Award facts

Opportunity
Contract value 100% obligated
$152,295,684.50 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 5 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Washington, DC 20407, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PS71 · Arra funded -recovery act modification to an existing contract- t he contractors signature in block 15B indicates agreement to a deduction to the contract in… -$0
Supplemental Agreement for work within scope PS70 · Recovery act modification to an existing contract- the purpose of this modification is to settle the pdls for tenant fit-out (clin 0019) and revisions for… -$106,545
Supplemental Agreement for work within scope PS69 · The purpose of this modification is to provide labor, material and equipment, in accordance with PC 415, to install an additional media converter on the back… $14,150
Supplemental Agreement for work within scope PS67 · The purpose of this modification PS67 is to settle the PDL for alternate blast mitigation-clin 0024. PS67 also incorporates various scope changes (CES and pcos)… -$879
Supplemental Agreement for work within scope PS68 · The purpose of this modification is to provide labor, mateiral and equipment for PCO 414R1, to install two manufacturerer provided turnstile control boxes at… $5,000
Supplemental Agreement for work within scope PS61 · The purpose of this modification is to provide labor, material, and equipment for PCO 187 in accordance to the scope of work summary dated april 30, 2014. The… $45,000
Supplemental Agreement for work within scope PS62 · The purpose of this modification is to provide labor, mateiral and equipment for pcos 198, 340, 355, 366, 373 in accordance to the scope of work summary dated… $63,949
Supplemental Agreement for work within scope PS63 · Contractor is to provide material, equipment and labor to add drywall ceiling. The following modification is a deduction of -($84,518.00) in contract price. -$84,518
Supplemental Agreement for work within scope PS57 · The contractor's signature in block 15B indicates agreement to perform all work associated with this modification for the total amount of $90,846.00. The… $90,846
Supplemental Agreement for work within scope PS53 · The contractor's signature in block 15B indicates his agreement to perform all work associated with this modification for the total amount of $98,850.00. The… $98,850
Supplemental Agreement for work within scope PS58 $73,323
Supplemental Agreement for work within scope PS59 · The contractor's signature in block 15B indicates agreement to perform all work associated with this modification for the total amount of $99,930.00. The… $99,930
Other Administrative Action PA69 · Transfer contracting officer authority from vincent matner to mary pineda. $0
Supplemental Agreement for work within scope PS66 · Contractor to provide services to complete various pcos in support of the 1800 f headquarters project. $3,209,937
Other Administrative Action PA64 · This administrative modification hereby transfers this contract from: contracting officer, mary e. Pineda to: contracting officer, vince e. Matner, office of… $0
Supplemental Agreement for work within scope PS60 · The purpose of this modification is to provide all labor, materials, and equipment for the changes to the guard booth $30,000
Supplemental Agreement for work within scope PS56 · The purpose of this modification is to provide labor, materials, and equipment in accordance to CE353 R01, CE357, CE362, CE363, CE364, CE366, PC403R1, PC405,… $125,642
Supplemental Agreement for work within scope PS55 · The purpose of this modification is to provide all labor, materials, and equipment to perform work in accordance to PCO335, PCO387, PCO401, and PCO402. $17,576
Supplemental Agreement for work within scope PS54 · The purpose of this modification is to provide labor, material, and equipment for CE 307 and pcos 070, 167R1, 190, 195, 197R1, 228, 232R1, 254, 292, 302 in… $1,053,758
Supplemental Agreement for work within scope PS52 · The purpose of this modification is to provide all labor, materials and equipment to perform bulletin 55 - training center in accordance with CE#298 dated 9 APR… $1,541,705
Supplemental Agreement for work within scope PS51 · Black out shades $11,328
Supplemental Agreement for work within scope PS50 · The purpose of this modification is to definitize modificaiton PC48, based on CE#345, dated 12/12/2013 which was issued in the amount not-to-exceed… $435,000
Supplemental Agreement for work within scope PS42 · The purpose of this modification is to provide all labor, material, and equipment for PCO 346, "digital signage" - green awareness dashboard customization in… $11,347
Supplemental Agreement for work within scope PS47 · Recovery - the purpose of this modification is to provide material, equipment, and labor for CE336, and PCO's 298, 315, 316, 360, and 362. The work shall be… $100,935
Supplemental Agreement for work within scope PS49 · Recovery - the purpose of this modification is to provide labor, material and equipment for contractor proposals (pcos) 383, 384, 285, and 389. The work shall… $127,000
Supplemental Agreement for work within scope PS46 · The purpose of this modification is to provide labor, material, and equipment for CE's 203, 205, 294, 299, 305, 308, 319, 322, 338, 343; and PCO's 143, 252,… $763,134
Supplemental Agreement for work within scope PS45 · The purpose of this modification is to provide all labor, material, and equipment for CES 214, 280, 293, 324, 337, 341, 347, 349, and pcos 257/301, 278, 284,… $122,144
Change Order PC48 · The purpose of this modification is to provide labor, materials, and equipment in accordance to CE#345, dated 08/23/2013, for security scope revision, SIS2435… $200,000
Supplemental Agreement for work within scope PS44 $62,000
Supplemental Agreement for work within scope PS41 $17,394
Supplemental Agreement for work within scope PS43 · The purpose of this modification is to provide all labor, material, and equipement for PCO305, installing lighting control station in OIG conference rooms… $5,780
Supplemental Agreement for work within scope PS38 · The purpose of this modification is to settle a/v & IT and security clins 0021 and 0022. The modification also incorporates scope changes (CES) that have been… -$2,212,446
Supplemental Agreement for work within scope PS40 · The purpose of this modification is to provide labor, material, and equipment for CE#340, GSA phase 2 refresh telecom. $52,549
Supplemental Agreement for work within scope PS39 $235,000
Supplemental Agreement for work within scope PS35 · The purpose of this modification is to provide all labor, material, and equipment for CE 139R1 , 192, 218, 263, 264, 310R1, and 317. $635,748
Supplemental Agreement for work within scope PS37 · The purpose of this modification is to provide all labor, materials, and equipment to complete work prescribed by "SOW-GSA phase 2 refresh telecom SOW… $75,000
Supplemental Agreement for work within scope PS34 · The purpose of this modification is to provide all labor, material, and equipment for CE 175 R1, and CE 235 the work to be performed includes: 1. Furnish and… $163,480
Other Administrative Action PA36 · The purpose of this modification is to correct the accounting string in PS32, CLIN0090 from: PN0N03282.2013.192X.11.PG80.P1140001.K01.PG413.DC0021ZZ.B5003536.… $0
Supplemental Agreement for work within scope PS32 · The purpose of this modification is to provide labor, material, and equipment for CE125, and CE272, in accordance to the scope of work summary dated april 5,… $391,674
Other Administrative Action PA33 · The purpose of this modificaiton is to correct the accounting string RWA account number: from:… $0
Supplemental Agreement for work within scope PS31 · The purpose of this modification is to incorporate settled CE's into the contract. The attached scope of work summary dated march 21, 2013, identifies various… $0
Supplemental Agreement for work within scope PS30 · The the purpose of this modification is to incorporate settled CES into the contract. The attached scope of work (SOW) summary, dated february 26, 2013,… $0
Supplemental Agreement for work within scope PS29 · The purpose of this modification is to provide labor, materials, and equipment for CE#256, CE#257, CE#258. The contractors signature in block 15B indicates… $502,027
Supplemental Agreement for work within scope PS28 · The purpose of this modification is to incorporate settled CE's into the contract. The scope of work (SOW) summary, dated february 21, 2013, identifies the… $0
Supplemental Agreement for work within scope PS27 · The purpose of this modification is to provide material, equipment, and labor to provide for CE#86 to include 1) division 27 security system (phase 1 only) as… $303,265
Supplemental Agreement for work within scope PS26 · The purpose of this modification is to provide for PC R003, removing all debris related to the demolition of the radiator covers on the 2ND, 4TH, and 6TH floors… $8,942
Supplemental Agreement for work within scope PS25 · The purpose of this modification is to provide all labor, materials, and equipment for additional IT data drops in accordance with PC R001. The contractor's… $60,166
Supplemental Agreement for work within scope PS24 · The purpose of this modification is to provide labor, material, and equipment for "refresh finishes", "refresh schedule" as prescribed by CE152. $2,945,261
Supplemental Agreement for work within scope PS23 · The purpose of modification PS23 is to incorporate settled CE's into the contract. The attached PS23 summary table lists the clin's and the associated CE's… $4,494,425
Supplemental Agreement for work within scope PS22 · Modification to definitize the scope and pricing relations to mods PS10 and PS16. $0
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

This is a $152,295,684.50 firm fixed-price definitive contract awarded by the National Capital Region (NCR) component of the General Services Administration (GSA) to the Whiting-Turner Walsh JV prime contractor. The contract is for construction services related to the "1800F Street Modernization Project" under the American Recovery and Reinvestment Act (ARRA) funding. The contract does not have a set-aside designation. The work is to be completed by May 23, 2015.

Quick answers

Who was awarded contract GS11P10MKC0025?

GS11P10MKC0025 was awarded to Whiting-Turner Walsh JV by National Capital Region (Public Buildings Service) on September 14, 2010.

How much is contract GS11P10MKC0025 worth?

The government has obligated $152,295,685 on GS11P10MKC0025.

Was contract GS11P10MKC0025 competed?

The extent of competition for GS11P10MKC0025 was full and open competition. The government received 5 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award