- This federal contract award with ID EPS40902|EP0015 was issued by the U.S. Environmental Protection Agency (EPA) Region 4 to Black & Veatch Special Projects Corp., doing business as Black & Veatch Architects LLC. The $1,317,516.33 time-and-materials contract provides oversight and verification of the construction and implementation of the remedial action, including system start-up, diagnostic testing, and performance monitoring at the Tower Chemical Superfund Site in Clermont, Florida....
- This is a $494,918.37 cost-plus-fixed-fee delivery order awarded by the Environmental Protection Agency Region 4 to Hydrogeologic, Inc. to provide remedial design services under the EPA Remedial Acquisition Framework: Design and Engineering Services (DES) indefinite-delivery/indefinite-quantity (IDIQ) contract. The task order is for the Tower Chemical Remedial Design (RD) project in Montverde, Florida. Hydrogeologic, Inc. has over 35 years of experience providing environmental engineering,...
- This is a $3,471,977.85 federal contract awarded by the U.S. Environmental Protection Agency (EPA) Region 4 to Environmental Restoration LLC, a for-profit limited liability company based in Fenton, Missouri. The contract was awarded on September 17, 2015 and has an ultimate completion date of December 23, 2021. The contract is a delivery order under the EPA's Emergency Rapid Response Services IV (ERRS IV) Indefinite Delivery/Indefinite Quantity (IDIQ) contract vehicle. ERRS IV is a...
- The U.S. Environmental Protection Agency Region 4 awarded a $915,536 delivery order to Hydrogeologic, Inc., a minority-owned, Asian-Pacific American small business, on March 5, 2021, under the EPA Remedial Acquisition Framework Design and Engineering Services master contract. This task order provides remedial design support during remedial action activities at the LCP Chemicals Operable Unit 1 Superfund site, with an ultimate completion date of December 31, 2024. The contract utilizes...
- The U.S. Environmental Protection Agency (EPA) Region 4 awarded a delivery order to Heliotech, a subsidiary of ST George Tanaq Corp (an Alaskan Native Corporation), to perform long-term remedial action (LTRA) activities at the Sanford Dry Cleaners contaminated site in Seminole County, Florida. This award, issued on December 8, 2022, carries a ceiling value of $1.2 million and extends through July 31, 2028. The contract utilizes a time and materials pricing structure and was issued without a...
- The U.S. Army Corps of Engineers (USACE) ENDIST Jacksonville awarded a $755,164.86 firm fixed-price delivery order to Aerostar Environmental and Construction LLC for post-remedial groundwater sampling and monitoring services at the former Tower Chemical Site in Clermont, Florida. The contract, awarded on May 9, 2025, extends through May 8, 2030, and represents a task order issued under Aerostar's existing $4.5 million indefinite delivery contract with USACE ENDIST Jacksonville established in...
- This contract was awarded by the U.S. Environmental Protection Agency (EPA) Region 5 to Environmental Restoration LLC, a for-profit limited liability company, for the TARACORP INDUSTRIES SOILS SITE remediation project. The contract is a Delivery Order under the Region 4 - 6 Emergency and Rapid Response Services (ERRS V) indefinite delivery, indefinite quantity (IDIQ) contract vehicle, which enables the EPA to rapidly mobilize environmental remediation and emergency response services across...
- This is a $3,085,277.93 firm fixed-price delivery order awarded by the U.S. Environmental Protection Agency (EPA) Region 4 to the prime contractor Hydrogeologic, Inc., a minority-owned, Asian-Pacific American small business. The contract is for operation and maintenance of a soil vapor extraction system at the Velsicol OU2 - Middle Disposal Area site in Toone, Tennessee. The contract has a period of performance through July 18, 2026. Hydrogeologic has been awarded multiple federal contracts...
- The U.S. Environmental Protection Agency (EPA) Region 4 awarded a $873,691.26 firm fixed-price contract to Polu KAI Services LLC for Underground Injection Control (UIC) field inspections, with performance in Atlanta, Georgia. The contract, awarded January 1, 2013, and completed December 31, 2017, was set aside as an 8(a) sole source award to the service-disabled veteran-owned small business. Polu KAI Services LLC, headquartered in Falls Church, Virginia, holds both SBA Certified Veteran-Owned...
- This is a delivery order contract awarded by the U.S. Army Corps of Engineers to the Northwind-Jacobs Joint Venture for environmental remediation services at the Tower Chemical EPA Superfund site in Clermont, Florida. The $19,905,916.51 firm fixed-price contract has a completion date of November 2, 2026. It was awarded on November 3, 2022 and is a task order under the SAD Regional Environmental Contracts 2018-2022 multiple-award IDIQ contract vehicle. Northwind-Jacobs Joint Venture is a small...
This is a $4,197,177.00 firm fixed price contract awarded by the U.S. Environmental Protection Agency (EPA) Region 4 to Polu KAI Services LLC, a minority-owned, small disadvantaged, veteran-owned limited liability company, for soil remediation services including excavation, transportation, and disposal of contaminated soils at the Tower Chemical Site in Clermont, Florida. The contract was awarded on October 28, 2009 under the American Recovery and Reinvestment Act (ARRA) and has an ultimate completion date of October 31, 2011. The contract was competed as a Competitive 8(a) set-aside. Polu KAI Services has been awarded over 50 prime federal contracts and delivery orders, as well as several indefinite-delivery/indefinite-quantity (IDIQ) contract vehicles with various federal agencies for construction, design-build, and facilities support services.
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
RECOVERY ACT - Soil Remedial Action, Operable Unit 3, Tower Chemical Site | PR-R4-09-10141 | Environmental Protection Agency Region 4 | Award Notice 1/1 | 5/11/09, 11:16 AM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| 18 | Additional Work (new agreement, FAR part 6 applies) | $379.8k | 9/3/10 | |
| 19 | Definitize Change Order | $31.2k | 9/3/10 | |
| 17 | Other Administrative Action | $162.8k | 8/20/10 | |
| 16 | Other Administrative Action | $0 | 8/16/10 | |
| 15 | Other Administrative Action | $162.8k | 8/11/10 |