Delivery Order AG0120C100007-AG0120D110022
Award Date 9/23/11
Potential Completion Date 10/15/12
Potential Value $1.2M
Federal Agency
Ultimate Awardee
Not listed NAICS Category
PSC Category
Not listed Federal Contract Vehicle
- Not listed
Set-Aside Type
No Set-Aside Used
Extent Competed
Full and Open Competition
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Girdwood, Anchorage, AK, USA
Solicitation Procedures
Multiple Award, Fair Opportunity
Number Of Offers Received
2
Legislative Mandate
Service Contract Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- The Federal Highway Administration awarded a $22.5 million definitive contract to Glacier Construction Inc. for reconstruction of Neck Lake Road in Coffman Cove, Alaska on March 31, 2025, under firm fixed-price pricing with no set-aside. The originating pre-solicitation describes comprehensive roadway reconstruction including excavation, rock blasting, embankment, grading, drainage, retaining wall, and guardrail installation on a 1.6- to 2.4-mile segment located 45 miles northwest of Coffman...
- This federal contract was awarded by the Department of Transportation Federal Highway Administration to the prime contractor Missouri River Contractors, LLC for the rehabilitation of the Many Glacier Road in Montana. The contract is a definitive, firm fixed-price contract with a potential value of $18,452,739.48 and a completion date of November 19, 2021. The work involves road and bridge repairs, including concrete work, electrical installations, asphalt paving, masonry, and traffic control...
- This federal contract award, with a ceiling value of $22,562,108.17, was issued by the Federal Highway Administration to the Alaskan Native Corporation-owned small disadvantaged business Brice Civil Constructors, Inc. The contract involves the rehabilitation of the final 9.3 miles of the Going-to-the-Sun Road and replacement of the McDonald Creek bridge in Glacier National Park, Montana. The scope of work includes new steel girder bridge construction, removal of the existing bridge, earthwork,...
- The Department of Transportation Federal Highway Administration awarded a $4.4 million definitive contract to Granite Construction Company. The contract involves reconstruction of approximately 4.85 miles of Beaver Meadows Road within Rocky Mountain National Park in Colorado. Work will include full depth reclamation of the existing asphalt roadway, addition of 4 inches of new asphalt concrete, drainage improvements, and construction of 2,550 linear feet of colored concrete curb and gutter....
- Missouri River Contractors LLC has been awarded a definitive, firm-fixed price contract valued at $9,756,815.49 by the National Park Service to rehabilitate 13 bridges across three locations in Glacier National Park. Per the original solicitation, work will involve bridge deck and approach repair, timber pile replacement, sidewalk and curb replacement, painting, concrete repair, and other rehabilitation efforts over two construction seasons from 2022 through 2023. There was no set-aside...
- The Department of Transportation Federal Highway Administration awarded a $12.4 million firm fixed price contract to H-K Contractors, Inc. to perform improvements at the North Entrance of Yellowstone National Park in Montana. The solicitation sought offers for construction services including renovating entrance facilities, widening approximately 12 miles of roadways, and performing earthwork. Major subcontractors include Poteet Construction Inc. for concrete work and traffic control, Highmark...
- On March 10, 2022, the U.S. Department of Transportation Federal Highway Administration awarded a $15,198,486.33 firm fixed price contract to Ceccanti, Inc., a for-profit S corporation construction company, to relocate approximately 8 miles of utilities including a sewer force main, power, and phone lines along Lake McDonald Road in Glacier National Park, Montana. The work must be completed by June 5, 2023. This contract was competitively awarded on a full and open basis with no set-aside...
- Valley Fence Incorporated received a definitive contract valued at $4,655,616.80 from the Department of Transportation Federal Highway Administration to resurface the last four miles of Camas Road within Glacier National Park, Montana. The firm fixed price contract calls for asphalt concrete paving, sub-excavation, slide repair, turnout rehabilitation, curb and gutter installation, sidewalk construction, underdrain installation, ditch reconditioning, and signing and striping along the...
- The Federal Highway Administration (FHWA), part of the Department of Transportation (DOT), awarded a firm fixed price contract valued at $664,099.25 to Vine Laboratories Inc. to complete subsurface investigations at five sites along Many Glacier Road in Glacier National Park, Montana. The investigations will inform mitigation designs for landsliding at mileposts 4.9, 5.00-5.25, 6.55, 7.35, and Swift. Performance will take place in West Glacier, Montana from January 2022 through November 2023....
- The Department of Transportation Federal Highway Administration awarded a $661,461 firm fixed price construction contract to DSB Construction, LLC. The contract calls for DSB to perform construction services at the Big Bend site along Going-to-the-Sun Road in Glacier National Park, Montana, including a prefabricated concrete vault toilet, turnout modification, drainage, masonry, rockery walls, barriers, pathways, landscaping, culvert installation, and pavement removal. This contract was...
- AG0120C100007Indefinite Delivery Contract
- AG0120C100007-AG0120D110022Delivery Order
BYRON GLACIER ROAD CONSTRUCTION
Posted 9/23/11
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
Forest Engineering and Road Maintenance | AG-0120-S-10-0002 | Department of Agriculture Forest Service R10-Alaska Region | Award Notice 1/1 | 11/25/09, 5:03 PM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| 5 | Supplemental Agreement for work within scope | ($3k) | 8/5/12 | |
| 4 | Supplemental Agreement for work within scope | $34.8k | 6/4/12 | |
| 3 | Supplemental Agreement for work within scope | $25.4k | 2/22/12 | |
| 2 | Supplemental Agreement for work within scope | $42.6k | 12/19/11 | |
| 1 | Supplemental Agreement for work within scope | $33.8k | 10/24/11 |