Recovery: construct security gates and fences, DHS consolidation program, ST. Elizabeth west campus, SE, washington, D.C.
Ended Definitive Contract Awarded Last action
- Contract number
- GS11P10MKC0058
- Awardee
-
Balfour Beatty Construction, LLC UEI PLF5D1ZJDQ63
- Awarding agency
-
National Capital Region
Public Buildings Service, General Services Administration
- Obligated
- $67,908,476
Award facts
- Opportunity
-
- GS11P10MKC0058 Solicitation number
- RECOVERY:SECURITY PERIMETER for the Consolidation of the Department of Homeland Security (DHS) at the St. Elizabeths Hospital site in Anacostia, Washington, DC. Award Notice · Posted Mar 12, 2010
- Contract value 100% obligated
- $67,908,475.97 Current and potential, with all options
- Completion date 100% complete
-
- Current, with exercised options
- Potential, with all options
- NAICS code
- 236220 Commercial and Institutional Building Construction
- PSC
- Y111 Construction Of Office Buildings
- Set-aside
- No set-aside
- Competition
- Full and Open Competition · 8 offers Negotiated Proposal / Quote
- Pricing
- Firm Fixed Price
- Place of performance
- Washington, DC 20032, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Funding Only Action | -$74 | |
| Funding Only Action | -$0 | |
| Supplemental Agreement for work within scope | $487,291 | |
| Supplemental Agreement for work within scope | $275,824 | |
| Other Administrative Action | $0 | |
| Supplemental Agreement for work within scope | -$73 | |
| Supplemental Agreement for work within scope | $151,814 | |
| Supplemental Agreement for work within scope | $314,346 | |
| Other Administrative Action | $0 | |
| Other Administrative Action | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Other Administrative Action | $0 | |
| Supplemental Agreement for work within scope | $256,499 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $165,478 | |
| Supplemental Agreement for work within scope | $92,105 | |
| Other Administrative Action | $0 | |
| Supplemental Agreement for work within scope | $23,848 | |
| Supplemental Agreement for work within scope | $70,678 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $439,934 | |
| Supplemental Agreement for work within scope | $0 | |
| Change Order | $177,427 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $1,999,153 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Other Administrative Action | $0 | |
| Supplemental Agreement for work within scope | $7,887,825 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Original award | $55,566,400 |
Show all 39
About this award
This is a federal contract awarded by the National Capital Region of the General Services Administration (GSA) to Balfour Beatty Construction, LLC to construct security gates and fences as part of the Department of Homeland Security (DHS) Consolidation Program at the St. Elizabeth West Campus in Washington, D.C. The $67,908,475.97 firm-fixed-price contract has an ultimate completion date of October 6, 2017. No set-aside designation was used for this award.
Major subcontractors on this project include Concrete Technology Services Mid Atlantic, Inc. for demolition, United General Contractors, Inc. for metal wall panels, Pro-Air, Inc. for plumbing/HVAC, and several other firms providing services such as electrical work, roofing, waterproofing, and landscaping. The contract is associated with consolidating DHS operations at the St. Elizabeth West Campus, which is a multi-year initiative to modernize and secure federal facilities in the National Capital Region.
Quick answers
Who was awarded contract GS11P10MKC0058?
GS11P10MKC0058 was awarded to Balfour Beatty Construction, LLC by National Capital Region (Public Buildings Service) on September 10, 2010.
How much is contract GS11P10MKC0058 worth?
The government has obligated $67,908,476 on GS11P10MKC0058.
Was contract GS11P10MKC0058 competed?
The extent of competition for GS11P10MKC0058 was full and open competition. The government received 8 offers.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award