Install and procure generator set ecrip at FT. Leonard wood, MO

Ended Definitive Contract Awarded Last action

Contract number
W912DQ19C4014
Awardee
Awarding agency
Obligated
$7,388,627

Award facts

Opportunity
Contract value 100% obligated
$7,388,627.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 3 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
FT LEONARD WD, MO 65473, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change Order A00013 $0
Change Order A00012 $18,059
Change Order A00011 $117,981
Change Order A00010 $0
Change Order A00009 · Install generator set $12,662
Change Order A00007 · Contractor to replace the spliced low voltage cabling running from the MCC4 series circuit breaker in the MDP to PNL-p with new spice free cabling. Replace by… $6,134
Change Order A00008 · Install generator set $0
Other Administrative Action A00006 · The purpose of this modification is to execute a zero dollar admin MOD to change the clin location (clin 0001: -$19,854 and clin 0002: +$19,854). $0
Supplemental Agreement for work within scope A00005 · Modification for covid-19 time extension to contract for install combined heat and power system (specker plant), bldg 2369 at FT. Leonard wood, missouri. $0
Supplemental Agreement for work within scope A00004 · Modification to plumb condensate drains to contract for install combined heat and power system (specker plant), bldg 2369 at FT. Leonard wood, missouri. $19,854
Other Administrative Action A00003 · Modification to delete manpower reporting requirement to contract for install combined heat and power system (specker plant), bldg 2369 at FT. Leonard wood,… -$7,701
Supplemental Agreement for work within scope A00002 · Modification for covid-19 time extension to contract for install combined heat and power system (specker plant), bldg 2369 at FT. Leonard wood, missouri. $0
Supplemental Agreement for work within scope A00001 · Modification for additional generator crane lift to contract for install combined heat and power system (specker plant), bldg 2369 at FT. Leonard wood,… $81,348
Other Administrative Action P00002 · Administrative modification to delete clauses 52.225-9 and 52.225-10 and add clauses 52.225-11 and 52.225-12. Install generator set $0
Other Administrative Action P00001 · Modification to update clause 52.211-10. $0
Original award $7,140,290
Show all 16

About this award

The U.S. Army Corps of Engineers, Kansas City District awarded a $7,388,627 firm-fixed-price contract to Ameresco Inc., a renewable energy and energy efficiency company, to install a 2.5 MW natural gas-powered combined heat and power (CHP) system and associated infrastructure upgrades at Fort Leonard Wood in Missouri. The contract, which was awarded on August 13, 2019, does not have a set-aside designation. The CHP system will provide electricity to the fort's local grid and waste heat to the high-temperature hot water distribution network serving approximately 45 buildings. Ameresco has experience as a prime contractor on other federal energy efficiency, renewable energy, and infrastructure projects for agencies such as the Department of Energy, Department of Defense, and General Services Administration.

Quick answers

Who was awarded contract W912DQ19C4014?

W912DQ19C4014 was awarded to Ameresco Inc. by ENDIST Kansas City (US Army Corps of Engineers) on August 13, 2019.

How much is contract W912DQ19C4014 worth?

The government has obligated $7,388,627 on W912DQ19C4014.

Was contract W912DQ19C4014 competed?

The extent of competition for W912DQ19C4014 was full and open competition. The government received 3 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award