Replace hydrant hydrant fuel system at robins AFB, GA

Ended Definitive Contract Awarded Last action

Contract number
W912HN15C0016
Awardee
Awarding agency
Obligated
$16,567,793

Award facts

Contract value 98% obligated
  • $16,567,793.00 Current, with exercised options
  • $16,854,493.00 Potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 3 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Warner Robins, GA 31098, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action A00020 · Correct period of performance on MOD A00019 in PD2 $0
Supplemental Agreement for work within scope A00019 · Install permanent PIG launcher system $222,489
Supplemental Agreement for work within scope A00018 · Tank outlet switches and fuel test port $33,401
Supplemental Agreement for work within scope A00017 · Truckfill stand TRV relief piping and crack repair at hydrant pits $30,076
Supplemental Agreement for work within scope A00016 · Clin 0005 funding removal -$91,100
Supplemental Agreement for work within scope A00014 · Media converters for e-stop at bldg 194 $1,999
Supplemental Agreement for work within scope A00013 · Misc user requested changes $8,533
Supplemental Agreement for work within scope A00012 · Sawcut control joints at hydrant pits; RFI-0001 design changes, product recovery tank access road $33,651
Supplemental Agreement for work within scope A00011 · Condition pump house control room $13,559
Supplemental Agreement for work within scope A00009 · Temporary pipe support $19,904
Supplemental Agreement for work within scope A00008 · Drainage layer replacement $71,817
Supplemental Agreement for work within scope A00007 · Phase 3 electrical structure removal $73,252
Supplemental Agreement for work within scope A00006 · Additional saw cutting $28,922
Supplemental Agreement for work within scope A00005 · Phase 2 single slab removal $22,911
Supplemental Agreement for work within scope A00004 · Phase 2 electrical demo $317,226
Supplemental Agreement for work within scope A00003 · Phase 2 concrete pavement demo $73,632
Supplemental Agreement for work within scope A00002 · FP7 & FP8 controls intergration into PCP $22,421
Supplemental Agreement for work within scope A00001 · Time extension - government delays $0
Original award $15,685,100
Show all 19

About this award

This is a $16,854,493.00 firm fixed price definitive contract awarded by the U.S. Army Corps of Engineers to MEB General Contractors Inc. to replace a hydrant fuel system at Robins Air Force Base in Georgia. The contract has no set-aside designation and the work is scheduled for completion by April 26, 2019. MEB General Contractors is a for-profit construction company based in Chesapeake, Virginia that has been awarded over $352 million in prime federal contracts since 2019, primarily for Department of Defense infrastructure projects. No major subcontractors are listed for this specific award.

Quick answers

Who was awarded contract W912HN15C0016?

W912HN15C0016 was awarded to MEB General Contractors Inc. by ENDIST Savannah (US Army Corps of Engineers) on August 19, 2015.

How much is contract W912HN15C0016 worth?

The government has obligated $16,567,793 on W912HN15C0016. Its potential value, with all options, is $16,854,493.

Was contract W912HN15C0016 competed?

The extent of competition for W912HN15C0016 was full and open competition. The government received 3 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award