washington. The contract has a completion date of May 28, 2019. Bruch And Bruch Construction Inc. also holds other federal construction contracts, including a 5-year, $15 million indefinite...
- This is a $652,807.24 firm fixed price delivery order contract awarded by the Department of Transportation Federal Highway Administration to AECOM Technical Services, Inc. The contract is to perform the beginning to intermediate design phases for the Spruce Railroad Trail Segment B project in Olympic National Park. No set-aside designation was used. AECOM Technical Services, Inc. is the prime contractor, and Shannon & Wilson Inc. is a subcontractor providing geotechnical reconnaissance and...
- This federal contract award from the Department of Transportation Federal Highway Administration is for the WA NPS OLYM 107(1), UPPER HOH RIVER EMERGENCY REPAIR project in Forks, Washington. The $455,752.30 firm fixed-price definitive contract was awarded to the small business prime contractor Bruch And Bruch Construction Inc. on June 11, 2018 with a completion date of October 12, 2018. Bruch And Bruch Construction Inc. is an experienced provider of construction services to federal agencies,...
- This is a definitive contract awarded by the U.S. Department of Transportation Federal Highway Administration to Massana Construction, Inc. (a self-certified small disadvantaged business) for $2,450,329.58. The contract is for minor bridge repair and preservation work at 18 bridges within Olympic National Park in Washington state, including epoxy coating, concrete repair, wood decking, bridge painting, and other small items. The work is to be completed by September 25, 2023. The original...
- The Department of Transportation Federal Highway Administration awarded a $2.3 million firm fixed price contract to Conway Construction Company to complete entrance station improvements at Olympic National Park in Port Angeles, Washington. The solicitation sought bids to renovate the Heart O the Hills Entrance Station building and grounds, including replacing the roof, siding, doors and windows; upgrading HVAC, electrical, and plumbing systems; repaving the parking area; and installing new...
- This is a $1,442,277.19 Definitive Contract awarded by the Department of Transportation Federal Highway Administration to the small disadvantaged business Conway Construction Company for the rehabilitation of the Staircase Road at Olympic National Park in Port Angeles, Washington. The contract is for construction services including roadway, sidewalk, and trail reconstruction; slope stabilization; retaining wall installation; culvert replacement; erosion control; asphalt paving; and associated...
The Department of Transportation Federal Highway Administration awarded a $5.7 million firm fixed price contract to Bruch And Bruch Construction Inc. to construct Segment B of the Spruce Railroad Trail in Olympic National Park, Washington. The 1.8-mile trail segment involves clearing, excavation, aggregate base, shotcrete, drainage, fencing, signs, and construction of a prefabricated steel bridge. Major subcontractors include Snell Crane Service, Inc. for crane services, Lakeside Industries Inc. for asphalt paving and contractor testing, and Rock Supremacy LLC for rock bolting, doweling, shotcrete, micropiles, and rockfall protection measures. Construction Quality Management, LLC will provide contractor quality control. Clark Land Office PLLC also holds an unspecified subcontract. There is no set-aside designation. All work must be completed between February 2020 and April 2021 to support recreation in Olympic National Park.
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
WA NPS OLYM 2017(1), Spruce Railroad Trail Segment B | 69056719B000004 | Department of Transportation Federal Highway Administration | Solicitation 2/3 | 11/21/19, 4:40 PM | |
WA NPS OLYM 2017(1), Spruce Railroad Trail Segment B | 69056720C000011 | Department of Transportation Federal Highway Administration | Award Notice 3/3 | 2/6/20, 12:41 PM | |
WA NPS OLYM 2017(1), Spruce Railrod Trail Segment B | 69056719B000004 | Department of Transportation Federal Highway Administration | Pre-Solicitation 1/3 | 8/7/19, 4:30 PM |
ContractNumber | Description | Subcontractor | Prime Award | Dollars Obligated | Updated At |
|---|---|---|---|---|---|
201008S | Snell Crane Service, Inc. | Definitive Contract 69056720C000011 | $31.5k | 4/17/20 | |
201005S | Lakeside Industries Inc. | Definitive Contract 69056720C000011 | $536.5k | 3/16/20 | |
201003S | Rock Supremacy LLC | Definitive Contract 69056720C000011 | $1.7m | 2/11/20 | |
201001S | Construction Quality Management, LLC | Definitive Contract 69056720C000011 | $200.0k | 2/6/20 | |
201002S | Clark Land Office PLLC | Definitive Contract 69056720C000011 | $98.7k | 2/6/20 |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| P00019 | Close Out | ($86k) | 4/6/22 | |
| P00018 | Supplemental Agreement for work within scope | ($2) | 1/18/22 | |
| P00017 | Supplemental Agreement for work within scope | $0 | 5/3/21 | |
| P00016 | Supplemental Agreement for work within scope | $0 | 4/1/21 | |
| P00015 | Supplemental Agreement for work within scope | $215.8k | 3/8/21 |