Recoveryproject#::006100::RP# FOX point hurricane barrier, refurbish the severely damaged pump #5

Ended Definitive Contract Awarded Last action

Contract number
W912WJ10C0013
Awardee
Awarding agency
Obligated
$3,055,699

Award facts

Contract value 100% obligated
$3,055,698.69 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 4 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Providence, RI 02903, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change Order P00008 · Arra::yes::arrarecoveryproject#:: A1775::RP# pump no. 5 overhaul, FOX point, RI $3,034
Change Order A00008 · Time extension $0
Change Order A00007 · Metal stitching and fabricate new lower bearing and additinal repairs for pump 1. $111,000
Other Administrative Action P00007 · Rehabilitate pump number 5 $0
Change Order A00006 · River gate gear box, pump number 5 overhaul, FOX point RI $35,054
Change Order A00005 · Rehabilitate pump number 5 overhaul, FOX point RI $96,939
Supplemental Agreement for work within scope A00004 $45,581
Change Order A00003 $27,875
Change Order A00002 · Rehabilitate pump number 5 $62,418
Change Order A00001 · Rehabilitate pump number 5 remove lead paint $50,000
Change Order P00006 · Rehabilitate pump number 5 $292,336
Supplemental Agreement for work within scope P00005 · Rehabilitate pump number 1 - add previously ommitted clause. $0
Supplemental Agreement for work within scope P00004 · Repairs to the stop gate lifting beam assembly and replacement of the sump pump in the dewatering chamber, FOX point hurricane barrier, providence, RI. $14,000
Supplemental Agreement for work within scope P00003 · Arra::yes::arra recoveryproject#::006100::RP# project title: FOX point hurricane barrier, providence, rhode island, pump 5 overhaul. Remove obstructions from… $1,118,310
Change Order P00002 · Recoveryproject#::006100::RP# FOX point hurricane barrier, repairs to 40-ton overhead crane $12,378
Supplemental Agreement for work within scope P00001 $4,500
Original award $1,182,275
Show all 17

About this award

This is a $3,055,698.69 Firm Fixed Price contract awarded by the U.S. Army Corps of Engineers' New England District (ENDIST New England) to Chas G. Allen Incorporated, a small business manufacturer, to refurbish the severely damaged Pump #5 at the Fox Point Hurricane Barrier in Providence, Rhode Island. The contract does not have a set-aside designation. Chas G. Allen Incorporated specializes in infrastructure construction, maintenance, and repair services for the Army Corps of Engineers, including past projects to support the agency's flood risk management and environmental programs. This contract supports the ENDIST New England's recovery efforts for the Fox Point Hurricane Barrier, a critical flood control system.

Quick answers

Who was awarded contract W912WJ10C0013?

W912WJ10C0013 was awarded to Chas G. Allen Incorporated by ENDIST New England (US Army Corps of Engineers) on April 27, 2010.

How much is contract W912WJ10C0013 worth?

The government has obligated $3,055,699 on W912WJ10C0013.

Was contract W912WJ10C0013 competed?

The extent of competition for W912WJ10C0013 was full and open competition. The government received 4 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award