FY15 army family housing at rock island arsenal, IL - award of base and options 01 - 04.

Ended Definitive Contract Awarded Last action

Contract number
W912QR16C0018
Awardee
Awarding agency
Obligated
$24,472,380

Award facts

Opportunity
Contract value 100% obligated
$24,472,379.89 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 5 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Rock Island, IL 61299, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00015 · Case 051 final rock quantity - option 5 final quantity case 52- porch handrail and asphalt delete porch handrail and asphalt. FHY15 RIA family housing -$182,529
Supplemental Agreement for work within scope A00014 $105,344
Supplemental Agreement for work within scope A00013 · Base proposal - construction of 33 homes -$2,732
Supplemental Agreement for work within scope P00003 · Case 44, lift station, install new sanitary sewer lift station and forced main, FY15 RIA family housing, rock island, IL $416,403
Supplemental Agreement for work within scope A00012 · Case 042 move hrvs and dehumidifiers out of garage into attic of garage, design/build army family housing (FY15), rock island arsenal, IL $225,850
Supplemental Agreement for work within scope A00011 · Case 00043 add 2" round vent between mechanical room and house, design/build army family housing project (FY15), rock island arsenal, IL $7,963
Supplemental Agreement for work within scope A00010 · Case 045 install carpet pad and tack strips, FY16 army family housing project, rock island arsenal, IL $14,453
Supplemental Agreement for work within scope A00009 · Base proposal - construction of 33 homes $70,889
Supplemental Agreement for work within scope A00008 · Case 017 delete ground on service line; case 028 bathroom & smoke detector circuits; case 030 pavement patching; case 038 delete sidewalk & grating,… $24,654
Supplemental Agreement for work within scope A00007 · Base proposal - construction of 33 homes $116,337
Supplemental Agreement for work within scope A00006 · Case 013 house elevations, driveways, and grading, design/build army family housing (FY15), rock island arsenal, IL $334,443
Supplemental Agreement for work within scope A00005 · Case 032 tie curb & gutter to roadway, design/build army family housing (FY15), rock island arsenal, IL $68,423
Supplemental Agreement for work within scope A00004 · Case 014 relocate gas main; case 016 reuse bus stop shelter, army family housing project, rock island arsenal, IL -$12,985
Supplemental Agreement for work within scope A00003 · Case 026 undercut roadway second area; case 027 undercut roadway third area, design/build army family housing project, rock island arsenal, IL $112,962
Supplemental Agreement for work within scope A00002 · Case 023 remove unsuitable soil, install geotextile fabric and place aggregate, design/build army family housing, rock island arsenal, IL $115,988
Supplemental Agreement for work within scope A00001 · Case 003 building coordinates; case 005 abandon existing well; case 007 remove fence & wall; case 008 remove & REP0LACE TOT lot; case 009 pave playground… $11,918
Exercise an Option P00002 · Exercise option, additional rock excavation. $208,000
Other Administrative Action P00001 · This is the notice to proceed (NTP) for the FY15 army family housing project at rock island arsenal, IL. $0
Original award $22,837,000
Show all 19

About this award

This is a $24,472,379.89 firm fixed-price definitive contract awarded by the U.S. Army Corps of Engineers to Debcon Inc., a small business, for the Fiscal Year 2015 Army Family Housing project at Rock Island Arsenal in Illinois. The contract includes a base period and four option periods with a total completion date of September 3, 2018. As a small business set-aside contract, it supports the Army's efforts to provide quality family housing for military personnel stationed at the Rock Island Arsenal.

Quick answers

Who was awarded contract W912QR16C0018?

W912QR16C0018 was awarded to Debcon Inc. by ENDIST Louisville (US Army Corps of Engineers) on August 18, 2016.

How much is contract W912QR16C0018 worth?

The government has obligated $24,472,380 on W912QR16C0018.

Was contract W912QR16C0018 competed?

The extent of competition for W912QR16C0018 was full and open competition after exclusion of sources. The government received 5 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award