Contract is for the renovation and construction of building 254 at wpafb, OH

Ended Definitive Contract Awarded Last action

Contract number
W912QR18C0008
Awardee
Awarding agency
Obligated
$15,412,528

Award facts

Opportunity
Contract value 100% obligated
$15,412,528.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 3 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
WPAFB, OH 45433, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00031 $3,600
Supplemental Agreement for work within scope A00030 · Base proposal $304,000
Supplemental Agreement for work within scope A00029 · CR 0031 ACS & IDS phase II, install new card readers, motion sensors and monitoring stations afrl offices F20254 $178,000
Supplemental Agreement for work within scope A00028 · CR 0020 server room 145/145A, CR 0023, omit marker boards, CR 0027, chiller expansion tank installation, CR 0028, duct penetration, CR 0033, fire alarm phase i $51,000
Other Administrative Action P00002 · Admin MOD to change address from original award to match current address listed in SAM registration for the contractor. $0
Supplemental Agreement for work within scope A00027 · Case 0030 fiber connections wright patterson AFB OH $380,000
Supplemental Agreement for work within scope A00026 · Case 0019 - google room revisions and case 0026 - power & lighting revisions phase II, wright patterson AFB, OH. $225,000
Supplemental Agreement for work within scope A00025 · CR005 fire alarm phase II, CR 0029 sprinkler head replacement afrl offices F20254, wpafb, OH $219,000
Supplemental Agreement for work within scope A00024 · Case 0032 - reprogramming time impace $475,000
Supplemental Agreement for work within scope A00023 · Case 0017 - phase II duct obstructions, part 2 - final, wpafb, OH. $84,500
Supplemental Agreement for work within scope A00022 · Base proposal $33,000
Supplemental Agreement for work within scope A00021 · CR 018 floor tile abatement - renovate construct afrl offices F20254 $13,800
Supplemental Agreement for work within scope A00020 · CR 015 engineering revisions - renovate afrl offices F20254 $34,500
Change Order A00019 · CR 017 phase II duct obstructions, part i NTP - trace and relocate active lines, relocation of FP line and power raceways - renovate construct afrl F20254 $30,000
Supplemental Agreement for work within scope A00018 · CR 007 sprinkler system revisions - bldg 254 $168,000
Supplemental Agreement for work within scope A00017 · Base proposal $205,000
Supplemental Agreement for work within scope A00016 · CR 014 gas & sewer utilites - provide gas service connection and revise layout of sewer line afrl offices F20254 $80,000
Supplemental Agreement for work within scope A00015 $450,000
Supplemental Agreement for work within scope A00014 $235,000
Supplemental Agreement for work within scope A00013 $29,700
Supplemental Agreement for work within scope A00011 $6,500
Supplemental Agreement for work within scope A00010 · Base proposal $68,000
Supplemental Agreement for work within scope A00009 · CR 06-2 foundation changes part II final to A00003, revise reinforcing steel, afrl offices F20254, wpafb, OH $74,597
Supplemental Agreement for work within scope A00008 · CR 010-2 remove existing foundation slab, part II final, remove reinforced concrete slab, renovate construct afrl, offices F20254 $131,000
Supplemental Agreement for work within scope A00007 · CR 04 crack injection - repair cracks on interior surfaces, renovate construct afrl offices F20254 $28,000
Supplemental Agreement for work within scope A00006 · Base proposal $41,473
Change Order A00005 · Case 10 remove existing foundation slab, part i NTP - remove existing reinforced concrete slab as shown on sketch - renovate construct afrl offices F20254,… $50,000
Supplemental Agreement for work within scope A00004 $14,858
Change Order A00003 $8,000
Supplemental Agreement for work within scope A00002 · Base proposal $110,000
Change Order A00001 · Case 002-1 existing conditions coordination, part i NTP, electrical changes to design, renovate construct afrl offices F202054 $70,000
Other Administrative Action P00001 · Notice-to-proceed modification for the building 254 project at wpafb, OH. $0
Original award $11,611,000
Show all 33

About this award

This is a firm fixed price contract awarded by the U.S. Army Corps of Engineers Engineering District Louisville to Messer Construction Co., doing business as Frank Messer & Sons Construction Co., for the renovation and construction of Building 254 at Wright-Patterson Air Force Base (WPAFB) in Ohio. The contract has a potential value of $15,412,528.00 and was awarded on December 8, 2017, with a completion date of January 21, 2021. The contract does not have a set-aside designation. Messer Construction Co. is a for-profit, Subchapter S corporation construction management and general contracting firm that has been awarded numerous prime federal contracts from agencies such as the U.S. Army Corps of Engineers and United States Special Operations Command for construction services supporting mission-critical infrastructure and facilities at military bases across multiple states.

Quick answers

Who was awarded contract W912QR18C0008?

W912QR18C0008 was awarded to Messer Construction Co by ENDIST Louisville (US Army Corps of Engineers) on December 8, 2017.

How much is contract W912QR18C0008 worth?

The government has obligated $15,412,528 on W912QR18C0008.

Was contract W912QR18C0008 competed?

The extent of competition for W912QR18C0008 was full and open competition. The government received 3 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award