Addition / alteration of the FME laboratory at wpafb, OH

Ended Definitive Contract Awarded Last action

Contract number
W912QR15C0012
Awardee
Awarding agency
Obligated
$27,230,403

Award facts

Opportunity
Contract value 100% obligated
$27,230,403.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 3 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
WPAFB, OH 45433, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00029 · Wpafb, FME lab - base $180,868
Supplemental Agreement for work within scope A00028 · CR 048 canopy to remain - delete requirement to remove canopy. Wpafb, FME lab - base -$7,948
Supplemental Agreement for work within scope A00027 · CR 047-REA gate closure - compensation for closure of gate wpafb, FME lab - base $71,124
Supplemental Agreement for work within scope A00026 $2,773
Supplemental Agreement for work within scope A00025 · Wpafb, FME lab - base $217,059
Supplemental Agreement for work within scope A00024 · Case 36, differing site at 4023, reroute ground wire in corridor 505, remove light switch and reroute receptacle, add/alter foreign materials exploitation… $9,928
Supplemental Agreement for work within scope A00023 · Case 44, sound rated rooms-install rubber strip change wall type. Case 46, EMR room cooling - install ductless air conditioning system, add/alter foreign… $168,960
Change Order A00022 · Wpafb, FME lab - base $18,056
Additional Work (new agreement, FAR part 6 applies) P00004 · FF & e modification wpafb, FME lab - base $252,414
Supplemental Agreement for work within scope A00019 · Case 035 differing site condition at republic road; case 038 security control area; case 042 divider curtain conflict, addition/alteration of foreign… $69,879
Supplemental Agreement for work within scope A00018 · Case 039 delete mill and overlay; case 045 install 6" metal conduit, add/alter foreign materials exploitation laboratory, wright-patterson AFB, OH -$13,578
Supplemental Agreement for work within scope A00017 · Case 031 RF filters; case 037 power to split cooling system; case 043 landscaping at connecting corridor, add/alter foreign materials exploitation laboratory,… $108,490
Supplemental Agreement for work within scope A00016 · Case 033, split cooling unit piping, add/alter foreign materials exploitation laboratory, wright-patterson AFB, OH $68,656
Supplemental Agreement for work within scope A00015 · Case 025 access control doors 501 & 505; case 026 perimeter interior paint ICD 705; case 028 roof detail at gable ends, add/alter foreign materials exploitation… $18,920
Change Order A00014 · Case 0030 DDC for lighting controls, part 1 notice to proceed, add/alter foreign materials exploitation laboratory, wright-patterson AFB. OH $2,500
Supplemental Agreement for work within scope A00013 · Case 032 non-compensable time extension, add/alter foreign materials exploitation laboratory, wright-patterson AFB, OH $0
Supplemental Agreement for work within scope A00012 · Case 027 time extension due to weather delays, addition/alteration of foreign materials exploitation laboratory, wright-patterson AFB, OH $0
Supplemental Agreement for work within scope A00011 · Case 020 highbay shaftwall changes; case 021 move water service valve, add/alter foreign materials exploitation laboratory, wright-patterson AFB, OH -$23,402
Supplemental Agreement for work within scope A00010 · Wpafb, FME lab - base -$994
Supplemental Agreement for work within scope A00009 · Case 0019 remove & dispose of unsuitable materials at mustang drive, addition/alteration foreign materials exploitation laboratory, wright-patterson AFB, OH $10,000
Supplemental Agreement for work within scope A00008 · Case 0018 substitute aggregate base for drainage layer, addition/alteration of foreign materials exploitation laboratory, wright-patterson AFB, OH -$25,277
Supplemental Agreement for work within scope A00007 · Case 0017 remove asbestos-laden abandoned steam pipe, addition/alteration of foreign materials exploitation laboratory, wright-patterson AFB, OH $12,306
Supplemental Agreement for work within scope A00006 · Case 009 delete requirement for curtain infill panels, provide additional steel supports and divider curtains, addition/alteration of foreign materials… $41,630
Supplemental Agreement for work within scope A00005 · Case 004 reroute water line, addition/alteration foreign materials exploitation laboratory, wright-patterson AFB, OH $9,376
Supplemental Agreement for work within scope A00004 · Case 006 provide floor box system mini towers; case 007 REA for unsuitable soils encountered in area a, addition/ alteration of foreign materials exploitation… $153,870
Exercise an Option P00003 · Wpafb, FME lab - exercise options 1, 1-b, 2, 4, 5, and 7 $1,479,000
Supplemental Agreement for work within scope A00003 · Case 003 site plan changes, add/alter foreign materials exploitation laboratory, wright-patterson AFB, OH -$20,702
Supplemental Agreement for work within scope A00002 · Case 005 remove abandoned steam lines, addition/alteration foreign materials exploitation laboratory, wright-patterson AFB, OH $30,777
Change Order A00001 · Case 002 - additional fire riser wpafb, FME lab - base $14,718
Exercise an Option P00002 · Modification to exercise option 3 wpafb, FME lab $15,000
Exercise an Option P00001 · Exercise option 6 security trailer wpafb, FME lab $200,000
Original award $24,166,000
Show all 32

About this award

This is a $27,230,403 firm-fixed-price definitive contract awarded by the U.S. Army Corps of Engineers to Messer Construction Co, a for-profit Subchapter S Corporation, for the addition and alteration of the FME Laboratory at Wright-Patterson Air Force Base in Ohio. The contract has no set-aside designation and was awarded through full and open competition. Messer Construction Co is a well-established construction management and general contracting firm with a strong track record of executing significant federal construction projects, particularly for defense agencies and military installations. The contract work involves comprehensive construction and renovation services for the FME Laboratory facility at Wright-Patterson Air Force Base, with an ultimate completion date of November 17, 2017.

Quick answers

Who was awarded contract W912QR15C0012?

W912QR15C0012 was awarded to Messer Construction Co by ENDIST Louisville (US Army Corps of Engineers) on June 23, 2015.

How much is contract W912QR15C0012 worth?

The government has obligated $27,230,403 on W912QR15C0012.

Was contract W912QR15C0012 competed?

The extent of competition for W912QR15C0012 was full and open competition. The government received 3 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award