EL paso CPC processing building BPS construction; SOL W9126G19R0103

Ended Definitive Contract Awarded Last action

Contract number
W9126G19C0027
Awardee
Awarding agency
Obligated
$19,707,852

Award facts

Opportunity
  • W9126G19R0103 Solicitation number
Contract value 100% obligated
$19,707,852.45 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
8(a) Sole Source
Competition
Not Available for Competition · 1 offer Only One Source
Pricing
Firm Fixed Price
Place of performance
El Paso, TX 79924, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change Order P00011 · Install gutters and downspouts for sally port canopy and extend contract completion date by 7 calendar days. $4,162
Supplemental Agreement for work within scope P00010 · P00010 C00023 procure stools and relocate millwork $45,368
Definitize Change Order P00009 · CPC processing building: clin 0018 smoke control system UN-priced change order (UCO) is changed from UCO to definitized. $398,071
Supplemental Agreement for work within scope A00011 · A00011 C00017 additional site security lighting $383,309
Supplemental Agreement for work within scope A00010 · A00010 C00018 changes to LAN room $42,595
Change Order P00008 · Modification unpriced change order (UCO) with a total not-to-exceed (NTE) amount of $200,000.00 install smoke management system. $200,000
Other Administrative Action P00006 · Administrative change to add paragraphs b "change in contract drawings" c" change in contract specifications" and f "closing statement". $0
Other Administrative Action P00007 · Administrative change to correct language paragraph e of clin 0017. $0
Change Order P00004 · Add hardened walkways & drive pad $748,119
Change Order P00005 · Erosion control $1,567,094
Supplemental Agreement for work within scope A00009 · A00009 C00020 EXT. Conduit for CCTV by others $20,294
Supplemental Agreement for work within scope A00008 · A00008 C00012 add. Security fence & gates C00015 42" high partition walls @ toilets $274,481
Supplemental Agreement for work within scope A00007 · A00007 C00007 communication line to BP station 1 C00014 add fire hydrant SE corner $194,001
Supplemental Agreement for work within scope A00006 · A00006 C00008 gun locker canopy and clearing barrel $4,368
Supplemental Agreement for work within scope A00005 · A00005 C00004 add boxes and conduit $58,323
Supplemental Agreement for work within scope A00004 · A00004 C00009 chain link cage over walkways $169,219
Supplemental Agreement for work within scope A00003 · A00003 C00006 add lightning protection system $251,173
Supplemental Agreement for work within scope A00002 · A00002 c-00005 concrete for canopy slab and HC-ramp $64,805
Other Administrative Action P00003 · Clins 0001 - 0004: extend POP / BCD an additional eleven (11) days. POP / BCD changed from 15-AUG-2019 to 26-AUG-2019. $0
Supplemental Agreement for work within scope A00001 · 0027 EL paso CPC processing bldg & power BPS A00001 changes to bldg.&site $0
Other Administrative Action P00002 · Administrative modification to adjust POP to align with NTP. $0
Other Administrative Action P00001 · Increase total funding amount and other administrative actions. $100
Original award $15,282,372
Show all 23

About this award

This is a $19,707,852.45 firm-fixed-price definitive contract awarded by the U.S. Army Corps of Engineers to Koman Construction, LLC, an Alaska Native Corporation-owned small disadvantaged business, for the construction of the El Paso CPC Processing Building as part of the Border Patrol Station (BPS) project. The contract was sole-sourced under the 8(a) program. Key subcontractors include Harrison Walker & Harper LLC, a construction management firm, and Integrated Modular Solutions, LLC, an economically disadvantaged women-owned small business that provides modular construction services. The contract encompasses a range of construction and infrastructure services such as general trades, civil/site work, mechanical, electrical, and fire protection systems to build and outfit the processing facility. Koman Construction has extensive experience delivering similar construction projects for the Department of Defense, Department of Homeland Security, and other federal agencies.

Quick answers

Who was awarded contract W9126G19C0027?

W9126G19C0027 was awarded to Koman Construction, LLC by ENDIST Fort Worth (US Army Corps of Engineers) on May 11, 2019.

How much is contract W9126G19C0027 worth?

The government has obligated $19,707,852 on W9126G19C0027.

Was contract W9126G19C0027 competed?

The extent of competition for W9126G19C0027 was not available for competition. The government received 1 offer. It was set aside: 8(a) Sole Source.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award