Definitive Contract DTFH7014C00002

Award Date 11/14/13
Potential Completion Date 8/31/15
Potential Value $1.1M
Ultimate Awardee
Not listed
Federal Contract Vehicle
Set-Aside Type
Total Small Business
Extent Competed
Full and Open Competition after exclusion of sources
Major Defense Program
Not listed
Pricing Type
Firm Fixed Price
Place of Performance
Montesano, WA 98563, USA
Solicitation Procedures
Sealed Bid
Number Of Offers Received
12
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed
Research Type
Not listed
Primary Consortia Member
Not listed
Similar Awards
This definitive contract, awarded by the Department of Transportation Federal Highway Administration, is for the WY FLAP CR CN10-277(1) Wiggins Creek Bridge project in Jeffrey City, Wyoming. Earth Work Solutions (Wy) will serve as the prime contractor on this partially small business set aside contract valued at $4,029,960.00 to remove an existing one-lane bridge and construct a new modular steel vehicular bridge. Work will include cofferdams, structural concrete, reinforcing steel, bridge...
The U.S. Federal Highway Administration (FHWA) awarded a $15,211,544.21 firm-fixed-price contract to Steve Manning Construction Inc., a certified HUBZone small disadvantaged business based in Redding, California. The contract is for the WY FLAP NAT 505 & BL 6409(1) CASPER MTN CIR DR & MUDDY MTN RD 3R CONSTRUCTION IMPROVEMENTS project, which involves minor widening/reconstruction and resurfacing, restoration, and rehabilitation work on approximately 12 miles of roads in Natrona County,...
This is a $3,499,705.45 definitive, firm-fixed-price contract awarded by the Federal Highway Administration, a civilian agency, to Avail Valley Construction-Wy LLC for the WY FLAP 30400(2) Gros Ventre Road road construction project in Wyoming. The contract is a follow-on after an initial termination for default and has an ultimate completion date of September 29, 2023. There is no set-aside designation for this contract. The original solicitation was for 3.8 miles of pulverization and paving...
The Department of Transportation Federal Highway Administration awarded a $30,000 delivery order contract to Oftedal Construction, Inc. for road construction services in Yellowstone National Park, Wyoming. Under the contract, Oftedal Construction will complete Phase 3 of the Norris to Golden Gate road project in Yellowstone National Park between January 29, 2021 and April 15, 2021. As a firm fixed price contract, Oftedal Construction will provide road construction services for a set price. The...
<p>This is a $291,656.00 firm-fixed-price delivery order awarded by the U.S. Department of the Interior (DOI) Fish and Wildlife Service to C3 Limited Liability Company. The contract is for the WORLAND SECURITY FENCE AND PARKING LOT project under the RECOVERY TAS::14 1112::TAS PROJECT NUMBER LDDFR0180000. The contract does not have a set-aside designation. The place of performance is Worland, Wyoming. The contract was awarded on June 7, 2010 with a completion date of July 29, 2010.</p>
<p>The Department of Transportation Federal Highway Administration awarded a $3,444,057.07 definitive contract to Triple A Building Services, Inc. as an 8(a) sole source small business concern. The firm fixed price contract is for construction services relating to CONSTRUCTION CONTRACT FOR WY FLAP CR CN10-285(1) HORSE CREEK ROAD FREMONT COUNTY. The place of performance will be Dubois, Wyoming, with work expected to be completed between April 5, 2023 and October 6, 2023.</p>
<p>The Department of Transportation Federal Highway Administration awarded a $14,381,587.74 firm fixed price definitive contract to W.W. Clyde &amp; CO., a for-profit organization, for the WY FLAP SR71(4), Sage Creek Highway Paving Project. The contract, which does not have a set-aside designation, was awarded on February 13, 2018, with a completion date of November 30, 2018. The project will be performed in Rawlins, Wyoming.</p>
This federal contract was awarded by the Department of Transportation Federal Highway Administration to Mountain Construction Company for the WY FLAP 6WX(1) SOUTHFORK ROAD project. The contract is a Definitive Contract with a Firm Fixed Price pricing type and a potential value of $12,940,009.69. The contract does not have a set-aside designation, and the place of performance is Cody, Wyoming. The contract has a completion date of September 18, 2020 and was awarded on April 15, 2019. The major...
This is a firm fixed price delivery order contract awarded by the Federal Highway Administration, a civilian agency within the U.S. Department of Transportation, to Oftedal Construction, Inc. as the prime contractor. The contract is for the Moose Wilson Road Phase 1 project in Grand Teton National Park, Wyoming, with a ceiling value of $17,115,377.20 and a completion date of August 28, 2023. This contract is not associated with a set-aside program. Oftedal Construction, Inc. has previously...
The Federal Highway Administration awarded a firm-fixed-price definitive contract worth $1,090,125.00 to Battle Ridge Builders, LLC, a small business, to replace the North Fork Crazy Woman Creek Bridge in Buffalo, Wyoming. The contract is part of the Federal Lands Access Program (FLAP) project WY FLAP JOH 14(1) to reconstruct the bridge and roadway approaches. Key work includes bridge removal, placement of structural concrete and prefabricated steel bridge, and construction of micropile...

WA PFH 203(3), WYNOOCHEE ROAD, PHASE III

Posted 11/14/13, 12:00 AM