Expand strategic airlift ramp and construct new clear water rinse concrete pad for c-17 aircraft.

Ended Definitive Contract Awarded Last action

Contract number
W9128A07C0004
Awardee
Awarding agency
Obligated
$26,916,616

Award facts

Opportunity
  • W9128A06R0007 Solicitation number
Contract value 100% obligated
$26,916,616.38 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
237310 Highway, Street, and Bridge Construction
PSC
Not on record
Set-aside
No set-aside
Competition
Full and Open Competition · 4 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Hickam AFB, HI 96853, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change Order P00002 $40,017
Change Order P00003 $26,556
Change Order A00044 -$77,513
Supplemental Agreement for work within scope A00042 $16,200
Change Order A00043 -$100,000
Other Administrative Action A00041 $0
Supplemental Agreement for work within scope A00040 · FY06 funds clear water rinse facility $32,312
Supplemental Agreement for work within scope A00038 · Clear water rinse facility $5,123
Supplemental Agreement for work within scope A00039 · FY06 funds clear water rinse facility $35,696
Funding Only Action A00037 · Clear water rinse facility $1,619
Supplemental Agreement for work within scope A00032 $5,705
Supplemental Agreement for work within scope A00036 $9,500
Supplemental Agreement for work within scope A00034 $6,714
Supplemental Agreement for work within scope A00033 -$500
Supplemental Agreement for work within scope A00035 · FY06 funds clear water rinse facility $6,906
Supplemental Agreement for work within scope A00031 · Additional cathodic protection for clear water rinse facility $4,040
Supplemental Agreement for work within scope A00028 · Cost sharing for facilitation partnering clear water rinse facility $1,852
Supplemental Agreement for work within scope A00026 · NAVFAC requirements for clear water rinse facility $5,461
Supplemental Agreement for work within scope A00030 · Raise/patch valve boxes and core holes, clear water rinse facility $2,442
Supplemental Agreement for work within scope A00027 · Seeding and mulching requirements for clear water rinse facility $30,000
Supplemental Agreement for work within scope A00029 · Additional rung for pump house ladder clear water rinse facility $735
Definitize Change Order A00023 · Definitize MOD A00011 to clear water rinse facility $20,406
Change Order A00024 · Restrain clear water rinse facility trench grates $36,000
Definitize Change Order A00025 · Reroute force main $10,025
Definitize Change Order A00022 · FY06 funds clear water rinse facility $38,000
Supplemental Agreement for work within scope A00021 · Install 11,500 SF of biaxial bridging fabric for subgrade soil reinforcing at the taxiway a-2 tie-in $9,840
Supplemental Agreement for work within scope A00020 · Disposal of petroleum impacted soil $37,420
Supplemental Agreement for work within scope A00019 · Extend communication cable for remote panel $11,000
Definitize Change Order A00017 · Storm drain pipes, clear water rinse facility, hafb -$8,335
Definitize Change Order A00018 · Definitize A00014, clear water rinse facility -$3,844
Definitize Change Order A00016 · Definitize modification no. A00001 $375
Supplemental Agreement for work within scope A00015 · Clear water rinse facility $11,000
Change Order A00014 $35,000
Supplemental Agreement for work within scope A00013 · FY06 funds clear water rinse facility $2,500
Change Order A00010 · Revise rinsate water flow NTP, FY06 funds clear water rinse facility $40,000
Supplemental Agreement for work within scope A00012 · Perform national clearance background checks clear water rinse facility $2,863
Change Order A00011 · Remove asbestos containing underground electrical conduit, clear water rinse facility $30,000
Change Order A00008 · Install additional water tank, clear water rinse facility $180,000
Supplemental Agreement for work within scope A00009 · Delete additional water tank, clear water rinse facility -$180,000
Change Order A00007 · Removal of two storm drain pipes, clear water rinse facility $20,000
Supplemental Agreement for work within scope A00005 · CI005 for clear water rinse facility $32,000
Supplemental Agreement for work within scope A00006 · CI015 for clear water rinse facility $31,694
Supplemental Agreement for work within scope A00004 · Clear water rinse facility, CI003, 6, 8-14 and 17 $76,000
Change Order A00003 · Delete centerline lights for clear water rinse taxiway -$23,192
Change Order A00002 $12,000
Change Order A00001 · FY06 funds clear water rinse facility $3,000
Supplemental Agreement for work within scope P00001 · No cost change $0
Original award $26,440,000
Show all 48

Quick answers

Who was awarded contract W9128A07C0004?

W9128A07C0004 was awarded to Dick Corporation (9321) by ENDIST Honolulu (US Army Corps of Engineers) on February 21, 2007.

How much is contract W9128A07C0004 worth?

The government has obligated $26,916,616 on W9128A07C0004.

Was contract W9128A07C0004 competed?

The extent of competition for W9128A07C0004 was full and open competition. The government received 4 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award