Repair telecommunications facility, b-2005, suwon AB

Ended Definitive Contract Awarded Last action

Contract number
W912UM23C0007
Awardee
Awarding agency
Obligated
$3,899,239

Award facts

Opportunity
  • W912UM23B0002 Solicitation number
Contract value 100% obligated
$3,899,238.88 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
No set-aside
Competition
Full and Open Competition · 9 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
South Korea
Defense program
Status of Forces Agreement

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00008 · Repair telecommunications facility, b-2005, suwon air base, korea - C.I.#014, #015 : add bonding / grounding for 800A ECB, TCF RM 106 attic sprinkler - add… $10,486
Supplemental Agreement for work within scope A00007 · C.i# CR010, replace door & hardware c.i# CR011, install two dampers / power line c.i# CR012, provide access hatch/visual indicators c.i# CR013, install new… $44,322
Supplemental Agreement for work within scope A00006 · C.i #CR009, time extension for government delay #2 repair telecommunications facility, b-20 $86,661
Supplemental Agreement for work within scope A00005 · C.i #CR008, replace TCF room window & ceiling tiles repair telecommunications facility, b-20 $16,343
Supplemental Agreement for work within scope A00004 · C.i #CR002, provide drywall finish c.i ECR007, remaining existing concrete ceiling slab repair telecommunications facility, b-20 $0
Supplemental Agreement for work within scope A00003 · C.i #CR006, remove rust & paint in lieu of replace repair telecommunications facility, b-20 -$181,351
Supplemental Agreement for work within scope A00002 · C.i #CRO01, change off-shore wall panels to local -$23,096
Supplemental Agreement for work within scope A00001 · C.i #CRO05, time extension for government delays $0
Original award $3,945,874

About this award

ENDIST Far East awarded a $3.9 million definitive contract to Seohai Construction Co., Ltd. for repair of telecommunications facility B-2005 at Suwon Air Base, South Korea, on July 13, 2023, under firm fixed-price terms with no set-aside.

The originating solicitation covers repair of telecommunications facility B-2005 at Suwon Air Base, including bonding and grounding work for an 800-ampere electrical control box in TCF Room 106 and attic sprinkler additions. Work is performed at Suwon Air Base, South Korea. The ultimate completion date is August 15, 2025. The contract ceiling value is $3,899,238.88. The contract is funded under the Status of Forces Agreement (SOFA) acquisition program, which encompasses construction, maintenance, and infrastructure improvements at U.S. military installations operating under host nation agreements.

Quick answers

Who was awarded contract W912UM23C0007?

W912UM23C0007 was awarded to Seohai Construction Co.,Ltd. by ENDIST Far East (US Army Corps of Engineers) on July 13, 2023.

How much is contract W912UM23C0007 worth?

The government has obligated $3,899,239 on W912UM23C0007. Its current value, with exercised options, is $3,899,239.

Was contract W912UM23C0007 competed?

The extent of competition for W912UM23C0007 was full and open competition. The government received 9 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award