Definitive Contract AG82B1C100077
Award Date 1/19/10
Potential Completion Date 9/30/10
Potential Value $652K
Federal Agency
Ultimate Awardee
Not listed NAICS Category
PSC Category
Federal Contract Vehicle
- Not listed
Set-Aside Type
HUBZone
Extent Competed
Full and Open Competition after exclusion of sources
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
McCall, ID 83638, USA
Solicitation Procedures
Sealed Bid
Number Of Offers Received
5
Legislative Mandate
Economy Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- <p>This is a federal contract award from the Operations Center Intermountain, a civilian agency, to Seubert Excavators, Inc., a for-profit organization. The contract, valued at $113,696.00, is for TAS::12 1102::TAS--MANN CREEK GRAVEL and is a definitive, firm-fixed price contract. The contract has a HUBZone set-aside designation and a completion date of April 28, 2011. Seubert Excavators, Inc. is the prime contractor, and the place of performance is McCall, ID 83638, USA.</p>
- <p>This is a $195,473.43 firm fixed price definitive contract awarded by the Operations Center Northwest, a civilian federal agency, to Thayer Excavating, LLC, a for-profit Subchapter S corporation. The contract is for the reconditioning of Forest Service Road 7400, including reconditioning the roadbed, purchasing and processing crushed rock, and constructing drain dips. The contract has a HUBZone set-aside designation and a completion date of December 21, 2010.</p>
- This is a federal contract awarded by the Operations Center Intermountain, a civilian agency, to Seubert Excavators, Inc., a for-profit organization. The contract, valued at $289,241.00, is a firm fixed-price definitive contract for the Lochsa Aggregate Stockpile (Jungle Point Crushing) project under ARRA-FS-CIM-0105-24R. The contract has a set-aside designation for HUBZone businesses and a completion date of July 11, 2011. No additional information about subcontractors or the agency's...
- <p>This is a $253,196.00 firm fixed price definitive contract awarded by the Intermountain Operations Center, a civilian federal agency, to Seubert Excavators, Inc. on March 15, 2010. The contract is for the Palouse River Road Aggregate Resurface Project, an American Recovery and Reinvestment Act (ARRA) project, and has an ultimate completion date of September 12, 2010. The contract is not designated as a set-aside. The work is to be performed in Harvard, ID.</p>
- This is a Definitive Contract awarded by the U.S. Department of Agriculture Forest Service to Granite Excavation, Inc., a large commercial excavation contractor, for the South Fork Salmon River Road Chip Seal Project. The $1,038,262.09 firm fixed-price contract has a completion date of September 23, 2011 and is set aside for HUBZone small businesses. Granite Excavation has provided similar heavy construction services, including road, bridge, and trail infrastructure work, to the Forest Service...
- This is a firm-fixed-price definitive contract awarded by the Operations Center Intermountain, a civilian agency, to 4 Lee's Excavation, a veteran-owned small business. The contract, with a ceiling value of $251,747.23, is for the Beaver Creek Roads project (Task Area Symbol 1102) and has a HUBZone set-aside designation. The contract was awarded on January 14, 2010, with a completion date of September 30, 2010. No additional details about potential larger contract vehicles or subcontractors were...
- This is a definitive contract awarded by the Operations Center Intermountain, a civilian agency, to Boulder Creek Engineering And Bridge Company, PC, a small business. The contract was awarded on April 16, 2010 with a ceiling value of $44,500.00 and a firm fixed price pricing type. The contract is for the provision of TAS::12 1102::TAS GOOSE LAKE ROAD CATTLEGUARDS, with a final completion date of June 1, 2010. The place of performance is McCall, ID 83638, USA. This contract does not appear to be...
- This is a $160,517.16 firm fixed-price definitive contract awarded by the U.S. Department of Agriculture Forest Service to Granite Excavation, Inc., a large commercial and municipal excavating contractor. The contract is for the Recovery Rosebud Culvert Replacements project, which involves capital improvement and maintenance work. The contract was awarded on March 2, 2010, with a completion date of November 21, 2012. No set-aside was used. Granite Excavation has previously performed heavy...
- <p>This is a $102,632.96 firm fixed price definitive contract awarded by the Operations Center Northwest, a civilian federal agency, to Weber Construction, Inc. for roadway excavation and embankment on the Evergreen Road. The work is part of the agency's TAS RECOVERY EVERGREEN ROAD REPAIR AND MAINTENANCE program and does not have a set-aside designation. The contract was awarded on March 16, 2010 with an ultimate completion date of October 31, 2010.</p>
- This is a definitive contract awarded by the U.S. Department of Agriculture's Operations Center Intermountain to Granite Excavation, Inc., a small business contractor, for a TAS::12 1102::TAS BLUE SPRINGS BOX CULVERT project in McCall, Idaho. The $57,306.94 firm-fixed-price contract was awarded on August 19, 2009, with a completion date of July 7, 2011. Granite Excavation has previously performed prime and subcontractor heavy construction services for the Department of Agriculture Forest Service...
This is a $652,457.16 firm-fixed-price definitive contract awarded by the U.S. Department of Agriculture's Operations Center Intermountain to Seubert Excavators, Inc., a HUBZone company, for the TAS: 12 1102 Goose Lake Road Surface Rock Replacement project. The contract was awarded on January 19, 2010 with a completion date of September 30, 2010. As this is a civilian agency contract, it is not associated with a larger contract vehicle.
Generated 4/2/25, 9:53 AM
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
RECOVERY** Goose Lake Road Surface Rock Replacement - Payette NF | AG-82B1-S-10-0058 | Department of Agriculture Forest Service Washington Office Economic Recovery Operations Center Intermountain | Award Notice 1/1 | 11/23/09, 9:09 PM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| 2 | Close Out | $4.0k | 8/5/10 | |
| 1 | Other Administrative Action | $0 | 7/30/10 | |
| Not listed | Not listed | $648.4k | 1/19/10 |