Definitive Contract INIRA000310033
Award Date 5/25/10
Potential Completion Date 3/31/11
Potential Value $727K
Funding Federal Agency
Contracting Federal Agency
Ultimate Awardee
Not listed NAICS Category
PSC Category
Set-Aside Type
No Set-Aside Used
Federal Contract Vehicle
- Not listed
Extent Competed
Full and Open Competition
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Lawton, OK 73502, USA
Solicitation Procedures
Sealed Bid
Number Of Offers Received
1
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- This is a definitive contract awarded by the Department of Agriculture Agricultural Research Service to Cimarron Construction Corporation, a self-certified small disadvantaged business. The contract, valued at $928,400.83, is for the replacement of Bridge A and Bridge D in El Reno, Oklahoma. It was set aside for small businesses and is a firm fixed-price contract. The original solicitation was posted as a pre-solicitation notice on FedBizOpps, seeking a contractor to furnish labor, material, and...
- <p>This is a $441,197.70 firm fixed-price definitive contract awarded by the Federal Highway Administration, a civilian agency, to Marbery Concrete Inc., a self-certified small disadvantaged business. The contract is for the KS FLAP CR1200(1) PLEASANTON EAST LAKE BRIDGE project located in Pleasanton, KS, with an ultimate completion date of August 31, 2016. The contract was not set aside for any specific business type.</p>
- This is a firm fixed-price purchase order contract awarded by the Plains Area division of a civilian U.S. government agency. The contract is for $29,438.80 and was awarded on May 4, 2020 to Cimarron Construction Co LLC, a self-certified small disadvantaged business located in Oklahoma City, Oklahoma. The contract is for work done on Bridge D in El Reno, Oklahoma and the ultimate completion date is June 4, 2020. This contract action is a ratification of an unauthorized commitment made...
- This is a definitive contract awarded by the Federal Highway Administration, a civilian agency, to Bell Contracting, Inc., a woman-owned small business, for $432,146.90. The contract is for the installation of a bridge and precast reinforced concrete box culverts at three project sites in Neosho Rapids, Kansas. The contract has a firm fixed price pricing type and an ultimate completion date of February 11, 2016. It was awarded on September 3, 2015 and was not set aside for any specific...
- This $2,211,641.51 firm fixed price contract was awarded to Hooker Creek Inc., a HUBZone certified small business, by the Department of Transportation Federal Highway Administration. The contract is for the construction of the CA ERFO KLAMATH NF 18N31(1) Upper West Branch Bridge in Acampo, California. The project entails the full replacement of a wildfire-damaged bridge with a 90-foot by 16-foot concrete bridge incorporating wood cellulose nano-crystals. Key work includes removal of existing...
- This is a definitive, firm-fixed price contract awarded by the Federal Highway Administration (FHWA), a civilian agency, to Randy Kinder Excavating Inc., a Service-Disabled Veteran-Owned Small Business (SDVOSB). The $1,552,331.25 contract is for the realignment and reconstruction of approximately 0.3 miles of County Road 64 (Big Fork Athens Road) in the Ouachita National Forest. The work includes grading, aggregate base, chip seal, asphalt concrete pavement, gabion retaining wall, drainage,...
- <p>This is a federal contract award from the Federal Highway Administration (FHWA), a civilian agency, to Razz Construction, Inc., a small business, for the repair of the Hard Creek Bridge in Marblemount, Washington. The contract is a definitive, firm-fixed price contract with a ceiling value of $426,046.55 and a completion date of May 27, 2016. The contract was set aside for small businesses.</p>
- <p>This is a $305,443.25 firm fixed-price definitive contract awarded by the Operations Center East (a civilian federal agency) to Arrodesign Inc. for the AQUATIC PASSAGE FR25 BRIDGE RECONSTRUCTION project. The contract has a set-aside designation for total small businesses and an ultimate completion date of May 15, 2011. The contract is funded under the agency's Capital Improvement & Maintenance program. No additional subcontractor information is provided.</p>
- This is a $292,600.83 firm fixed-price definitive contract awarded by the United States Department of Agriculture Forest Service to Price Contracting Inc., a veteran-owned small business prime contractor. The contract is for the Canyon Creek Bridge/Peter's Creek Culvert Replacement project on the Flathead National Forest, which involves road construction, reconstruction, and drainage structure work. This award is part of the American Recovery and Reinvestment Act (ARRA) and must be completed...
- The Federal Highway Administration awarded a $6,737,948.97 firm-fixed-price contract to Krci LLC, a small disadvantaged business, for the construction of a new 125-foot precast deck bulb T girder bridge in Cle Elum, Washington. The project involves demolishing the existing concrete bridge and constructing the new bridge with abutments on cast-in-drilled piles. Major subcontractors include Malcolm Drilling Company, Inc., Combined Construction Inc., Columbia Basin Striping LLC, B&B...
This is a $726,902.92 firm fixed price construction contract awarded by the Federal Highway Administration, a civilian agency, to K & R Builders, Inc. for the construction of the East Cache Creek Bridge in Lawton, Oklahoma. The contract was awarded on May 25, 2010 with a completion date of March 31, 2011. This contract was not set aside for any small business program.
Generated 4/2/25, 10:04 AM
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
E. Cache Creek Bridge Project | RA000310027 | Department of the Interior Bureau of Indian Affairs Central Office | Award Notice 1/1 | 4/5/10, 3:46 PM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| 4 | Close Out | ($13k) | 5/20/11 | |
| 3 | Funding Only Action | ($11k) | 10/8/10 | |
| 2 | Change Order | $5.7k | 7/23/10 | |
| 1 | Funding Only Action | $21.7k | 6/1/10 | |
| Not listed | Not listed | $723.3k | 5/25/10 |