FY10 contract for southfield drain no. 2 drain rehabilitation project cured in place pipe lining system

Ended Definitive Contract Awarded Last action

Contract number
W911XK10C0020
Awardee
Awarding agency
Obligated
$1,444,263

Award facts

Contract value 135% obligated
$1,071,350.37 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 7 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Lathrup Village, MI 48076, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change Order P00010 · Arra::yes::arra - variation in estimated quantity modification to adjust the material being sent to a landfill from a sewer pipe. -$8,993
Change Order P00010 · Variation in estimated quantity to adjust the materials being sent to a landfill from a sewer pipe. -$2,087
Change Order P00009 · Arra::yes::arra, sewer cleaning addition $27,284
Change Order P00009 · Non-federal funds - sewer cleaning addition $0
Change Order P00008 · Non-federal funds - time extension $0
Change Order P00008 · Arra::yes::arra, time extension $0
Change Order P00007 · Non-federal funds -, siphon cleaning $0
Change Order P00007 · Arra::yes::arra as part of the operations and maintenance contract project: FY10 contract for southfield drain no. 2 drain rehabilitation project cured in place… $100,860
Change Order P00006 · Non-federal funds - change disposal site location. $0
Change Order P00006 · Arra::yes::arra, change disposal site location $18,326
Change Order P00005 · Non-federal funds - repar roughly 15' of pipe $0
Change Order P00005 · Arra::yes::arra, repair roughly 15' of pipe $31,390
Change Order P00004 · Non-federal funds - add additional pipe lining $0
Change Order P00004 · Arra::yes::arra, add additional pipe lining $16,800
Change Order P00003 · Arra::yes::arra, change pipe diameter $4,290
Change Order P00003 · Change diameter of pipe. $0
Change Order P00002 · Arra::yes::arra time extension $0
Change Order P00002 · Non-federal funds - time extension $0
Change Order P00001 · Non-federal funds - install a different diameter pipe $0
Change Order P00001 · Arra::yes::arra as part of operations and maintenance contract project : FY10 contract for southfield drain no. 2 drain rehabilitation project cured n place… $1,253
Modification $375,000
Original award Arra::yes::arra as part of the operations and maintenance contract project: FY10 contract for southfield drain no. 2 drain rehabilitation project cured in place… $880,141
Show all 22

About this award

This is a federal contract awarded by the U.S. Army Corps of Engineers (USACE) to Blaze Contracting Inc., a small business, for the FY10 Southfield Drain No. 2 Drain Rehabilitation Project. The contract is a definitive, firm-fixed-price contract valued at $1,071,350.37. The contract is for a cured-in-place pipe lining system to rehabilitate the Southfield Drain No. 2 in Southfield, Michigan. The contract has a total small business set-aside designation and was awarded on September 23, 2010, with a target completion date of March 13, 2012.

Quick answers

Who was awarded contract W911XK10C0020?

W911XK10C0020 was awarded to Blaze Contracting Inc. by ENDIST Detroit (US Army Corps of Engineers) on September 23, 2010.

How much is contract W911XK10C0020 worth?

The government has obligated $1,444,263 on W911XK10C0020. Its current value, with exercised options, is $1,071,350.

Was contract W911XK10C0020 competed?

The extent of competition for W911XK10C0020 was full and open competition after exclusion of sources. The government received 7 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award