Swope park bank stabilization

Ended Definitive Contract Awarded Last action

Contract number
W912DQ16C1097
Awardee
Awarding agency
Obligated
$4,371,176

Award facts

Opportunity
Contract value 92% obligated
  • $4,371,175.79 Current, with exercised options
  • $4,754,981.69 Potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 2 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Kansas City, MO 64106, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00003 · Modification for time extension due to unusually severe weather to contract for swope park industrial district - PH II at kansas city, missouri. $0
Supplemental Agreement for work within scope A00002 · Modification for bolt-on 24 inch flapgate to contract for swope park industrial district - PH II at kansas city, missouri. $7,250
Supplemental Agreement for work within scope A00001 · Modification for time extension due to unusually severe weather to contract for swope park industrial district - PH II at kansas city, missouri. $0
Supplemental Agreement for work within scope P00005 · Modification for stormwater improvements to contract for swope park industrial district - PH II at kansas city, missouri. $79,844
Change Order P00004 · Modification for shot rock key to contract for swope park industrial district - PH II at kansas city, missouri. $331,108
Supplemental Agreement for work within scope P00003 · Modification for weather time extension due to unusually severe weather to contract for swope park industrial district - PH II at kansas city, missouri. $0
Supplemental Agreement for work within scope P00002 · Modification for vecp - replace ACB with riprap to contract for swope park industrial district - PH II at kansas city, missouri. -$547,714
Exercise an Option P00001 · Exercise of option $827,855
Original award $3,672,833

About this award

The U.S. Army Corps of Engineers awarded a $4,754,981.69 firm-fixed-price contract to ESI Contracting, Corp., a small business subchapter S corporation, for the Swope Park Bank Stabilization project in Kansas City, Missouri. The contract was set aside for small businesses and has an ultimate completion date of September 30, 2018. ESI Contracting, a construction and infrastructure development company, has previously performed levee rehabilitation, bank stabilization, and other heavy construction projects for the Army Corps of Engineers and the Department of Defense. The contract was awarded on September 20, 2016 and is part of the agency's efforts to maintain and repair critical infrastructure along the Missouri River.

Quick answers

Who was awarded contract W912DQ16C1097?

W912DQ16C1097 was awarded to ESI Contracting, Corp. by ENDIST Kansas City (US Army Corps of Engineers) on September 20, 2016.

How much is contract W912DQ16C1097 worth?

The government has obligated $4,371,176 on W912DQ16C1097. Its potential value, with all options, is $4,754,982.

Was contract W912DQ16C1097 competed?

The extent of competition for W912DQ16C1097 was full and open competition after exclusion of sources. The government received 2 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award