Stli-155567,statue of liberty national monument, complete life and safety upgrades.

Ended Definitive Contract Awarded Last action

Contract number
INP11PC20096
Awardee
Awarding agency
Obligated
$43,854,565

Award facts

Opportunity
  • N2011110096 Solicitation number
Contract value 100% obligated
$43,854,565.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
236220 Commercial and Institutional Building Construction
PSC
Not on record
Set-aside
No set-aside
Competition
Full and Open Competition · 3 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
New York, NY 10004, USA
Legislative mandates
National interest action
Hurricane Sandy 2013

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope 25 $98,055
Supplemental Agreement for work within scope 24 $1,276,995
Supplemental Agreement for work within scope 23 $15,957
Supplemental Agreement for work within scope 22 $2,051,208
Supplemental Agreement for work within scope 21 $1,007,991
Supplemental Agreement for work within scope 20 $609,196
Supplemental Agreement for work within scope 19 $973,612
Supplemental Agreement for work within scope 18 $349,253
Supplemental Agreement for work within scope 17 $1,468,256
Supplemental Agreement for work within scope 16 $352,862
Supplemental Agreement for work within scope 15 $1,048,202
Supplemental Agreement for work within scope 14 $44,895
Supplemental Agreement for work within scope 13 $3,039,282
Supplemental Agreement for work within scope 12 $429,714
Supplemental Agreement for work within scope 11 $489,309
Other Administrative Action 10 $0
Change Order 9 · Stli 155567, life and safety upgrades, statue of liberty national monument, new york county, NY--modification 0009 extends the contract completion date from… $300,000
Change Order 8 · Modification revising completion date to construction services contract (NPS pmis #stli 155567) for life and safety upgrades statue of liberty national… $228,620
Change Order 6 · Stli 155567 unilateral change order modification deleting MOD 5 funding amount -$250,000
Change Order 7 · Stli 155567 unilateral change order modification related to RE-opening of statue of liberty $250,000
Supplemental Agreement for work within scope 5 $1,099,601
Supplemental Agreement for work within scope 4 · Stli 155567, life and safety upgrades, statue of liberty national monument, new york county, NY--modification 0004 definitizes change orders 05 revision 1, 06… $1,362,792
Other Administrative Action 3 · The purpose of this modification is to make administrative changes to the contract within the contract line item (clin) structure in order to facilitate the… $0
Supplemental Agreement for work within scope 2 · Stli 155567, life and safety upgrades, statue of liberty national monument, new york county, NY -- modification 0002 definitizes change orders 01, 02, 04 and 05… $359,765
Other Administrative Action 1 · Administrative modification to contract correcting accounting and appropriation data. $0
Original award $27,249,000
Show all 26

Quick answers

Who was awarded contract INP11PC20096?

INP11PC20096 was awarded to Joseph A Natoli Construction Corp by National Office (National Park Service) on August 4, 2011.

How much is contract INP11PC20096 worth?

The government has obligated $43,854,565 on INP11PC20096.

Was contract INP11PC20096 competed?

The extent of competition for INP11PC20096 was full and open competition. The government received 3 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award