Arcyber HQ, fort gordon, GA (PN 85811 and 85818)

Ended Definitive Contract Awarded Last action

Contract number
W912HN16C0014
Awardee
Awarding agency
Obligated
$175,851,815

Award facts

Contract value 100% obligated
$175,851,815.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 10 offers Two Step
Pricing
Firm Fixed Price
Place of performance
Fort Gordon, GA 30905, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00110 · Modification for GC154 additional cost for as-builts $8,028.00 PN85811 (construction) $8,027.00 PN85818 $16,055
Supplemental Agreement for work within scope A00109 · Modification for REA elevator repair added cost FY16 PN85811 $3,100.45, FY13 PN85811 $9,283.55 no time. $12,384
Supplemental Agreement for work within scope A00108 · FY16 PN85811 (construction) - modification for GC147 REA modify sidewalk at whitelaw added cost $49,648.00 no time $49,648
Supplemental Agreement for work within scope A00107 · PN85811 GC144 REA misc. Drywall added cost, no time, $24,500.00. $24,500
Supplemental Agreement for work within scope A00106 · PN85811 (construction) GC145 REA for temp power added cost no time, $43,540.00. $43,540
Supplemental Agreement for work within scope A00105 · FY16 PN85811 (construction) - GC143 REA for site utility locate fees, added cost no time. $34,707
Supplemental Agreement for work within scope A00104 · FY16 PN85811 (construction) - GC153 REA steel modifications added cost no time. $62,155
Supplemental Agreement for work within scope A00103 · Modification for GC066 cummins PLC interface mvsg added cost no time PN85818: clin 11 $60,926.74, clin 25 $9,970.26, PN85811: clin 27 $70,896.00. $141,793
Supplemental Agreement for work within scope A00102 · Modification for GC148 misc. Site improvements added cost no time. PN85811 added $46,021.00. PN85818 added $198,695.00. $198,695
Supplemental Agreement for work within scope A00101 · Modification for GC095 add scif accreditation requirements, added cost $73,535.00 on PN85811 $73,535
Supplemental Agreement for work within scope A00100 · Modification for GC149 AHU economizer control sequence change. Change in cost no time. $15,488.50 on PN85811 and $15,488.50 on PN85818. $30,977
Supplemental Agreement for work within scope A00099 · Modification for GC141 dining air handler unit controls. Added cost no time. $41,045
Supplemental Agreement for work within scope A00098 · Modification for GC140 miscellaneous changes added cost no time, and GC146 REA - chiller chemicals, added cost no time. PN85811/PN85818. $27,323
Supplemental Agreement for work within scope A00097 · FY16 PN85811 (construction) - $27,865
Supplemental Agreement for work within scope A00096 · Modification for GC135 add misc. Wall changes added cost on PN85811 of $19,866.00 and on PN85818 $3,213.00, and add time on PN85818 of 26 days changing the… $23,079
Supplemental Agreement for work within scope A00095 · Modification GC134 add misc. Electrical items #2. Added cost $34,645.00 on PN85811 and $12,814.00 on PN85818. Added time 5DAYS on PN85818. $47,459
Supplemental Agreement for work within scope A00094 · Modification for GC123 replace refrigerator in 2C109. Added cost not time. $2,991
Supplemental Agreement for work within scope A00093 · Modification for GC136 add exhaust duct to women's shower and GC138 final paint LE9 walls without graphics, added cost no time. $39,252
Supplemental Agreement for work within scope A00092 · Modification for GC137 fuel oil piping system and GC139 labor for architectural hardware install, credit and added cost, added time, CCD on 10 JAN 2020. $18,529
Supplemental Agreement for work within scope A00091 · FY16 PN85811 (construction) - $0
Supplemental Agreement for work within scope A00090 · FY16 PN85811 (construction) - FY17 PN85818 increased cost modification for GC119 revised column fireproofing - AV closets, GC124 provide beverage counter, GC125… $148,994
Supplemental Agreement for work within scope A00089 · FY17 PN85818 cost and time increase FY16 PN85811 cost increase $75,653
Supplemental Agreement for work within scope A00088 · Modification to GC127 provide dishwasher/ICE maker power in PN85811. Add cost no time. $8,971
Supplemental Agreement for work within scope A00087 · MOD for added cost and no time $146,835.00. GC103 reconciliatory MOD for GC073. $146,835
Supplemental Agreement for work within scope A00086 · Added cost MOD of $8,170.00, on PN85811 to add leak detection & control valves $8,170
Supplemental Agreement for work within scope A00084 · This MOD is for the relocation of the FCU from the elec. RM. In LL PN85818, LC7.LC120 to LC7.LC119, add supply and return ducts the result is a change in cost… $12,900
Supplemental Agreement for work within scope A00085 · MOD for GC109 ductsmokes FCU firealarm & detectors and GC114 LC7.LC8 quarry tile added cost and time and captures the 68 days from GC121 A00084 and 10DAYS… $61,680
Supplemental Agreement for work within scope A00083 · This is an added cost and no time modification for GC083 return grilles for corridors split between PN85811 and PN85818. Total cost of $50,291.00. $50,291
Supplemental Agreement for work within scope A00082 · Credit modification for deleted filter fabric/asphalt pavement in the PN85818 footprint. Amnt of credit -$76,946.00 -$76,946
Supplemental Agreement for work within scope A00081 · Modification for added cost and no time for added SCADA camera & data revisions and for added fitness fan, coiling door, door holder $21,170
Supplemental Agreement for work within scope A00080 · This is a change in cost modification to add an elevator inspector. $12,528
Supplemental Agreement for work within scope A00079 · GC117 revise pavement at duct banks added cost and time 24 calendar days & GC104 revise miscellaneous electrical items added cost & GC099 construct walls in… $191,172
Supplemental Agreement for work within scope A00078 · The combined modifications are for pedestrian gates w/crash bars credit/ added cost for building 11 wall graphics/and the added cost to raise the security fence… $61,666
Supplemental Agreement for work within scope A00077 · Modification for GC097 plenum wrap in PN85818, increase in funds not time. $14,821
Supplemental Agreement for work within scope A00076 · Modification to PN85811 and PN85818, added cost for the addition of smoke detectors at fireproof steel locations. Necessary to meet life safety code. $32,793
Supplemental Agreement for work within scope A00075 · Modification for add lights & revise ceiling on PN85811 and PN85818 $52,589
Supplemental Agreement for work within scope A00074 · Modification for a/v credenzas $33,141
Supplemental Agreement for work within scope A00073 · Modification for chilled water flushing, and to change the performance end date, and to add funding information $149,612
Supplemental Agreement for work within scope A00072 · IGE::e:: FY16 PN85811 (construction) - FY17 PN85818 (construction) -$2,903
Supplemental Agreement for work within scope A00071 $19,079
Supplemental Agreement for work within scope A00070 $1,406
Supplemental Agreement for work within scope A00069 $3,165
Supplemental Agreement for work within scope A00068 $15,577
Supplemental Agreement for work within scope A00067 $54,462
Supplemental Agreement for work within scope A00066 $13,258
Supplemental Agreement for work within scope A00065 $21,846
Supplemental Agreement for work within scope A00064 $46,966
Supplemental Agreement for work within scope A00060 $18,358
Supplemental Agreement for work within scope A00059 $10,933
Supplemental Agreement for work within scope A00063 · IGE:::: FY16 PN85811 (construction) - FY17 PN85818 (construction) $197,656
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

This is a $175,851,815.00 firm fixed price contract awarded by the U.S. Army Corps of Engineers Savannah District to the prime contractor BL Harbert International LLC for the construction of the U.S. Army Cyber Command (ARCYBER) headquarters at Fort Gordon, Georgia. The project includes the construction of new facilities and renovations at multiple buildings on the installation. No set-aside designation was used for this award. BL Harbert International LLC has subcontracted portions of the work to various small businesses and specialized firms, including Aluma Designs LLC for signage, Astic Signals Defenses L.L.C. for radio frequency mitigation, and Carpet Decorators Inc. for flooring installation. The contract has an ultimate completion date of February 10, 2020.

Quick answers

Who was awarded contract W912HN16C0014?

W912HN16C0014 was awarded to BL Harbert International LLC by ENDIST Savannah (US Army Corps of Engineers) on August 29, 2016.

How much is contract W912HN16C0014 worth?

The government has obligated $175,851,815 on W912HN16C0014.

Was contract W912HN16C0014 competed?

The extent of competition for W912HN16C0014 was full and open competition. The government received 10 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities