Contract is for the construction of an at/MOB dining facility at FT. Mccoy, WI.

Ended Definitive Contract Awarded Last action

Contract number
W912QR18C0002
Awardee
Awarding agency
Obligated
$13,595,157

Award facts

Opportunity
Contract value 97% obligated
  • $13,595,157.00 Current, with exercised options
  • $13,944,157.00 Potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 3 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Fort McCoy, WI 54656, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00015 $0
Supplemental Agreement for work within scope A00014 · Base proposal - additional funding $740
Change Order A00013 · CR 012-2 FY17 PA speaker system, part i supplement $19,456
Change Order A00012 · Case 0014-1 - hot water tank NTP, FY17 atmob dinning facility, fort mccoy WI. $7,084
Supplemental Agreement for work within scope A00011 $2,600
Supplemental Agreement for work within scope A00010 · Base proposal - additional funding $23,623
Supplemental Agreement for work within scope A00009 · Case 0010 (R00010) " additional bollards and tile, fort mccoy WI $12,127
Supplemental Agreement for work within scope A00008 · Base proposal - additional funding $17,328
Supplemental Agreement for work within scope A00007 · Case 0009 - miscellaneous modifications, FY17 at/MOB dfac fort mccoy, WI $16,718
Supplemental Agreement for work within scope A00006 · Base proposal - additional funding $9,508
Supplemental Agreement for work within scope A00005 · Case 00007 air barrier revisions; case 00002 ASI changes, annual training/mobilization (at/MOB) dining facility, FT. Mccoy, WI $71,151
Supplemental Agreement for work within scope A00004 · Case 004-delete asphalt paving south parking lot - delete saw cutting, heavy duty asphalt paving, milling and overlay for south parking lot - at/MOB dining… -$103,637
Supplemental Agreement for work within scope A00003 · Case 003, water service conflict & water main bore, modify exterior pipe layout and change material, fort mccoy at/MOB dining facility, fort mccoy, WI $5,776
Supplemental Agreement for work within scope A00002 $46,083
Supplemental Agreement for work within scope A00001 $0
Exercise an Option P00002 · Base proposal - additional funding $12,200
Other Administrative Action P00001 · NTP MOD for the construction of an at/MOB dining facility at FT. Mccoy, WI $0
Original award $13,454,400
Show all 18

About this award

The Department of the Army Corps of Engineers Engineering District Louisville awarded a Firm Fixed Price contract to L.S. Black Constructors, LLC, doing business as L.S. Black and Dew, for the construction of an Annual Training/Mobilization (AT/MOB) Dining Facility at Fort McCoy, Wisconsin. The contract, valued at $13,944,157.00, does not have a set-aside designation. The project includes construction of the dining facility, as well as supporting infrastructure such as paving, utilities, and force protection measures. L.S. Black Constructors has experience working as a prime contractor on various military construction projects for the Army, Navy, and Air Force.

Quick answers

Who was awarded contract W912QR18C0002?

W912QR18C0002 was awarded to L.s. Black Constructors, LLC by ENDIST Louisville (US Army Corps of Engineers) on October 19, 2017.

How much is contract W912QR18C0002 worth?

The government has obligated $13,595,157 on W912QR18C0002. Its potential value, with all options, is $13,944,157.

Was contract W912QR18C0002 competed?

The extent of competition for W912QR18C0002 was full and open competition. The government received 3 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award