Design build hitchcock hall building 37

Ended Definitive Contract Awarded Last action

Contract number
GS11P17MKC0017
Awardee
Awarding agency
Obligated
$20,783,996

Award facts

Opportunity
Contract value 100% obligated
$20,783,996.35 Current and potential, with all options
Completion date 100% complete
  • Current, with exercised options
  • Potential, with all options
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 4 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Washington, DC 20032, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action PO22 · DE-obligate funds in excess of contract vlaue after settlement of claim for contract closeout -$86,652
Supplemental Agreement for work within scope PS21 · Settlement of 11/24/20 certified claim. Parties agree and understand this agreement is a compromise and settlement of disputed claims relating to and arising… $670,000
Supplemental Agreement for work within scope PS19 · Provide labor, materials, equipment and supervision for miscellaneous repairs under the hitchcock project $158,059
Change Order PC18 · Various CES, general conditions fire alarm revisions cooling for MDF room turn board transition 2ND floor lobby relocation of junction box additional electrical… $515,377
Change Order PC17 · Directive, unilateral equitable adjustment to provide labor, materials, supervision and equipment to perform the scopes of work as detailed in CE 41, 43, 46 and… $544,305
Supplemental Agreement for work within scope PS16 · To perform the scopes of work under various CES $557,952
Other Administrative Action PA15 · The purpose for the mass MOD is to change the current local billing office address to the new designated billing office address of bcfa. Approval of the mass… $0
Change Order PS14 $902,713
Change Order PS13 $404,467
Other Administrative Action PA12 · Contract no. GS-11-p-17-MK-c-0017 hitchcock hall building 37, ST elizabeths west campus, SE, wash DC MOD PA12 - no cost administrative modification - funding… $0
Change Order PC11 $450,883
Supplemental Agreement for work within scope PS10 $11,851
Other Administrative Action PO09 · Contract no. GS-11-p-17-MK-c-0017, hitchcock hall, adaptive reuse building 37, ST elizabeths west campus, SE, wash., DC MOD PO09: no cost administrative… $0
Supplemental Agreement for work within scope PS08 · Contract GS-11-p-17-MK-c-0017 hitchcock hall, adaptive reuse building 37, ST elizabeths west campus, SE, wash., DC MOD PS08 - final settlement of hitchcock hall… $179,375
Change Order PC07 · Contract GS-11-p-17-MK-c-0017 hitchcock hall building 37 phase II adaptive reuse unilateral directive MOD PC07 - various scope additions NTE $353,617.00. In… $353,617
Change Order PS06 · Water infiltration issues $84,850
Supplemental Agreement for work within scope PS05 · Additional AV.IT pathways in building 37 and extended general conditions $268,699
Supplemental Agreement for work within scope PS04 · CES 4,5,7,8. Concrete, chilled water and condensate lines, casing and steel, lula elevator no. 3, soundtraps $176,844
Supplemental Agreement for work within scope PS02 · Lead base paint remediation services $394,431
Change Order PC01 · PDL NTE for containment, miscellaneous cleaning and air filtering of hazardous materials in the critical areas of building 37 to allow work to continue safely… $45,385
Original award $15,151,840
Show all 21

About this award

This is a Definitive Contract awarded by the General Services Administration Public Buildings Service National Capital Region to Fei-Winmar Joint Venture, a minority-owned small business, for a design-build project to construct the Hitchcock Hall Building 37 in Washington, DC. The $20,783,996.35 firm fixed-price contract was set aside for total small business participation. The contractor provides a range of construction services including building design, installation of conduit and cooling systems, painting, lighting, and waste management. Over time, the contractor has expanded its customer base from the Department of Defense and Department of Health and Human Services to also include the Department of Justice and GSA.

Quick answers

Who was awarded contract GS11P17MKC0017?

GS11P17MKC0017 was awarded to Fei-Winmar Joint Venture by National Capital Region (Public Buildings Service) on June 30, 2017.

How much is contract GS11P17MKC0017 worth?

The government has obligated $20,783,996 on GS11P17MKC0017.

Was contract GS11P17MKC0017 competed?

The extent of competition for GS11P17MKC0017 was full and open competition after exclusion of sources. The government received 4 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award