Install and procure generator set ecrip at FT. Leonard wood, MO
Ended Definitive Contract Awarded Last action
- Contract number
- W912DQ19C4014
- Awardee
-
Ameresco Inc. UEI DKL8RJPGE4R3
- Awarding agency
-
ENDIST Kansas City
US Army Corps of Engineers, Department of Defense
- Obligated
- $7,388,627
Award facts
- Opportunity
-
- ERCIP Install Combined Heat and Power System Solicitation · W912DQ19R4004 · Posted Nov 2, 2018
- ERCIP Install Combined Heat and Power System Award Notice · Posted Aug 21, 2019
- Contract value 100% obligated
- $7,388,627.00 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- Contracting staff
- NAICS code
- 236220 Commercial and Institutional Building Construction
- Set-aside
- No set-aside
- Competition
- Full and Open Competition · 3 offers Negotiated Proposal / Quote
- Pricing
- Firm Fixed Price
- Place of performance
- FT LEONARD WD, MO 65473, USA
- Legislative mandates
-
- Walsh-Healey Public Contracts Act FAR subpart 22.6
- Davis-Bacon Act FAR subpart 22.4
- Employment Eligibility Verification (E-Verify) FAR subpart 22.18
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Change Order | $0 | |
| Change Order | $18,059 | |
| Change Order | $117,981 | |
| Change Order | $0 | |
| Change Order | $12,662 | |
| Change Order | $6,134 | |
| Change Order | $0 | |
| Other Administrative Action | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $19,854 | |
| Other Administrative Action | -$7,701 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $81,348 | |
| Other Administrative Action | $0 | |
| Other Administrative Action | $0 | |
| Original award | $7,140,290 |
Show all 16
About this award
The U.S. Army Corps of Engineers, Kansas City District awarded a $7,388,627 firm-fixed-price contract to Ameresco Inc., a renewable energy and energy efficiency company, to install a 2.5 MW natural gas-powered combined heat and power (CHP) system and associated infrastructure upgrades at Fort Leonard Wood in Missouri. The contract, which was awarded on August 13, 2019, does not have a set-aside designation. The CHP system will provide electricity to the fort's local grid and waste heat to the high-temperature hot water distribution network serving approximately 45 buildings. Ameresco has experience as a prime contractor on other federal energy efficiency, renewable energy, and infrastructure projects for agencies such as the Department of Energy, Department of Defense, and General Services Administration.
Quick answers
Who was awarded contract W912DQ19C4014?
W912DQ19C4014 was awarded to Ameresco Inc. by ENDIST Kansas City (US Army Corps of Engineers) on August 13, 2019.
How much is contract W912DQ19C4014 worth?
The government has obligated $7,388,627 on W912DQ19C4014.
Was contract W912DQ19C4014 competed?
The extent of competition for W912DQ19C4014 was full and open competition. The government received 3 offers.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award