Ldsm - volume 1 base

Ended Definitive Contract Awarded Last action

Contract number
W9126G19C0022
Awardee
Awarding agency
Obligated
$39,497,707

Award facts

Opportunity
Contract value 100% obligated
$39,497,706.65 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Funding agency
US Army Corps of Engineers Department of the Army, Department of Defense
Set-aside
No set-aside
Competition
Full and Open Competition · 4 offers Two Step
Pricing
Firm Fixed Price
Place of performance
Lewisville, TX 75057, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00045 · No cost or time. USACE agrees to accept all turf establishment as of 30 september 2022 in exchange for granite performing certain activities during the 1-year… $0
Supplemental Agreement for work within scope A00044 · Increased by $51,725. This MOD addresses SA1 erosion issues: jones ST shoulder reshaping, swale, rock check dams, clean culvert. ITR rock dike and check dams.… $51,725
Supplemental Agreement for work within scope A00043 · VEQ MOD. Net increase of $199,528.72, volume 1 base bid, option 1, and option 2 with no change unit price and no change in time. Clin's… $199,529
Supplemental Agreement for work within scope A00042 · VEQ MOD. Net decrease of $475,728, volume 1 base bid with no change in time. Clin's 17 & 26, quantity reduced. -$475,728
Supplemental Agreement for work within scope A00041 · Variation in estimated quantity MOD. Net decrease of $54,585.58, volume 1 base bid -$83,063 and volume 1 option 1 $28,477.42, with no change in contract time.… -$54,586
Other Administrative Action P00003 -$555,497
Supplemental Agreement for work within scope A00040 · Increased by $48,636 and 16 calendar days. This MOD addresses covid delays and concurrent misc subgrade changes, laerf RD and erosion changes, and punchlist… $48,636
Supplemental Agreement for work within scope A00039 · Reference MI042 weather time extension AUG 21. The contract completion date shall be extended by 6 calendar days by reason of this modification. No change in… $0
Supplemental Agreement for work within scope A00038 · Reference MI041 weather time extension JUL 21. The contract completion date shall be extended by 3 calendar days by reason of this modification. No change in… $0
Supplemental Agreement for work within scope A00037 · This modification addresses the veqs for clins 0054, 0056 & 0061 which work is complete. Contract amount increases by $88,590.00 with no change in contract… $88,590
Supplemental Agreement for work within scope A00036 · Increase $31,016 and 19 additional calendar days. Relocate the existing 4" waterline east of OW approx. 580 LF. Use minimum DR 11, 4" diameter hdpe pipe.… $31,016
Supplemental Agreement for work within scope A00035 · MOD covers: veqs for clin 0033 and 0077, PZ boxes and COL interconnect vault warranty and RE-inspection credit. Contract amount increases by $20,447.44 with… $20,447
Supplemental Agreement for work within scope A00034 · Additional crest crack quantities from MI021 modification. Contract amount increased by $24,114.07 with 0 calendar days. $24,114
Supplemental Agreement for work within scope A00033 · Reference MI037 unusually severe weather time extension JUN 2021. The contract completion date shall be extended by 7 calendar days by reason of this… $0
Supplemental Agreement for work within scope A00032 · Install a concrete drainage ditch at SA2 weir. Replaced SOD with hydroseed. VEQ for clins 0015 and 0020. Total contract amount is increased by $41,651.11 and… $41,651
Supplemental Agreement for work within scope A00031 · Install neenah rated boxes to 3 piezometers located at the crest road. Install cable and conduit for piezometers 177C, 175C and 19 and bring them to the data… $35,803
Supplemental Agreement for work within scope A00030 · Reference MI033 unusually severe weather time extension may 2021. The contract completion date shall be extended by 25 calendar days by reason of this… $0
Supplemental Agreement for work within scope A00029 · Reference MI032 unusually severe weather time extension APR 2021. The contract completion date shall be extended by 2 calendar days by reason of this… $0
Supplemental Agreement for work within scope A00028 · Increase the quantity of fine aggregate by 437 CY (for a total of fine aggregate at the outlet works of total 652 CY). Credit for not having to deploy… $111,983
Supplemental Agreement for work within scope A00027 · Increase in contract amount of $70,591.50 and 20 calendar days. This MOD addresses the VEQ for vfds and #89 coarse AGG as well as the pipe rail fence at the… $70,592
Supplemental Agreement for work within scope A00026 · Ldsm - volume 1 base. Reduce the width of jones ST west of the conduit to a paved width of 24 feet. This reduces clin 0037 and clin 0038 by 5400 SY each for a… -$178,200
Supplemental Agreement for work within scope A00025 · Cost is $35,945.00, no calendar days. This MOD is for the slide on tthe upstream berm between DAM STA 177+70 and 178+50. IT includes the excavation and… $35,945
Supplemental Agreement for work within scope A00024 · Cost is $16,473.00, no calendar days. IT covers credit for 18" RCP on the parallel corridor, replacing IT with ditch resurfacing as per sheet CG-411 at SA1.… $16,473
Supplemental Agreement for work within scope A00023 · Reference MI030 unusually severe weather time extension MAR 2021. The contract completion date shall be extended by 2 calendar days by reason of this… $0
Supplemental Agreement for work within scope A00022 · Cost is $118,626 and an additional 16 days to the contract. Ditch resurfacing at SA2 addresses the seep found south of the SCT along the existing ditch… $118,626
Supplemental Agreement for work within scope A00021 · Price increase of $67,288.45 with no change in contract time. Excavation at the outlet works clin 071 in excess of the bid schedule quantity. Final quantity… $67,288
Supplemental Agreement for work within scope A00020 · Price increase of $34,323.14 and 9 calendar days. Excavation of the crest crack repair to EL 550. Embankment by using lime treated material, geogrid. If… $34,323
Supplemental Agreement for work within scope A00019 · Price increase of $17,513 and 4 calendar days. Credit for fine aggregate specification change, coring 2 pipe penetrations in SA2 weir box, and removal and… $17,513
Supplemental Agreement for work within scope A00018 · Reference MI025 unusually severe weather time extension FEB 2021. The contract completion date shall be extended by 6 calendar days by reason of this… $0
Supplemental Agreement for work within scope A00017 · Construct granular filter weephole at the sinkhole, furnish 316 stainless steel wire cloth with 1/16" square woven or approved similar, backfill with C33 and… $16,120
Supplemental Agreement for work within scope A00016 · MI017 - R00017 $4877 & 3 calendar days delay removal and extend temp piezometer at SA1 total of 3 PZ's: p-DW 1, 5 and 11. $4,877
Supplemental Agreement for work within scope A00015 · Increase contract time by 22 days, allows materials haul via jones ST for limited time, resolves issues of out of spec #67 stone used at waterline, in… $0
Supplemental Agreement for work within scope A00014 · Reference no. R00015 MI015 weather time extension OCT 20. The contract completion date shall be extended by 5 calendar days by reason of this modification. $0
Supplemental Agreement for work within scope A00013 · Reference no. R00014 MI014 weather time extension SEP 2020. The contract completion date shall be extended by 2 calendar days by reason of this modification. $0
Supplemental Agreement for work within scope A00012 · $37839.25. Perform cone penetrometer testing (CPT) on completed vertical filter drain (VFD) installations and nearby in situ soils. Relocation 4" waterline at… $37,839
Other Administrative Action P00002 · 52.204-25 MOD $0
Supplemental Agreement for work within scope A00011 · This modification provides payment for 1628 VLF of dewatering system wellpoints in excess of the bid schedule quantity. No adjustment in unit price, the clin is… $179,080
Supplemental Agreement for work within scope A00010 · Zero cost modification. Provide a credit for cable post not in concrete, as only 1 out of every 4 were in concrete. Preserve the piezometers in conflict… $0
Supplemental Agreement for work within scope A00009 · $8778 install one additional temp PZ in SA1. Cover the existing slide with plastic, cutting the current matting in the scarp area, cut a notch on the top and… $8,778
Additional Work (new agreement, FAR part 6 applies) A00008 · Final quantity, 300.3 VLF, and price adjustment, $8,392.59, for clin 0032. Clarification on the location and configuration of the non-perforated pipe transition… $8,393
Supplemental Agreement for work within scope A00007 · This modification extends the time for delays caused by unusually severe weather during 01 march 2020 through 31 march 2020. The contract completion date… $0
Additional Work (new agreement, FAR part 6 applies) P00001 · Change the borrow haul route configuration to where the 2 lanes are not adjacent. Shift the utility corridor to the south to match the old clearing limits, stay… $359,000
Additional Work (new agreement, FAR part 6 applies) A00005 · For volume 1, option 2 work, install and monitor five (5) settlement pins in the embankment slope above the top of excavation. Also make one of the borings in… $27,735
Additional Work (new agreement, FAR part 6 applies) A00006 · Reroute the existing 4" waterline on the file "COL WL reroute option 2" PDF from the contractor. The hdpe pipe shall be DR 11 (160 PSI), 4" nominal diameter,… $63,350
Supplemental Agreement for work within scope A00004 · The contract time is extended by 3 calendar days per far 52.249-10, default, for unusually severe weather that delayed the project during the month of january… $0
Additional Work (new agreement, FAR part 6 applies) A00003 -$62,683
Additional Work (new agreement, FAR part 6 applies) A00002 · Ldsm - volume 1 base MI003 - R00002 - dewatering system changes: no cost changed POP end date to 14 FEB 2021 $0
Additional Work (new agreement, FAR part 6 applies) A00001 · Ldsm - volume 1 base. Increase contract by $14,021 for partnering facilitator. No change in contract time. $14,021
Original award $39,090,953
Show all 49

About this award

This contract was awarded by the Department of the Army Corps of Engineers to Granite Construction Company, a for-profit construction services firm. The contract, valued at $39,497,706.65, is for the LDSM - VOLUME 1 BASE project, a Firm Fixed Price Definitive Contract with no set-aside designation. The contract work is to be performed in Lewisville, Texas and has a completion date of September 1, 2021. Granite Construction Company is the prime contractor on this infrastructure project, which likely includes tasks such as airfield paving, road construction, drainage systems, and retaining walls based on the company's past performance on similar federal contracts. The award does not mention any major subcontractors.

Quick answers

Who was awarded contract W9126G19C0022?

W9126G19C0022 was awarded to Granite Construction Company by ENDIST Fort Worth (US Army Corps of Engineers) on May 30, 2019.

How much is contract W9126G19C0022 worth?

The government has obligated $39,497,707 on W9126G19C0022.

Which agency awarded contract W9126G19C0022?

ENDIST Fort Worth (US Army Corps of Engineers) awarded W9126G19C0022, with funding from US Army Corps of Engineers (Department of the Army).

Was contract W9126G19C0022 competed?

The extent of competition for W9126G19C0022 was full and open competition. The government received 4 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award