Recovery act funding. Full modernization of the george c. Young federal building and courthouse (FB-CT), as part of the american recovery & reinvestment act, into a high-performance green building.
Ended Definitive Contract Awarded Last action
- Contract number
- GS04P09EXC0078
- Awardee
-
Skanska USA Building Inc. UEI HSHBF3HWNMM1
- Awarding agency
-
Region 4
Public Buildings Service, General Services Administration
- Obligated
- $48,248,358
Award facts
- Opportunity
- Contract value 100% obligated
- $48,248,358.00 Current and potential, with all options
- Completion date 100% complete
-
- Current, with exercised options
- Potential, with all options
- NAICS code
- 236220 Commercial and Institutional Building Construction
- PSC
- Z111 Maint-Rep-Alt/Office Bldgs
- Set-aside
- No set-aside
- Competition
- Full and Open Competition · 15 offers Two Step
- Pricing
- Firm Fixed Price
- Place of performance
- Orlando, FL 32801, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Other Administrative Action | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Other Administrative Action | $0 | |
| Other Administrative Action | $0 | |
| Other Administrative Action | $0 | |
| Other Administrative Action | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $24,920 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $10,081 | |
| Other Administrative Action | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $14,917 | |
| Supplemental Agreement for work within scope | $570,580 | |
| Other Administrative Action | $0 | |
| Supplemental Agreement for work within scope | -$357,000 | |
| Supplemental Agreement for work within scope | $770,591 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | -$1,326,512 | |
| Supplemental Agreement for work within scope | $246,643 | |
| Supplemental Agreement for work within scope | $692,888 | |
| Other Administrative Action | $0 | |
| Supplemental Agreement for work within scope | $101,250 | |
| Other Administrative Action | $0 | |
| Supplemental Agreement for work within scope | $12,500,000 | |
| Other Administrative Action | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Other Administrative Action | $0 | |
| Original award | $35,000,000 |
Show all 32
About this award
This is a firm fixed-price definitive contract awarded by the General Services Administration (GSA) Region 4 to Skanska USA Building Inc. for $48,248,358.00. The contract is for the full modernization of the George C. Young Federal Building and Courthouse in Orlando, Florida as part of the American Recovery and Reinvestment Act, transforming it into a high-performance green building. The contract does not have a set-aside designation and the ultimate completion date is April 29, 2013. Skanska USA Building Inc. is the prime contractor for this project.
Quick answers
Who was awarded contract GS04P09EXC0078?
GS04P09EXC0078 was awarded to Skanska USA Building Inc. by Region 4 (Public Buildings Service) on July 27, 2009.
How much is contract GS04P09EXC0078 worth?
The government has obligated $48,248,358 on GS04P09EXC0078.
Was contract GS04P09EXC0078 competed?
The extent of competition for GS04P09EXC0078 was full and open competition. The government received 15 offers.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award