Fall creek fish facility

Ended Definitive Contract Awarded Last action

Contract number
W9127N16C0034
Awardee
Awarding agency
Obligated
$14,336,488

Award facts

Opportunity
Contract value 100% obligated
  • $14,336,488.00 Current, with exercised options
  • $14,340,988.00 Potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 7 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Lowell, OR 97452, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Additional Work (new agreement, FAR part 6 applies) A00009 · Fall creek DAM and reservoir adult fish facility, lane county, oregon - final quantity adjustments to clin's 0004AA & 0005AA. -$7,342
Supplemental Agreement for work within scope A00008 · Fall creek DAM and reservoir adult fish facility, lane county, oregon - dewatering flume and brail modifications $323,800
Supplemental Agreement for work within scope A00007 · Fall creek DAM and reservoir adult fish facility, lane county, oregon; miscellaneous follow on work $52,500
Change Order A00006 · Fall creek DAM and reservoir adult fish facility, lane county, oregon; entrance gate e-4 maintenance platform $54,450
Change Order A00005 · Fall creek DAM and reservoir adult fish facility, lane county, oregon - dewatering structure modification $14,100
Change Order A00004 · Fall creek DAM and reservoir adult fish facility, lane county, oregon - headbox waterstop installation $9,145
Change Order A00003 · Fall creek DAM and reservoir adult fish facility, lane county, oregon - addition of demolition at existing facility $19,525
Change Order A00002 · Fall creek DAM adult fish facility, lane county, oregon, procurement of new facility electrical $22,450
Change Order P00001 · Fall creek adult fish facility, lane county, oregon, dewatering screen modifications $3,500
Change Order A00001 · Fall creek DAM and reservoir adult fish facility, lane county, oregon - suspension of work and delayed NTP $0
Original award $13,844,360
Show all 11

About this award

This is a firm-fixed-price definitive contract awarded by the U.S. Army Corps of Engineers (USACE) to Record Steel and Construction, Inc. (dba RSCI), a for-profit self-certified HUBZone joint venture organization, for the Fall Creek Fish Facility project. The $14,340,988.00 contract has an ultimate completion date of March 15, 2020 and did not utilize any set-aside designations. RSCI is a construction firm with expertise in large-scale infrastructure projects for federal agencies, including water treatment plants, military facilities, and national park improvements. This contract supports the USACE's mission to provide engineering solutions for the nation's water resources, security, and sustainability.

Quick answers

Who was awarded contract W9127N16C0034?

W9127N16C0034 was awarded to Record Steel And Construction, Inc. by ENDIST Portland (US Army Corps of Engineers) on August 2, 2016.

How much is contract W9127N16C0034 worth?

The government has obligated $14,336,488 on W9127N16C0034. Its potential value, with all options, is $14,340,988.

Was contract W9127N16C0034 competed?

The extent of competition for W9127N16C0034 was full and open competition. The government received 7 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award