Construct oxbow valley storage sites a & c, fort worth, texas, period of perfomance: from contract award through 465 days after NTP is issued.

Ended Definitive Contract Awarded Last action

Contract number
W9126G15C0030
Awardee
Awarding agency
Obligated
$30,077,836

Award facts

Contract value 97% obligated
  • $30,077,835.68 Current, with exercised options
  • $30,902,835.68 Potential, with all options
Completion date 100% complete
Current and potential, with all options
Funding agency
US Army Corps of Engineers Department of the Army, Department of Defense
Set-aside
No set-aside
Competition
Full and Open Competition · 2 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Fort Worth, TX 76111, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00008 $400,000
Other Administrative Action P00007 · Oxbow a & c - ALT. Sched. No 2 $0
Change Order A00011 $494
Change Order A00010 $112,345
Change Order A00009 $707
Other Administrative Action A00008 $0
Change Order A00007 · Contract for fort worth central city, upper trinity river, riverside oxbow - sites a and c, valley storage mitigation at fort worth, texas. Reference no.… $0
Change Order A00006 · Contract for FT worth central city, upper trinity river, riverside oxbow - sites a and c, valley storage mitigation at fort worth, texas. Reference no.… $90,000
Supplemental Agreement for work within scope P00006 · Valley storage mitigation, riverside oxbow sites a & c, additional excavation $1,335,988
Supplemental Agreement for work within scope P00005 · Valley storage mitigation, riverside oxbow a & c, RE-grading for low spots $113,411
Supplemental Agreement for work within scope P00004 · Valley storage mititgation, riverside oxbow a & c, concrete debris $241,369
Change Order P00003 · Modification for the removal of unsuitable materials.oxbow a & c - ALT. Sched. No 2 $104,058
Supplemental Agreement for work within scope A00005 · , valley storage mitigation, riverside oxbow sites a & c, time extension due to weather delays $0
Supplemental Agreement for work within scope P00001 · Valley storage mitigation, riverside oxbow sites a & c, beach street DAM repair for regulator $41,388
Supplemental Agreement for work within scope A00004 · , valley storage mitigation, riverside oxbow sites a and c, time extension due to weather delays. $0
Supplemental Agreement for work within scope A00003 · Time extension due to adverse weather, oxbow sites a & c $0
Supplemental Agreement for work within scope A00002 · Removal of unsuitable materials, oxbow sites a & c - $46,201
Supplemental Agreement for work within scope A00001 · Oxbow a & c, time extension due to weather delays $0
Original award $27,591,875
Show all 19

About this award

This firm fixed-price contract was awarded by the U.S. Army Corps of Engineers (USACE) to Thalle Construction Co Inc. in the amount of $30,902,835.68. The contract is for the construction of the Oxbow Valley Storage Sites A & C in Fort Worth, Texas, with a period of performance from the contract award through 465 days after the Notice to Proceed is issued. The contract does not have a set-aside designation. Thalle Construction Co Inc. is a for-profit construction company specializing in large-scale infrastructure projects for federal agencies such as the USACE and the Bureau of Reclamation. The company has demonstrated expertise in complex engineering and construction tasks across various sectors, including water resources, civil engineering, and specialized facility construction.

Quick answers

Who was awarded contract W9126G15C0030?

W9126G15C0030 was awarded to Thalle Construction Co Inc. by ENDIST Fort Worth (US Army Corps of Engineers) on August 27, 2015.

How much is contract W9126G15C0030 worth?

The government has obligated $30,077,836 on W9126G15C0030. Its potential value, with all options, is $30,902,836.

Which agency awarded contract W9126G15C0030?

ENDIST Fort Worth (US Army Corps of Engineers) awarded W9126G15C0030, with funding from US Army Corps of Engineers (Department of the Army).

Was contract W9126G15C0030 competed?

The extent of competition for W9126G15C0030 was full and open competition. The government received 2 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities