Armourdale shawnee avenue pump station

Ended Definitive Contract Awarded Last action

Contract number
W912DQ20C1117
Awardee
Awarding agency
Obligated
$15,294,805

Award facts

Contract value 100% obligated
  • $15,294,805.00 Current, with exercised options
  • $15,346,805.00 Potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Funding agency
US Army Corps of Engineers Department of the Army, Department of Defense
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 3 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Kansas City, KS 66101, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00014 · Modification for 12TH street PS security to contract for KCL arm PS repair at kansas city, kansas $53,737
Supplemental Agreement for work within scope A00013 · Modification for mill BPU upgrade fees to contract for KCL arm PS repair at kansas city, kansas $24,952
Supplemental Agreement for work within scope A00012 · Modification for 12TH ST PS motors part 2 to contract for KCL arm PS repair at kansas city, kansas. $142,673
Supplemental Agreement for work within scope A00011 · Modification for 12TH ST PS motors to contract for KCL arm PS repair at kansas city, kansas. $50,000
Supplemental Agreement for work within scope A00010 · Modification for 12TH street PS electrical to contract for KCL arm PS repair at kansas city, kansas $265,307
Change Order A00009 · Modification for 12TH street PS long lead time switchgear to contract for KCL arm PS repair at kansas city, kansas. $166,535
Change Order A00008 · Modification for increased security measures and testing to contract for kansas city levees - armourdale unit pump station modifications at kansas city, kansas. $75,000
Supplemental Agreement for work within scope A00007 · Modification for gate actuators to contract for kansas city levees - armourdale unit pump station modifications at kansas city, kansas. $102,277
Supplemental Agreement for work within scope A00006 · Modification for generator disconnect security cages for contract for kansas city levees - armourdale unit pump station modifications at kansas city, kansas. $12,557
Supplemental Agreement for work within scope A00005 · Modification for 5TH & 12TH street PS reas to contract for kansas city levees - armourdale unit pump station modifications at kansas city, kansas. $10,357
Supplemental Agreement for work within scope A00004 · Modification for shawnee PS BPU upgrade fees to contract for kansas city levees - armourdale unit pump station modifications at kansas city, kansas. $11,214
Supplemental Agreement for work within scope A00003 · Modification for osage PS gatewell changes to contract for kansas city levees - armourdale unit pump station modifications at kansas city, kansas. $17,968
Supplemental Agreement for work within scope A00002 · Modification for osage, 12TH ST, 5TH ST changes to contract for kansas city levees - armourdale unit pump station modifications at kansas city, kansas. $69,164
Supplemental Agreement for work within scope A00001 · Modification for WK restr's, WIT testing & bypass cap to contract for kansas city levees - armourdale unit pump station modifications at kansas city, kansas. $0
Original award $14,293,064
Show all 15

About this award

The U.S. Army Corps of Engineers awarded a $15.3 million firm fixed-price definitive contract to Supplied Industrial Solutions, Inc., a veteran-owned and minority-owned small business, for modifications to pump stations associated with the Kansas City levee program in Kansas City, Kansas. This total small business set-aside contract encompasses structural, mechanical, and electrical upgrades to seven existing pump stations along the Armourdale Levee Unit, with an ultimate completion date of March 1, 2025. Supplied Industrial Solutions, Inc. is an SBA Certified 8(a) Program Participant headquartered in Granite City, Illinois, and brings extensive experience in federal infrastructure projects through prior awards from the Army Corps of Engineers and other federal agencies.

The contract represents part of a larger procurement strategy by the Army Corps of Engineers Kansas City District to upgrade multiple pump stations across levee units in the Kansas City area. This award leverages the contractor's established capabilities in infrastructure repairs, equipment procurement, and construction services, as well as its existing blanket purchase agreements with the Army Corps of Engineers for flood abatement equipment and materials. The selection of Supplied Industrial Solutions, Inc. through this small business set-aside designation supports federal objectives to provide contracting opportunities for small, disadvantaged, and veteran-owned businesses while advancing critical flood control infrastructure improvements in the Kansas City region.

Quick answers

Who was awarded contract W912DQ20C1117?

W912DQ20C1117 was awarded to Supplied Industrial Solutions, Inc. by ENDIST Kansas City (US Army Corps of Engineers) on October 14, 2020.

How much is contract W912DQ20C1117 worth?

The government has obligated $15,294,805 on W912DQ20C1117. Its potential value, with all options, is $15,346,805.

Which agency awarded contract W912DQ20C1117?

ENDIST Kansas City (US Army Corps of Engineers) awarded W912DQ20C1117, with funding from US Army Corps of Engineers (Department of the Army).

Was contract W912DQ20C1117 competed?

The extent of competition for W912DQ20C1117 was full and open competition after exclusion of sources. The government received 3 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities