FY18 sabin DAM removal, boardman river restoration, traverse city, MI.

Ended Definitive Contract Awarded Last action

Contract number
W911XK18C0007
Awardee
Awarding agency
Obligated
$4,492,286

Award facts

Opportunity
Contract value 100% obligated
$4,492,285.91 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 4 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Traverse City, MI 49696, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Definitize Change Order A00006 · FY18 sabin DAM removal boardman river. Modification issued for reduction in variation in estimated quantities for temp bulk bag cofferdam, seed floodplain… -$112,429
Definitize Change Order A00005 · Sabin DAM removal, traverse city, MI. Modification issued for providing alternate erosion control blankets $9,115
Definitize Change Order A00004 · Sabin DAM removal boardman river. Modification issued for additional DIG and pitch operation, channel bed and floodplain material placement, large wood and… $389,211
Definitize Change Order A00003 · Sabin DAM removal boardman river modification A00003 for supplemental channel riffle material and vegetation salvage $497
Definitize Change Order A00002 · MOD A00002 basic change GH004: remove SSP at powerhouse. This change provides, under contract clause 52.236-2 "differing site conditions", for removal of 50… $11,943
Change Order A00001 · FY18 sabin DAM removal boardman river at traverse city, MI. Modification issued for part 1 modification to add channel substrate & vegetation salvage. $150,000
Change Order P00003 · Sabin DAM removal boardman river - exercised division 3 options items 3,4,7,8 and 9. $260,671
Other Administrative Action P00002 · Sabin DAM removal boardman river option time extension $0
Change Order P00001 · Sabin DAM removal boardman river - change completion date based on the notice to proceed $0
Original award $3,783,278

About this award

This firm-fixed-price contract was awarded by the Department of the Army Corps of Engineers Engineering District Detroit to Job Site Services Inc., a for-profit Subchapter S corporation, for the FY18 Sabin Dam Removal and Boardman River Restoration project in Traverse City, Michigan. The contract has a potential value of $4,492,285.91 and a completion date of August 22, 2019. The original solicitation, W911XK-17-B-0004, was a full and open competition with no set-aside requirements. The contract requires the demolition and removal of the Sabin Dam Powerhouse, spillway, and appurtenances, as well as the restoration of approximately 4,500 linear feet of the Boardman River. Job Site Services Inc. has previously served as a subcontractor on federal environmental remediation contracts.

Quick answers

Who was awarded contract W911XK18C0007?

W911XK18C0007 was awarded to Job Site Services Inc. by ENDIST Detroit (US Army Corps of Engineers) on June 6, 2018.

How much is contract W911XK18C0007 worth?

The government has obligated $4,492,286 on W911XK18C0007.

Was contract W911XK18C0007 competed?

The extent of competition for W911XK18C0007 was full and open competition. The government received 4 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award