Task order: 2031JG18D00005/2031JG23F00303-chiller replacement-united states mint-philadelphia
Ended Awarded Last action
- Contract number
- 2031JG23F00303
- Awardee
-
Lorenzon Construction, Inc. UEI VTFETK1MEMM7
- Awarding agency
-
United States Mint
Department of the Treasury
- Obligated
- $5,837,637
Award facts
- Contract value 100% obligated
- $5,837,636.81 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- Contracting staff
- NAICS code
- 236210 Industrial Building Construction
- Set-aside
- No set-aside
- Competition
- Full and Open Competition Negotiated Proposal / Quote
- Pricing
- Firm Fixed Price
- Place of performance
- Philadelphia, PA 19118, USA
- Legislative mandates
-
- Service Contract Act FAR subpart 22.10
- Davis-Bacon Act FAR subpart 22.4
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Supplemental Agreement for work within scope | $99,444 | |
| Supplemental Agreement for work within scope | $18,630 | |
| Supplemental Agreement for work within scope | $50,972 | |
| Other Administrative Action | -$4,152 | |
| Supplemental Agreement for work within scope | $258,300 | |
| Other Administrative Action | $0 | |
| Supplemental Agreement for work within scope | $757,568 | |
| Supplemental Agreement for work within scope | $3,565,695 | |
| Other Administrative Action | $0 | |
| Original award | $1,091,180 |
About this award
Lorenzon Construction, Inc., doing business as Lorenzon Brothers Company, received a firm fixed-price delivery order valued at $5.84 million from the United States Mint for chiller replacement work at the Philadelphia Mint facility. Awarded on August 18, 2023, with an ultimate completion date of September 27, 2026, this task order was issued under the Philadelphia Mint Renovation Multiple-Award Indefinite Delivery/Indefinite Quantity (IDIQ) contract. The scope of work encompasses relocation of the cooling towers skid, furnish and installation of two cooling tower isolation valves, installation of heat trace controllers required for system integration, and installation of chemical treatment piping. No small business set-aside designation was applied to this award.
Lorenzon Construction has established itself as the primary facilities management and renovation contractor for the U.S. Mint's Philadelphia operations, with a demonstrated track record of managing complex infrastructure projects across the facility. The Treasury Department contractor, based in Wyndmoor, Pennsylvania, holds two significant IDCs with the Mint totaling approximately $23.7 million for renovation and facilities support services at multiple Pennsylvania locations. This chiller replacement project represents a critical infrastructure upgrade supporting the Mint's operational requirements, with Lorenzon Construction performing the work directly as the prime contractor without subcontractor involvement, consistent with the company's historical contract performance.
Quick answers
Who was awarded contract 2031JG23F00303?
2031JG23F00303 was awarded to Lorenzon Construction, Inc. by United States Mint (Department of the Treasury) on August 18, 2023.
How much is contract 2031JG23F00303 worth?
The government has obligated $5,837,637 on 2031JG23F00303.
Is contract 2031JG23F00303 an order under another contract?
Yes. 2031JG23F00303 is a delivery order under 2031JG18D00005, an indefinite delivery contract.
Was contract 2031JG23F00303 competed?
The extent of competition for 2031JG23F00303 was full and open competition.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award