'''' the contractor is to provide all labor, materials, equipment, and incidentals needed for partial seismic upgrade and related improvements needed due to impact on architectural finishes, MEP…

Ended Definitive Contract Awarded Last action

Contract number
GS09P16KTC7027
Awardee
Awarding agency
Obligated
$28,668,392

Award facts

Contract value 100% obligated
$28,668,392.45 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 1 offer Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
North Richmond, CA 94801, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PS29 · X $16,821
Supplemental Agreement for work within scope PS28 $27,760
Supplemental Agreement for work within scope PS27 $19,820
Supplemental Agreement for work within scope PS26 $29,680
Supplemental Agreement for work within scope PS25 $6,660
Supplemental Agreement for work within scope PS24 $70,206
Supplemental Agreement for work within scope PS23 $29,522
Supplemental Agreement for work within scope PS22 $145,683
Supplemental Agreement for work within scope PS21 $113,761
Supplemental Agreement for work within scope PS20 · Project: partial seismic upgrade and related improvements needed at the frank hagel federal building, 1221 nevin avenue, richmond, california (RFP #40/PCO… $2,850,171
Supplemental Agreement for work within scope PS19 · This modification is to provide for the following: 1. Provide revisions to door functionality and a new drinking fountain in the basement per bulletin #6 issued… $138,384
Change Order PC18 · The contractor is authorized and hereby directed to proceed with a limited portion of the work contained in MSU/BSU build-out as outlined in the request for… $250,000
Change Order PC17 · The contractor is authorized and hereby directed to proceed with remove plates and weld dams as noted in RFI #109/apsi #107 dated january 4, 2018, RFI #… $42,637
Supplemental Agreement for work within scope PS16 · This modification is to provide for the following: 1. Core or saw cut a 12" circular/square exploratory hole approximately 4" in depth to the top of the… $17,456
Definitize Change Order PS15 · This modification is to provide for the following: 1. Definitization of PDL modification PC10 dated february 8, 2018 issued in the amount of NTE $52,000.00… $66,535
Change Order PC14 · The contractor is authorized and hereby directed to proceed with cladding panel improvements in the NW and SE mechanical shafts and the stair b, c and d… $30,000
Supplemental Agreement for work within scope PS13 · This modification is to provide for the following: 1. At the NE stair a (only) omit the top seismic connections type e, f, j, and c (total 6) detailed on… $18,200
Supplemental Agreement for work within scope PS12 · This modification is to provide for the following: 1. Lower the three (3) existing fire alarm pulls and complete installation of four (4) exit signs in the… $39,101
Supplemental Agreement for work within scope PS11 · This modification is to provide for the following: 1. Automatic door actuator for the double door #b-74C, omit the specified emergency eyewash and demo the… $37,983
Change Order PC10 · The contractor is authorized and hereby directed to proceed with remove plates and weld dams as noted in RFI #109/apsi #107 dated january 4, 2018, RFI #… $52,000
Supplemental Agreement for work within scope PS09 $81,392
Supplemental Agreement for work within scope PS08 $25,498
Supplemental Agreement for work within scope PS07 $58,419
Supplemental Agreement for work within scope PS06 · ''''this modification is being issued to provide for the following changes: 1. Additional gypboard in basement corridors in the amount of $40,708.00 as accepted… $90,628
Supplemental Agreement for work within scope PS05 · '''' this modification is being issued to provide for definitization of modification no. PC02 dated may 11, 2017 in the NTE amount of $46,000.00 to the… $114,036
Supplemental Agreement for work within scope PS04 · '''' this modification is being issued to provide for the following: 1. To change acceptable controls manufacturer from alerton to ALC as outlined in bulletin… $169,138
Supplemental Agreement for work within scope PS03 · '''' this modification is being issued to provide for additional telephone/data/electrical work as outlined in bulletin #02 dated february 17, 2017. $483,060
Change Order PC02 · '''' this PDL modification is being issued to start work on bulletin no. 04 dated may 8, 2017 in the NTE amount of $46,000.00. This work is to replace the… $46,000
Supplemental Agreement for work within scope PS01 · '''' this modification is being issued to provide for repair and replace damaged and missing sprinkler pipe hangers in basement per RFI #39 response dated april… $30,664
Original award $23,567,177
Show all 30

About this award

This is a definitive, firm-fixed-price contract awarded by the General Services Administration's Region 9 office to Stronghold Engineering Inc., a minority-owned, woman-owned business located in Perris, California. The $28,668,392.45 contract is for the partial seismic upgrade and related improvements to the Frank Hagel Federal Building in Richmond, California, including impacts to architectural finishes, mechanical/electrical/plumbing systems, and temporary swing space.

Stronghold Engineering Inc. has a history of providing construction, infrastructure, and engineering services to various federal agencies, including the Department of the Interior, Department of the Army, Department of Veterans Affairs, and Department of the Navy. This contract is not associated with a larger contract vehicle. There were no set-aside designations applied to this award.

Description

'''' the contractor is to provide all labor, materials, equipment, and incidentals needed for partial seismic upgrade and related improvements needed due to impact on architectural finishes, MEP systems and build-out swing space at the frank hagel federal building, 1221 nevin avenue, richmond, CA.

Quick answers

Who was awarded contract GS09P16KTC7027?

GS09P16KTC7027 was awarded to Stronghold Engineering Inc. by Region 9 (Public Buildings Service) on September 13, 2016.

How much is contract GS09P16KTC7027 worth?

The government has obligated $28,668,392 on GS09P16KTC7027.

Was contract GS09P16KTC7027 competed?

The extent of competition for GS09P16KTC7027 was full and open competition. The government received 1 offer.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award