Construction of an army reserve center at ST charles, MO

Ended Definitive Contract Awarded Last action

Contract number
W912QR12C0044
Awardee
Awarding agency
Obligated
$17,822,809

Award facts

Opportunity
Contract value 100% obligated
$17,822,809.19 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
236220 Commercial and Institutional Building Construction
PSC
Y1JZ Construction Of Miscellaneous Buildings
Set-aside
No set-aside
Competition
Full and Open Competition · 10 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
St Peters, MO 63304, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00032 · Case 112 recondition septic system, U.S. Army reserve center, ST. Charles, MO $12,316
Supplemental Agreement for work within scope A00031 · Case 111 raise depmeds drain inlet, U.S. Army reserve center, ST. Charles, MO $2,870
Change Order A00030 · Case 109 - parking lot stripping and case 110 stairwell window cavity ST charles, MO $2,685
Supplemental Agreement for work within scope A00029 · Case 107 provide drainage system at base of all trees, U.S. Army reserve center, ST. Charles, MO $2,400
Supplemental Agreement for work within scope A00028 · Case 094 add isolation valves in chilled water system; case 096 redesign septic system; case 100 add septic field gravel road; case 101 add retaining wall… $22,783
Supplemental Agreement for work within scope A00027 · Case 104 time extension due to weather delays, U.S. Army reserve center, ST. Charles, MO $0
Supplemental Agreement for work within scope A00026 · Case 065 equitable adjustment for costs associated with removal of soil, part 2 final, U.S. Army reserve center, ST. Charles, MO $23,082
Supplemental Agreement for work within scope A00025 · Case 093 exterior ladder security; case 095 change exterior entrance lights; case 098 add subbase to SE military equipment parking area; case 099 add ceramic… $7,130
Supplemental Agreement for work within scope A00024 · Case 087 power for chiller freezer protection; case 088 relocate light switch, t-stat and data line; case 090 provide BCS computer; case 091 install carpet in… $11,900
Supplemental Agreement for work within scope A00023 · Case 089 time extension due to weather delays, U.S. Army reserve center, ST. Charles, MO $0
Supplemental Agreement for work within scope A00022 · Case 081 delete omar kitchen equipment; case 084 install spandrel glass cover; case 085 provide vfds for hot water pumps; case 086 correct modification A00020… $586
Supplemental Agreement for work within scope A00021 · Case 070 remove and replace light pole; case 078 miscellaneous electrical changes; case 079 change signage; case 080 add IDS backbone; case 082 install… $25,903
Supplemental Agreement for work within scope A00020 · Case 068 change breakroom paint scheme; case 071 provide power to hot box; case 072 delete water TAP and water line; case 073 provide shaft liner drywall;… $6,835
Supplemental Agreement for work within scope A00019 · Case 061 realign sidewalk at heated storage building; case 063 change tepid water piping; case 064 additional drywall framing; case 067 IT changes; case 069… $31,007
Supplemental Agreement for work within scope A00017 · Case 054 change BIO-retention soil; case 059 add soil geotechnical services; case 060 add kitchen wall tile, U.S. Army reserve center, ST. Charles, MO -$1,997
Supplemental Agreement for work within scope A00018 · Case 066 time exension due to weather delay, U.S. Army reserve center, ST. Charles, MO $0
Supplemental Agreement for work within scope A00016 · Case 010 remove additional soil, part 1 notice to proceed, U.S. Army reserve center, ST. Charles, MO $353,207
Supplemental Agreement for work within scope A00015 · Case 043 change locker funding type; case 057 delete keyed locks from lockers, U.S. Army reserve center, ST. Charles, MO -$603
Supplemental Agreement for work within scope A00014 · Case 036 electrical changes; case 051 adjust grade at pad; case 052 return air plenum increase; case 053 drywall underside 2ND floor landing; case 055… $52,215
Change Order A00013 · Case 042 - rework s-28 soil ST charles, MO $85,685
Supplemental Agreement for work within scope A00012 · Case 041 connect downspouts and add underdrains; case 044 change beam connections; case 046 relocate telephone lines at soldiers drive; case 047 provide power… $62,774
Exercise an Option P00003 · ST charles, MO exercise option n unheated storage, option p kitchen addn, and option r heated storage. $139,000
Supplemental Agreement for work within scope A00011 · Case 028 delete 2 communication lines; case 034 redesign storm drain lines; case 038 provide steel lintels and plates; case 039 adjust locker widths; case 040… $9,323
Supplemental Agreement for work within scope A00010 · Case 029 install freestanding current transformer/potential transformer cabinets, U.S. Army reserve center, ST. Charles, MO $27,126
Supplemental Agreement for work within scope A00009 · Case 025 upgrade breaker; case 026 kitchen changes; case 030 mechanical system changes; case 032 change return air fan; case 033 install tapping sleeve for 3/4"… $11,741
Supplemental Agreement for work within scope A00008 · Case 022 change 5 water coolers to bottle-fill type; case 023 add 3 switches in cages; case 024 encase chiller lines; case 027 provide additional… $11,996
Supplemental Agreement for work within scope A00007 · Case 014 add rebar in footings and piers; case 015 change type of glass from vision to spandral; case 016 provide electrical panel in storage building; case 020… $16,993
Supplemental Agreement for work within scope A00006 · Case 018 remove soil at first placement of retaining wall and replace with screens; case 019 time extension due to additional time for settlement of native soil… $1,000
Exercise an Option P00002 · Exercise option b - omar bona fide need items in the amount of $67,000.00. $67,000
Supplemental Agreement for work within scope A00005 · Case 008 provide primary power to project site; case 017 time extension, U.S. Army reserve center, ST. Charles, MO $86,925
Supplemental Agreement for work within scope A00004 · Case 013 time extension due to weather delays, U.S. Army reserve center, ST. Charles, MO $0
Supplemental Agreement for work within scope A00003 · Case 011 remove 473 cubic yards of unsuitable soil and replace with structural fill outside and west of limits defined on contract drawing, U.S. Army reserve… $10,303
Supplemental Agreement for work within scope A00002 · Case 011 remove 440 CY of unsuitable soil and replace with structural fill, U.S. Army reserve center, ST. Charles, MO $9,369
Supplemental Agreement for work within scope A00001 · Case 006 remove 2 concrete-encased underground drain lines that LIE within 5' of unsuitable soil to be removed and plug exposed ends to prevent future drainage,… $73,255
Change Order P00001 · ST charles, MO - this action is to extend the option date. $0
Original award $16,658,000
Show all 36

Quick answers

Who was awarded contract W912QR12C0044?

W912QR12C0044 was awarded to K & S Associates, LLC by ENDIST Louisville (US Army Corps of Engineers) on July 13, 2012.

How much is contract W912QR12C0044 worth?

The government has obligated $17,822,809 on W912QR12C0044.

Was contract W912QR12C0044 competed?

The extent of competition for W912QR12C0044 was full and open competition. The government received 10 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award