Recovery gwmp pmis #150123 rehabilitate arlington house, outbuilding and grounds, phase 2A and 2B, george washington memorial parkway

Ended Definitive Contract Awarded Last action

Contract number
INP10PC76371
Awardee
Awarding agency
Obligated
$3,285,923

Award facts

Contract value 100% obligated
$3,285,923.40 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
PSC
C119 Other Buildings
Set-aside
Competitive 8(a)
Competition
Full and Open Competition after exclusion of sources · 3 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Fort Myer, Arlington, VA 22211, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Funding Only Action 9 · Recovery gwmp-150123, modification no. 0009, an administrative modification which adds funding in the amount of $115,345.40 that were holdback funds that were… $115,345
Change PIID 8A $0
Other Administrative Action 8 · Recovery gwmp-150123--the purpose of this modification 0008 is to make administrative changes to the contract within the contract line item (clin) structure… $0
Supplemental Agreement for work within scope 7 · Recovery gwmp-150123, modification no. 0007: definitizes mods 5 and 6, RPP-9 and COD-8. $52,062
Change Order 6 · Recovery gwmp-150123, modification no. 0006: a unilateral modificaiton which adds work within scope to handle differing site conditions and errors and omissions… $20,980
Change Order 5 · Recovery gwmp-150123, modification no. 0005, a unilateral modificaiton which adds work within scope to handle differing site conditions and errors and omissions… $45,704
Supplemental Agreement for work within scope 4 · Modification no. 0004 adds work within scope to handle differing site conditions. $68,436
Definitize Change Order 3 · Modification no. 0002 definitizes a change order and adds work within scope to handle differing site conditions. $31,907
Definitize Change Order 2 · Modifcation no. 0002 definitizes changes under the contract due to differing site conditions and specification discrepancies. $29,373
Definitize Change Order 1 · Modification no. 0001 definitizes changes under the contract due to differing site conditions and extends the period of performance as a result of the differing… $82,116
Original award $2,840,000
Show all 11

About this award

This is a $3,285,923.40 firm fixed price definitive contract awarded by the National Office of the National Park Service, a civilian federal agency, to Bell / Biscayne JV, LLC, an 8(a) joint venture. The contract is for the rehabilitation of the Arlington House, outbuildings, and grounds on the George Washington Memorial Parkway, which is part of the Recovery program's Project Management Information System (PMIS). The contract has a completion date of April 25, 2013 and was awarded on May 13, 2010 through a competitive 8(a) set-aside solicitation process.

Quick answers

Who was awarded contract INP10PC76371?

INP10PC76371 was awarded to Bell / Biscayne JV, LLC by National Office (National Park Service) on May 13, 2010.

How much is contract INP10PC76371 worth?

The government has obligated $3,285,923 on INP10PC76371.

Was contract INP10PC76371 competed?

The extent of competition for INP10PC76371 was full and open competition after exclusion of sources. The government received 3 offers. It was set aside: Competitive 8(a).

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award