Construction of a new US courthouse in greenville, MS

Ended Awarded Last action

Contract number
47PH0822F0016
Awardee
Awarding agency
Obligated
$49,569,391

Award facts

Opportunity
  • EQ7PCA220007 Solicitation number
Contract value 100% obligated
$49,569,391.02 Current and potential, with all options
Completion date 100% complete
  • Current, with exercised options
  • Potential, with all options
Contracting staff
Set-aside
No set-aside
Competition
Full and Open Competition · 4 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Greenville, MS, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change Order PC0033 · This modification definitizes PDL modification PC0027. The scope of work to be performed was to install smoke detectors in the elevator pits at the construction… $0
Change Order PC0032 · Modification PC0032 is for work necessary to complete the construction of the new u. S. Courthouse in greenville, MS as IT pertains to additional hardware for… $39,979
Definitize Change Order PC0031 · This MOD definitizes MOD PC0030 PDL for duct detectors and smoke beam work in the greenville courthouse, MS. -$805
Change Order PC0030 · PDL MOD to provide all labor, materials, equipment, transportation, and supervision necessary to perform the work in bulletin 36 revised (work associated with… $55,303
Change Order PC0029 · Definitize PDL MOD PC0026 for bulletin 37 scope requirements $196,486
Change Order PC0028 · The work includes cleaning after interior and exterior work, civil, concrete and SOD work, lowering the gates, install of metal handrails, carpentry, metal… $174,388
Change Order PC0027 · Add smoke detectors to the elevator pits $52,908
Change Order PC0026 · Partial SOW to be performed from bulletin 37 related to roofing, doors and hardware (doors 246 and 255), mechanical work and electrical work $244,304
Change Order PC0025 · Removal of plywood and installation of gypsum board extending 1 inch to 7 inch down from the soffits at the perimeter of 2ND and 3RD floor courtrooms… $107,691
Change Order PC0024 · Modification to add various pcos 27 -31, 33-34, and 37 construction signage, greenville, MS $134,258
Change Order PC0023 · Add various proposed changes as IT relates to bulletin 36, greenville courthouse, greenville, MS $286,247
Change Order PC0022 · Add bulletin 35 for court eagle signage, exterior emblem PCO 27 bulletin 35 signage change, switches and usdc AV, and elevator a.17 requirements RFI 741, etc to… $386,047
Change Order PC0021 · Add PCO 032 overhead door requirement, greenville, MS courthouse $72,800
Supplemental Agreement for work within scope PC0020 · Provide construction effort required to incorporate the custom fence corrugated panels, electrical changes related to RFI-564, RFI-565, RFI-594, RFI-604,… $246,374
Supplemental Agreement for work within scope PC0019 · No cost time extension of contract for the new US courthouse in greenville, MS. $0
Supplemental Agreement for work within scope PS0018 · Bulletin 34 (miscellaneous changes) & structured cabling clarifications for the new US courthouse in greenville, MS $246,371
Change Order PC0017 · No cost time extension of contract to 06/26/2025 for the new US courthouse in greenville, MS. $0
Supplemental Agreement for work within scope PS0016 · US marshals' service structured cabling and US district courts' signage at the US courthouse in greenville, MS $106,487
Supplemental Agreement for work within scope PS0015 · GSA structured cabling at the US courthouse in greenville, MS. $23,695
Change Order PC0014 · Add 46 days for weather delays from september-december 2022 and from april-june 2023 at the new US courthouse in greenville, MS. $0
Change Order PC0013 · Add 28 days for weather delays from january-march 2023 at the new US courthouse in greenville, MS $0
Supplemental Agreement for work within scope PS0012 · US district courts structured cabling at the new US courthouse in greenville, MS $246,203
Supplemental Agreement for work within scope PS0011 · Electrical, millwork, doors and signage at the new US courthouse in greenville, MS $249,883
Supplemental Agreement for work within scope PS0010 · Electrical work, signage, millwork and wage determination at the new US courthouse in greenville, MS $242,560
Supplemental Agreement for work within scope PS0009 · Window frame flashing & finish color schedule change for the new US courthouse in greenville, MS $299,205
Supplemental Agreement for work within scope PS0008 · Doors, architectural barriers work, turnstile & cell phone locker power at the new US courthouse in greenville, MS $60,853
Supplemental Agreement for work within scope PS0007 · A/v, electrical and communications at the new US courthouse in greenville, MS $85,978
Supplemental Agreement for work within scope PS0006 · Add mechanical and plumbing review comments for the new US courthouse in greenville, MS $82,659
Supplemental Agreement for work within scope PS0005 · US marshals' window, paint and underground storage tank removal at the new US courthouse in greenville, MS $68,746
Supplemental Agreement for work within scope PS0004 · Incorporate changes to landscaping, concrete site walls, and security gates at the new US courthouse, greenville, MS $388,502
Supplemental Agreement for work within scope PS0003 · Incorporate various value engineering design documents (light lens assembly, exterior metal panels, ceilings, millwork, bollards, etc.) for the new US… $163,661
Supplemental Agreement for work within scope PS0002 · Incorporate roof drain, judges parking & sallyport drainage, change dampers and envelope mockup for the new US courthouse in greenville, MS $0
Supplemental Agreement for work within scope PS0001 · Incorporate the awarded value engineering for switchboard with updated design documents for the US courthouse in greenville, MS $0
Original award $45,308,609
Show all 34

About this award

The General Services Administration Region 7 issued a delivery order to The Robins & Morton Group on March 29, 2022, with a ceiling value of $49.569 million for construction of a new U.S. Courthouse in Greenville, Mississippi. The order is issued under the GSA Region 7 General Construction with Design Build Capabilities IDIQ.

The GSA Region 7 IDIQ supports general construction and design-build services covering Texas, Arkansas, Louisiana, Oklahoma, and New Mexico, with secondary coverage across the continental United States. Place of performance is Greenville, MS. Ultimate completion is scheduled for June 25, 2026.

Modification PC0032 addresses work necessary to complete construction, specifically additional hardware for means of egress and security functionality. The contract is firm fixed-price with no set-aside. Robins & Morton has engaged subcontractors including Marathon Electrical Contractors for electrical work, TK Elevator Corporation for elevator installation, Serigraphics Sign Systems for signage, and a multi-vendor team for structural steel, plumbing and HVAC, roofing, fire sprinkler systems, drywall, flooring, glazing, landscaping, and access flooring.

Subawards

Subcontractor Amount Awarded
Serigraphics Sign Systems, Inc. ELECTRICAL WORK, SIGNAGE, MILLWORK AND WAGE DETERMINATION AT THE NEW US COURTHOUSE IN GREENVILLE, MS Signage $40,122
Serigraphics Sign Systems, Inc. US MARSHALS' SERVICE STRUCTURED CABLING AND US DISTRICT COURTS' SIGNAGE AT THE US COURTHOUSE IN GREENVILLE, MS Signage $55,641
Ambiance Landscape LLC ELECTRICAL WORK, SIGNAGE, MILLWORK AND WAGE DETERMINATION AT THE NEW US COURTHOUSE IN GREENVILLE, MS Landscaping $481,397
Ambiance Landscape LLC US MARSHALS' SERVICE STRUCTURED CABLING AND US DISTRICT COURTS' SIGNAGE AT THE US COURTHOUSE IN GREENVILLE, MS Landscaping $481,397
John Pendergast Consulting LLC ELECTRICAL WORK, SIGNAGE, MILLWORK AND WAGE DETERMINATION AT THE NEW US COURTHOUSE IN GREENVILLE, MS Access Flooring $83,479
John Pendergast Consulting LLC US MARSHALS' SERVICE STRUCTURED CABLING AND US DISTRICT COURTS' SIGNAGE AT THE US COURTHOUSE IN GREENVILLE, MS Access Flooring $83,479
Rain Harvest Systems II LLC US MARSHALS' SERVICE STRUCTURED CABLING AND US DISTRICT COURTS' SIGNAGE AT THE US COURTHOUSE IN GREENVILLE, MS Cisterns $189,923
Rain Harvest Systems II LLC ELECTRICAL WORK, SIGNAGE, MILLWORK AND WAGE DETERMINATION AT THE NEW US COURTHOUSE IN GREENVILLE, MS Cisterns $185,557
Vulcan Fabricated Metals, Inc. CONSTRUCTION OF A NEW US COURTHOUSE IN GREENVILLE, MS Structural Steel $4,256,200
Rec Construction, LLC ELECTRICAL WORK, SIGNAGE, MILLWORK AND WAGE DETERMINATION AT THE NEW US COURTHOUSE IN GREENVILLE, MS Concrete Forming $1,042,498
Rec Construction, LLC US MARSHALS' SERVICE STRUCTURED CABLING AND US DISTRICT COURTS' SIGNAGE AT THE US COURTHOUSE IN GREENVILLE, MS Concrete Forming $1,042,498
DRP Masonry LLC CONSTRUCTION OF A NEW US COURTHOUSE IN GREENVILLE, MS Masonry $1,703,549
Subcontractor not on record US MARSHALS' SERVICE STRUCTURED CABLING AND US DISTRICT COURTS' SIGNAGE AT THE US COURTHOUSE IN GREENVILLE, MS Site Access Roads $196,092
Subcontractor not on record ELECTRICAL WORK, SIGNAGE, MILLWORK AND WAGE DETERMINATION AT THE NEW US COURTHOUSE IN GREENVILLE, MS Site Access Roads $147,250
Subcontractor not on record US MARSHALS' SERVICE STRUCTURED CABLING AND US DISTRICT COURTS' SIGNAGE AT THE US COURTHOUSE IN GREENVILLE, MS Earthwork $1,929,063
Subcontractor not on record ELECTRICAL WORK, SIGNAGE, MILLWORK AND WAGE DETERMINATION AT THE NEW US COURTHOUSE IN GREENVILLE, MS Earthwork $46,383
Smith-Midland Corporation CONSTRUCTION OF A NEW US COURTHOUSE IN GREENVILLE, MS Slenderwall $1,751,631
Smith-Midland Corporation ELECTRICAL WORK, SIGNAGE, MILLWORK AND WAGE DETERMINATION AT THE NEW US COURTHOUSE IN GREENVILLE, MS Slenderwall Fabrication $1,693,618
Smith-Midland Corporation US MARSHALS' SERVICE STRUCTURED CABLING AND US DISTRICT COURTS' SIGNAGE AT THE US COURTHOUSE IN GREENVILLE, MS Slenderwall Fabrication $1,971,671
Southern Carpet, Hardwood & Tile, Inc. ELECTRICAL WORK, SIGNAGE, MILLWORK AND WAGE DETERMINATION AT THE NEW US COURTHOUSE IN GREENVILLE, MS Flooring $399,277
Southern Carpet, Hardwood & Tile, Inc. US MARSHALS' SERVICE STRUCTURED CABLING AND US DISTRICT COURTS' SIGNAGE AT THE US COURTHOUSE IN GREENVILLE, MS Flooring $401,432
Durwood Construction LLC CONSTRUCTION OF A NEW US COURTHOUSE IN GREENVILLE, MS Drywall $3,209,959
Subcontractor not on record US MARSHALS' SERVICE STRUCTURED CABLING AND US DISTRICT COURTS' SIGNAGE AT THE US COURTHOUSE IN GREENVILLE, MS Casework $2,008,845
Subcontractor not on record ELECTRICAL WORK, SIGNAGE, MILLWORK AND WAGE DETERMINATION AT THE NEW US COURTHOUSE IN GREENVILLE, MS Casework $1,995,296
Subcontractor not on record CONSTRUCTION OF A NEW US COURTHOUSE IN GREENVILLE, MS Millwork $2,064,104
Andreola Terrazzo & Restoration, Inc. ELECTRICAL WORK, SIGNAGE, MILLWORK AND WAGE DETERMINATION AT THE NEW US COURTHOUSE IN GREENVILLE, MS Terrazzo Flooring $481,948
Andreola Terrazzo & Restoration, Inc. US MARSHALS' SERVICE STRUCTURED CABLING AND US DISTRICT COURTS' SIGNAGE AT THE US COURTHOUSE IN GREENVILLE, MS Terrazzo Flooring $481,948
Durwood Construction LLC ELECTRICAL WORK, SIGNAGE, MILLWORK AND WAGE DETERMINATION AT THE NEW US COURTHOUSE IN GREENVILLE, MS Drywall $3,296,683
Durwood Construction LLC US MARSHALS' SERVICE STRUCTURED CABLING AND US DISTRICT COURTS' SIGNAGE AT THE US COURTHOUSE IN GREENVILLE, MS Drywall $3,577,518
Apex Building Co LLC US MARSHALS' SERVICE STRUCTURED CABLING AND US DISTRICT COURTS' SIGNAGE AT THE US COURTHOUSE IN GREENVILLE, MS Air & Vapor Barrier $360,628
Apex Building Co LLC ELECTRICAL WORK, SIGNAGE, MILLWORK AND WAGE DETERMINATION AT THE NEW US COURTHOUSE IN GREENVILLE, MS Air & Vapor Barrier $324,707
Basesix Systems LLC ELECTRICAL WORK, SIGNAGE, MILLWORK AND WAGE DETERMINATION AT THE NEW US COURTHOUSE IN GREENVILLE, MS Intrusion Detection $368,486
Basesix Systems LLC US MARSHALS' SERVICE STRUCTURED CABLING AND US DISTRICT COURTS' SIGNAGE AT THE US COURTHOUSE IN GREENVILLE, MS Intrusion Detection $368,486
Subcontractor not on record ELECTRICAL WORK, SIGNAGE, MILLWORK AND WAGE DETERMINATION AT THE NEW US COURTHOUSE IN GREENVILLE, MS Security $536,636
Subcontractor not on record US MARSHALS' SERVICE STRUCTURED CABLING AND US DISTRICT COURTS' SIGNAGE AT THE US COURTHOUSE IN GREENVILLE, MS Security $545,036
Subcontractor not on record CONSTRUCTION OF A NEW US COURTHOUSE IN GREENVILLE, MS Security $571,801
Oaks Brothers Inc. ELECTRICAL WORK, SIGNAGE, MILLWORK AND WAGE DETERMINATION AT THE NEW US COURTHOUSE IN GREENVILLE, MS Lath & Plaster $80,597
Oaks Brothers Inc. US MARSHALS' SERVICE STRUCTURED CABLING AND US DISTRICT COURTS' SIGNAGE AT THE US COURTHOUSE IN GREENVILLE, MS Lath & Plaster $97,213
United Piping, Inc. ELECTRICAL WORK, SIGNAGE, MILLWORK AND WAGE DETERMINATION AT THE NEW US COURTHOUSE IN GREENVILLE, MS Fire Sprinklers $458,176
United Piping, Inc. US MARSHALS' SERVICE STRUCTURED CABLING AND US DISTRICT COURTS' SIGNAGE AT THE US COURTHOUSE IN GREENVILLE, MS Fire Sprinklers $458,176
Sauder Manufacturing Co ELECTRICAL WORK, SIGNAGE, MILLWORK AND WAGE DETERMINATION AT THE NEW US COURTHOUSE IN GREENVILLE, MS Pews & Benches $67,316
Sauder Manufacturing Co US MARSHALS' SERVICE STRUCTURED CABLING AND US DISTRICT COURTS' SIGNAGE AT THE US COURTHOUSE IN GREENVILLE, MS Pews & Benches $39,590
Willoughby Roofing & Sheet Metal Inc. ELECTRICAL WORK, SIGNAGE, MILLWORK AND WAGE DETERMINATION AT THE NEW US COURTHOUSE IN GREENVILLE, MS Roofing $1,186,110
Willoughby Roofing & Sheet Metal Inc. US MARSHALS' SERVICE STRUCTURED CABLING AND US DISTRICT COURTS' SIGNAGE AT THE US COURTHOUSE IN GREENVILLE, MS Roofing $1,265,830
Willoughby Roofing & Sheet Metal Inc. CONSTRUCTION OF A NEW US COURTHOUSE IN GREENVILLE, MS Roofing $1,009,225
Abba Contract, Inc. ELECTRICAL WORK, SIGNAGE, MILLWORK AND WAGE DETERMINATION AT THE NEW US COURTHOUSE IN GREENVILLE, MS Window Shades $50,000
Abba Contract, Inc. US MARSHALS' SERVICE STRUCTURED CABLING AND US DISTRICT COURTS' SIGNAGE AT THE US COURTHOUSE IN GREENVILLE, MS Window Shades $50,000
Berkel & Company Contractors Inc. US MARSHALS' SERVICE STRUCTURED CABLING AND US DISTRICT COURTS' SIGNAGE AT THE US COURTHOUSE IN GREENVILLE, MS Grout Piles $480,670
Residential Acoustics, LLC ELECTRICAL WORK, SIGNAGE, MILLWORK AND WAGE DETERMINATION AT THE NEW US COURTHOUSE IN GREENVILLE, MS Acoustic Panels $145,889
Landmark Bird Control LLC ELECTRICAL WORK, SIGNAGE, MILLWORK AND WAGE DETERMINATION AT THE NEW US COURTHOUSE IN GREENVILLE, MS Bird Control $24,121
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

Quick answers

Who was awarded contract 47PH0822F0016?

47PH0822F0016 was awarded to The Robins & Morton Group by Region 7 (Public Buildings Service) on March 29, 2022.

How much is contract 47PH0822F0016 worth?

The government has obligated $49,569,391 on 47PH0822F0016.

Is contract 47PH0822F0016 an order under another contract?

Yes. 47PH0822F0016 is a delivery order under 47PH0821D0009, an indefinite delivery contract, on Region 7 General Construction with Design Build Capabilities IDIQ.

Was contract 47PH0822F0016 competed?

The extent of competition for 47PH0822F0016 was full and open competition. The government received 4 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award