Design/build roof and exterior repairs, ramey U.S. Army reserve center, aguadilla, PR

Ended Definitive Contract Awarded Last action

Contract number
W912QR10C0047
Awardee
Awarding agency
Obligated
$8,053,524

Award facts

Opportunity
Contract value 118% obligated
$6,798,529.54 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 5 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Aguadilla, 00603, Puerto Rico
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change Order A00016 · Arra::yes::arra case 021 global settlement agreement to resolve all outstanding disputes and issues (asbca 58635, 59048), U.S. Army reserve center, aguadilla,… $0
Change Order A00016 · Case 021 global settlement agreement to resolve all outstanding disputes and issues (asbca 58635, 59048), U.S. Army reserve center, aguadilla, PR $350,000
Supplemental Agreement for work within scope A00015 · Arra::yes::arra case 018 equitable adjustment for additional design services associated with notational furniture layouts, design/build roof and exterior… $0
Supplemental Agreement for work within scope A00015 · Case 018 equitable adjustment for additional design services associated with notational furniture layouts, design/build roof and exterior repairs, ramey U.S.… $21,534
Supplemental Agreement for work within scope A00014 · Arra::yes::arra case 020 removal of 2 15' asbestos contaminated pipes and 12' of rubber wall base at existing arms vault, design/build roof and exterior… $0
Supplemental Agreement for work within scope A00014 · Case 020 removal of 2 15' asbestos contaminated pipes and 12' of rubber wall base at existing arms vault, design/build roof and exterior repairs, ramey U.S.… $11,560
Supplemental Agreement for work within scope A00013 · Arra::yes::arra case 019 provide new bathroom partitions and accessories for 1ST, 2ND and 3RD floor bathrooms in buildings 807 & 808 and dispose of existing… $0
Supplemental Agreement for work within scope A00013 · Case 019 provide new bathroom partitions and accessories for 1ST, 2ND and 3RD floor bathrooms in buildings 807 & 808 and dispose of existing partitions,… $65,978
Supplemental Agreement for work within scope A00012 · Case 014 IT changes to buildings 807 and 808 to implement new telecom infrastructure, design/build roof and exterior repairs, ramey U.S. Army reserve center,… $0
Supplemental Agreement for work within scope A00012 · Arra::yes::arra case 014 IT changes to buildings 807 and 808 to implement new telecom infrastructure, design/build roof and exterior repairs, ramey U.S. Army… $353,114
Supplemental Agreement for work within scope A00011 · Case 016 replace sanitary sewer system for buildings 807 and 808 by replacing main line from 1ST floor of buildings and pipes located in bathrooms on 2ND and… $23,981
Supplemental Agreement for work within scope A00011 · Arra::yes::arra case 016 replace sanitary sewer system for buildings 807 and 808 by replacing main line from 1ST floor of buildings and pipes located in… $6,493
Supplemental Agreement for work within scope A00010 · Arra::yes::arra case 007 construct new armor vault located in east side of 1ST floor of building 808 and demolish existing armor vault, design/build roof and… $0
Supplemental Agreement for work within scope A00010 · Case 007 construct new armor vault located in east side of 1ST floor of building 808 and demolish existing armor vault, design/build roof and exterior… $115,354
Supplemental Agreement for work within scope A00009 · Arra::yes::arra case 012 compensation for additional time and expense incurred during furniture delivery and installation, design/build roof and exterior… $0
Supplemental Agreement for work within scope A00009 · Case 012 compensation for additional time and expense incurred during furniture delivery and installation, design/build roof and exterior repairs, ramey U.S.… $6,493
Other Administrative Action A00008 · Arra::yes::arra case 013 administrative change to correct line item amounts to reflect credit for deleting blast mitigation windows (delete line item 0017 and… $0
Other Administrative Action A00008 · Case 013 administrative change to correct line item amounts to reflect credit for deleting blast mitigation windows (delete line item 0017 and take credit… $0
Change Order P00002 · Arra::yes::arra case 008 delete requirement for blast mitigation windows and design and install glass blocks to fill all window openings, design/build roof… -$74,308
Change Order P00002 · Case 008 delete requirement for blast mitigation windows and design and install glass blocks to fill all window openings, design/build roof and exterior… $0
Supplemental Agreement for work within scope A00006 · Arra::yes::arra case 009 remaining asbestos abatement including removal and disposal of 2520 SF of vinal composite tile and mastic at 2ND floor building 808,… $0
Supplemental Agreement for work within scope A00006 · Case 009 remaining asbestos abatement including removal and disposal of 2520 SF of vinal composite tile and mastic at 2ND floor building 808, asbestos inside… $124,321
Supplemental Agreement for work within scope A00005 · Case 0011 time extension and associated costs with delay in government turnover of building to contractor for commencement of work, design/build roof and… $36,052
Supplemental Agreement for work within scope A00005 · Arra::yes::arra case 0011 time extension and associated costs with delay in government turnover of building to contractor for commencement of work, design/build… $0
Supplemental Agreement for work within scope A00007 · Arra::yes::arra case 010 install day gate to specified rooms, design/build roof and exterior repairs, ramey U.S. Army reserve center, aguadilla, PR (no arra… $0
Supplemental Agreement for work within scope A00007 · Case 010 install day gate to specified rooms, design/build roof and exterior repairs, ramey U.S. Army reserve center, aguadilla, PR $9,687
Supplemental Agreement for work within scope A00004 · Case 5-3 construct transclosure type pad mounted 1000 KVA substation (lead material requirement established by modification A00002), design/build roof and… $296,410
Supplemental Agreement for work within scope A00004 · Arra::yes::arra case 5-3 construct transclosure type pad mounted 1000 KVA substation (lead material requirement established by modification A00002),… $0
Supplemental Agreement for work within scope A00003 · Case 6 asbestos and lead abatement, design/build roof and exterior repairs, ramey U.S. Army reserve center, aguadilla, PR $193,625
Supplemental Agreement for work within scope A00003 · Arra::yes::arra case 6 asbestos and lead abatement, design/build roof and exterior repairs, ramey U.S. Army reserve center, aguadilla, PR $0
Supplemental Agreement for work within scope A00001 · Arra::yes::arra case 5-2 provide new electrical substation design and long lead material for construction of transclosure type pad mounted 1000KVA substation… $32,085
Supplemental Agreement for work within scope A00002 · Case 5-2 provide long lead material for construction of transclosure type pad mounted 1000 KVA substation connected to existing underground system lines (work… $0
Supplemental Agreement for work within scope A00001 · Case 5-2 provide new electrical substation design and long lead material for construction of transclosure type pad mounted 1000KVA substation connected to… $0
Supplemental Agreement for work within scope A00002 · Arra::yes::arra case 5-2 provide long lead material for construction of transclosure type pad mounted 1000 KVA substation connected to existing underground… $106,145
Exercise an Option P00001 · Arra::yes::arra exercise bid option d for new oil interceptor and option e for fire suppression system requirements due to failure flow test, design/build… $385,000
Exercise an Option P00001 · Exercise bid option d for new oil interceptor and option e for fire suppression system requirements due to failure flow test, design/build roof and exterior… $0
Modification Arra::yes::arra design/build roof and exterior repairs, ramey U.S. Army reserve center, aguadilla, PR $5,990,000
Original award $0
Show all 38

About this award

This is a firm fixed price definitive contract awarded by the U.S. Army Corps of Engineers (USACE) to Design Build, LLC, a small disadvantaged business located in Puerto Rico. The $6,798,529.54 contract is for the design and construction of roof and exterior repairs at the Ramey U.S. Army Reserve Center in Aguadilla, Puerto Rico. The contract has a total small business set-aside designation. Design Build, LLC has previously received multiple prime contracts from the Department of Veterans Affairs and Veterans Health Administration for cleaning and maintenance services to support COVID-19 response efforts at VA healthcare facilities in Puerto Rico, demonstrating their capabilities in facility maintenance and pandemic response support services for federal agencies.

Quick answers

Who was awarded contract W912QR10C0047?

W912QR10C0047 was awarded to Design Build, Llc. by ENDIST Louisville (US Army Corps of Engineers) on April 8, 2010.

How much is contract W912QR10C0047 worth?

The government has obligated $8,053,524 on W912QR10C0047. Its current value, with exercised options, is $6,798,530.

Was contract W912QR10C0047 competed?

The extent of competition for W912QR10C0047 was full and open competition after exclusion of sources. The government received 5 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award