Giww, gulf intracoastal waterway, calcasieu lock 2017, south chamber guidewall replacement, calcasieu parish, louisiana ED 17-010
Ended Definitive Contract Awarded Last action
- Contract number
- W912P818C0007
- Awardee
-
Phylway Construction, L.l.c UEI E2QBXKSNRWB3
- Awarding agency
-
ENDIST New Orleans
US Army Corps of Engineers, Department of Defense
- Obligated
- $15,309,681
Award facts
- Opportunity
-
- W912P818B0001 Solicitation number
- GIWW, Calcasieu Lock 2017 South Chamber Guidewall Replacement, Calcasieu Parish, LA Award Notice · Posted Nov 2, 2017
- Contract value 100% obligated
- $15,309,681.19 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- Contracting staff
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- Set-aside
- No set-aside
- Competition
- Not Competed under SAP · 1 offer Simplified Acquisition
- Pricing
- Firm Fixed Price
- Place of performance
- New Orleans, LA 70118, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Other Administrative Action | -$800,000 | |
| Supplemental Agreement for work within scope | $118,000 | |
| Supplemental Agreement for work within scope | $252,354 | |
| Funding Only Action | $630,215 | |
| Supplemental Agreement for work within scope | $278,105 | |
| Supplemental Agreement for work within scope | $225,197 | |
| Supplemental Agreement for work within scope | $68,656 | |
| Supplemental Agreement for work within scope | $38,095 | |
| Definitize Change Order | $30,000 | |
| Change Order | $0 | |
| Change Order | $1,080,869 | |
| Supplemental Agreement for work within scope | -$8,125 | |
| Change Order | $0 | |
| Definitize Change Order | $179,383 | |
| Supplemental Agreement for work within scope | $368,000 | |
| Change Order | $800,000 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Supplemental Agreement for work within scope | $3,183 | |
| Supplemental Agreement for work within scope | $201,000 | |
| Supplemental Agreement for work within scope | $0 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Original award | $11,844,750 |
Show all 30
About this award
The U.S. Army Corps of Engineers, New Orleans District awarded a $15,309,681.19 firm fixed-price definitive contract to Phylway Construction, L.L.C., a woman-owned small business, for the Gulf Intracoastal Waterway (GIWW) Calcasieu Lock South Chamber Guidewall Replacement project in Calcasieu Parish, Louisiana. The contract, which does not have a set-aside designation, was awarded on February 22, 2018 with a completion date of June 25, 2021. Phylway Construction is an experienced federal contractor, having received previous awards from the Corps of Engineers for levee enlargement, seepage remediation, and other civil works infrastructure projects in the region. This contract supports the Corps' flood control and hurricane protection efforts along the Mississippi River and Gulf Coast.
Quick answers
Who was awarded contract W912P818C0007?
W912P818C0007 was awarded to Phylway Construction, L.l.c by ENDIST New Orleans (US Army Corps of Engineers) on February 22, 2018.
How much is contract W912P818C0007 worth?
The government has obligated $15,309,681 on W912P818C0007.
Was contract W912P818C0007 competed?
The extent of competition for W912P818C0007 was not competed under sap. The government received 1 offer.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award